MELC-211 · Lesson 12 of 12 · 31 min
Readiness review: a practice test for new contractors
▶ Video coming soon A video version of this lesson is on the way.
Yukon has no published master electrician or contractor exam, so this lesson is not about test-day tactics. It is about readiness: a final review of the whole course, a practice test that covers each lesson, and a plan for the first year of Tagish Lake Electric. If you can answer the questions here without looking back, you know the Yukon system well enough to run a licensed electrical contracting business in it.
How to use this lesson
Work through the review in three passes. First, read the summary map below and mark any area that feels unfamiliar. Second, do the practice set without notes and score yourself. Third, go back to the lessons behind any question you missed. Rena does this the week before Tagish Lake Electric files its licence application, and again after its first six months.
The system in ten facts
| Fact | Source | Lesson |
|---|---|---|
| Electrical licensing rests on the Electrical Protection Act and Regulation | Act and O.I.C. 1992/017 | 1 |
| The chief inspector receives licence applications | Reg. s.4(2) | 3 |
| A qualified accredited representative is needed if the applicant lacks the qualifications | Reg. s.4(4) | 2 |
| The licence bond is 1,000 dollars | Reg. s.4(3) | 3 |
| Licences run for one year | Reg. s.4(8) | 11 |
| Declaration authority needs 12 months of active Yukon contracting | Reg. s.5(6) | 4 |
| The 2024 Code took effect on April 1, 2025 | Bulletin 25-01 | 5 |
| Inspection requests need 72 business hours' notice | Permit page | 6 |
| Serious incidents are reported to the WSCB immediately | WSC Act s.57 | 10 |
| Employers give written injury notice within 3 days | WSC Act s.89 | 10 |
Calculations you should be able to do
Three kinds of calculation come up in Yukon licensing work, and all three are short. Permit fees by bracket. Dates: licence expiry, annual permit expiry, and the 3-day injury notice. And special inspection charges at 50 dollars an hour plus travel. The script below runs one of each; try them by hand first.
import math
from datetime import date
def permit_fee(v):
if v <= 500: return 25.00
if v <= 1000: return 25.00 + 2.50 * math.ceil((v - 500) / 100)
if v <= 3000: return 37.50 + 3.00 * math.ceil((v - 1000) / 100)
if v <= 10000: return 97.50 + 1.50 * math.ceil((v - 3000) / 100)
if v <= 50000: return 202.50 + 1.00 * math.ceil((v - 10000) / 100)
return None # larger brackets not needed here
print("Fee for 7,400:", permit_fee(7400))
print("Fee for 7,400 started without a permit:", 2 * permit_fee(7400))
issued = date(2027, 11, 2)
print("Annual permit expiry:", date(issued.year + (issued.month >= 10), 12, 31))
hours = 3.5
print("Special inspection time charge:", hours * 50, "plus travel")Fee for 7,400: 163.5 Fee for 7,400 started without a permit: 327.0 Annual permit expiry: 2028-12-31 Special inspection time charge: 175.0 plus travel
Scenarios
Worked problem
The basement suite
A Whistle Bend homeowner has started wiring a basement suite to rent out. He holds an owner permit and wants Tagish Lake Electric to check his work and sign off. What is the problem, and what can Rena offer?
Show solution
- The government's permit page says work on any rental unit requires a contractor.
- Section 15 also limits owner permits to premises the owner occupies as a dwelling, so a rental suite raises the same issue.
- Rena cannot sign off someone else's work as her own; she can take a permit in the company's name and complete the work to the Code, opening up what she cannot verify.
- If the owner permit is cancelled, s.15(2) requires the owner to hire a licensed contractor or have the installation disconnected or removed.
Answer: The suite needs a contractor; Rena can take her own permit and complete the work, but she cannot vouch for unseen work.
Worked problem
The Carcross cabin in January
Tagish Lake Electric is wiring a new cabin near Carcross. The builder wants the insulation and boards up before a cold snap. Rena requested the rough-in inspection two business days ago and the company does not yet have declaration authority. What should she do?
Show solution
- Inspection requests need at least 72 business hours' notice, so the inspection may not be due yet.
- Without declaration authority, the company cannot declare the rough-in and receive a cover-up date.
- Section 5(7) prohibits concealing the work before approval, and the authority can order it opened.
- She tells the builder the wiring stays open until approval, gives the office clear directions to avoid a special inspection charge, and protects the site from the cold in the meantime.
Answer: Keep the work open until approval and make the inspection easy to reach.
Your first-year plan
Readiness is also a plan. Rena's first-year plan for Tagish Lake Electric has five lines:
- Licence, bond, insurance, WSCB registration and City business licence in place before the first job.
- Every job permitted, every stage inspected, nothing covered early, final operational checks before every final.
- A monthly routine: account reconciled, bulletins checked, records filed.
- A safety program that fits in the truck, with a remote-site plan and immediate reporting steps.
- At 12 months, a review of the year and an application for declaration authority if the record supports it.
What we could not confirm
An honest readiness review includes the gaps. When this course was prepared, we could not confirm from official sources: the full list of licence classes and the qualifications in section 13(3) of the Act; the current licence fee and processing time; whether the office sets any written test for a contractor licence; the Builders Lien Act's current holdback and deadlines; the transition rules in Bulletin 25-01; and the safety committee thresholds. Each is a question for the office, the WSCB or a lawyer before you rely on it. Making that list is itself a contractor skill.
A second practice set
Here is a second set of questions to test yourself. Try each without looking back, then check the answer and the lesson it comes from.
Practice problems
Work each problem on paper first, then reveal the answer to check.
Which section of the regulation sets the conditions for owner permits?
Show answer
Section 15 (Lesson 6).
What voltage, phase and current limits apply to an owner permit?
Show answer
No more than 150 volts to ground, single phase and 200 amperes (Lesson 6).
How long is a temporary connection permit valid, and how many renewals are allowed?
Show answer
90 days, renewable once for 90 days at the inspector's discretion (Lesson 6).
What fee applies to a re-inspection under the schedule?
Show answer
25 dollars per building (Lesson 6).
What must appear in a contractor's advertising?
Show answer
The licence class and licence number (Lessons 2 and 7).
What must a homeowner do if an owner permit is cancelled?
Show answer
Hire a licensed contractor to complete the work, or have the installation disconnected or removed (Lesson 6).
What does Bulletin 25-04 require for outdoor EV equipment?
Show answer
Among other things, mechanical protection where it could be struck, and a rating for minus 40 degrees (Lessons 5 and 11).
What must happen to the inspection approval number and cover-up date for declared work?
Show answer
They must be posted at the site (Lesson 4).
Scenario: the new partner
Worked problem
A partner with a different trade
Jonas wants to bring in a friend who is a refrigeration mechanic as a third shareholder. The friend would like to do heat pump installations under Tagish Lake Electric's name, including the electrical connections. What licensing questions arise?
Show solution
- The company's licence class and accredited representative stay the same; adding a shareholder does not by itself change who the licence relies on.
- Electrical connections are electrical work and must be done under the company's permits by people allowed to do them, supervised as the rules require.
- Electric heat in a listed diesel community needs the utility's permission, so heat pumps sold in those places need care.
- Load calculations may be needed for the service, and the permit fee is based on the value of the electrical work.
- The company should ask the office whether any change needs to be reported, and check whether the friend's own trade has separate licensing rules.
Answer: A new shareholder does not change the licence, but electrical connections stay under the company's permits and supervision rules.
Scenario: the hotel maintenance contract
Worked problem
An annual permit in practice
A Whitehorse hotel offers Tagish Lake Electric a maintenance contract starting on October 12, 2027. The manager asks whether the crew can make small changes without a permit each time. What should Rena explain?
Show solution
- An annual permit under s.11 covers minor alterations in one building for the permit year; one permit is needed for each independent building.
- Because it would be issued after October 1, it would run to December 31, 2028.
- The application names the electrician or contractor who will perform or supervise the work; if Tagish Lake Electric stops working there, the permit ends.
- Every alteration, repair and addition must go in a written log, kept and produced on request.
- The fee is 50 dollars per building under the schedule.
Answer: Yes, with an annual permit naming the company, a log of every change, and an expiry of December 31, 2028.
Final checklist
Before you take your first permit, check that you can say yes to each of these:
- I have read the Electrical Protection Regulation and can find sections 4, 5, 11, 14, 15 and 18.
- I know which licence class my company holds and who its accredited representative is.
- I can calculate a permit fee and know when it doubles.
- I know how much notice an inspection needs and what information a remote request should include.
- I know the Yukon bulletins that affect my common jobs, and where to find new ones.
- I have insurance, WSCB registration and a municipal business licence where needed.
- I know where to read Yukon's Builders Lien Act and when to call a lawyer.
- I know the immediate and written reporting rules for injuries, and that electrical accidents also go to the chief electrical inspector.
- I have a renewal calendar and a records system.
If any answer is no, go back to the lesson. If all are yes, you are ready.
The last word goes to Bill. He tells Rena that passing this review does not mean she knows everything. It means she knows what she knows, what she does not, and where to look. In a territory where the nearest colleague may be hours away, that is the skill that keeps a contractor safe and in business.
Rena files the checklist in the licence folder, books a call with the office to ask her list of unconfirmed questions, and sends the application. Tagish Lake Electric's first permit is three weeks away, and when it arrives, every system in this course will already be in place to support it.
If you are preparing your own business, copy that approach. Make your own list of unconfirmed points, call the office with it, and write down the answers with the date and the name of the person you spoke to.
Then go back through the four quadrants of the course map one more time, and for each one name the single habit you will build first. Those four habits are your own first-year plan.
Common mistakes
MistakeTreating the lack of a master exam as a lack of standards.
InsteadCompetence is checked at the certificate, the licence review, declaration authority and every inspection.
MistakeMemorizing fee brackets without practising the calculation.
InsteadWork the bracket, round each part 100 up, and double for late permits.
MistakeRelying on this course for numbers we flagged as unconfirmed.
InsteadConfirm them with the office, the WSCB or a lawyer.
MistakeSkipping the review after the first six months.
InsteadThe first months show where your systems are weak; review and fix them.
Summary and key terms
- Yukon has no published master or contractor exam; readiness means knowing the system and running it well.
- Know the ten core facts: Act and regulation, chief inspector, accredited representative, bond, term, declaration authority, Code date, notice, and the two WSCB reporting rules.
- Practise fee, date and special inspection calculations.
- Work through scenarios on owner permits, rental units, concealment and remote inspections.
- Keep a list of what you have not confirmed, and ask before relying on it.
- Readiness review
- A structured check that you know the material, done before licensing and again after six months.
- First-year plan
- The short list of systems a new contractor puts in place in its first year.
- Unconfirmed item
- A point this course could not verify from an official source.
- Rental unit rule
- The rule on the permit page that work on any rental unit needs a contractor.
- Concealment
- Covering electrical work, prohibited before approval under s.5(7).
Practice problems
Work each problem on paper first, then reveal the answer to check.
What is the permit fee for a 7,400 dollar installation?
Show answer
97.50 plus 1.50 for each 100 over 3,000: 44 hundreds, so 97.50 plus 66.00 equals 163.50 dollars.
And if work started before the permit?
Show answer
Double: 327.00 dollars.
An annual permit is issued on November 2, 2027. When does it expire?
Show answer
December 31, 2028.
A special inspection takes 3.5 hours. What is the time charge?
Show answer
175 dollars, plus travel expenses.
Lesson quiz · 5 questions
Score 60% or more to complete this lesson.
Create a free account to save your progress, take quizzes and earn a certificate.