HSE-217 · Lesson 7 of 12 · 29 min

Shoring and shielding

Where there is no room to slope, or the soil is too weak for a practical slope, the walls must be supported or the workers must be shielded. Shoring holds the walls in place so they cannot move. Shielding accepts that the walls might move and puts a strong box around the workers so that soil cannot reach them. Both work only when the right system is chosen for the soil and depth, installed exactly as designed, and kept in use for the whole time anyone is in the trench.

Shoring versus shielding

The difference matters because it decides what the system protects and how it must be used:

  • Shoring is an active support. Struts, wales, sheathing or hydraulic cylinders press against the walls and resist the earth pressure. Properly installed shoring prevents the walls from moving, which also protects nearby pavement, utilities and foundations.
  • Shielding is a passive protective structure. A trench box or shield is placed in the trench, and workers stay inside it. The walls may still slough or collapse against the outside of the box, but the box resists the load and keeps the workers' space open. Shields do not protect adjacent structures from settlement.

Workers inside a shield are protected only while they stay inside it. The most common way shields fail to protect people is not structural failure but workers stepping out of the end of the box to guide a pipe, check a grade or retrieve a tool.

Timber shoring

Timber shoring uses vertical sheathing or uprights against the walls, horizontal wales and cross braces between them. OSHA Appendix C to Subpart P gives timber shoring tables for trenches up to 20 ft deep in Type A, B and C soils, specifying the size and spacing of cross braces, wales and uprights by depth and trench width. The tables assume specific wood species and grades, and the minimum sizes and maximum spacings must not be relaxed. Timber shoring is labor-intensive and now less common than hydraulic and box systems, but it remains useful for irregular excavations and where prefabricated systems cannot fit.

Worked problem

Planning cross braces from spacing limits

A trench 9 ft deep and 40 ft long is to be shored with timber cross braces. The applicable Appendix C table limits horizontal brace spacing to 6 ft and vertical spacing to 4 ft for this soil and depth (check the actual table for your conditions). How many brace positions are needed on each level, and roughly how many levels?

Show solution
  1. Horizontal: \( 40 / 6 \approx 6.7 \), so 7 bays and 8 brace positions along the trench.
  2. Vertical: with braces no more than 4 ft apart, a 9 ft wall needs at least three levels.
  3. Total cross braces: about \( 8 \times 3 = 24 \).
  4. Uprights and wales must also meet the table's sizes and spacings.

Answer: Eight positions per level and three levels, about 24 cross braces.

Hydraulic and mechanical shoring

Hydraulic shores are aluminum or steel cylinders with rails or sheeting that are lowered into the trench and pumped against the walls from above, so workers never have to enter an unprotected trench to install them. OSHA Appendix D gives tables for aluminum hydraulic shoring in Type A, B and C soils; otherwise, manufacturer's tabulated data apply. The tabulated data must be in writing, approved by a registered professional engineer, and a copy kept at the jobsite while the system is in use.

Hydraulic shoring is quick to install and remove and pre-loads the soil, which reduces wall movement. Its weak points are human: cylinders spaced too far apart, sheeting omitted in soils that need it, shores installed at an angle, and hydraulic pressure that bleeds off without anyone checking. Shores should be installed and removed from the top of the trench using the manufacturer's tools, with the pressure checked at each inspection.

Cross-section and plan of a trench supported by hydraulic shores. Vertical rails press sheathing against each wall, and horizontal hydraulic cylinders span between the rails at regular vertical and horizontal spacing. An installer on the surface lowers the next shore with a pole tool.
Hydraulic shoring is installed from the surface and pumped against the walls at the spacing the tabulated data require.

Trench boxes and shields

A trench box is a pair of steel or aluminum side panels held apart by spreaders. It is lowered into the trench by the excavator, and workers enter only once it is in place. Boxes come in many sizes and can be stacked for deeper trenches. Slide rail systems, where panels slide down vertical posts as the excavation proceeds, are a hybrid that provides some shoring action in large or deep excavations.

Every box is designed for specific conditions. The manufacturer's tabulated data state the maximum depth for each soil type, how boxes may be stacked, the spreader lengths allowed, and how the box must be used. A box rated for 15 ft in Type B soil may only be good for 10 ft in Type C. OSHA 1926.652(g) requires shields to be installed so as to restrict lateral or other hazardous movement, forbids workers from being in the shield while it is installed, removed or moved vertically, and allows excavation up to 2 ft below the bottom of a shield only if the shield is designed for the full depth and there is no indication of soil loss from behind or below it.

Cross-section of a trench shield in a trench. The bottom of the shield is no more than 2 ft above the trench floor. The gap between the shield and the trench walls is kept small or backfilled. A worker stands inside the shield, and a ladder inside the shield extends 3 ft above the top. A label notes that workers must stay inside the shield.
Key points for a trench shield: rated for the soil and depth, no more than 2 ft above the floor, gaps controlled, and workers inside.

Worked problem

Is the box rated for this trench?

A shield's tabulated data express its capacity as an allowable lateral pressure of 800 psf on the panels. The manufacturer uses equivalent fluid pressures of 45 psf per foot of depth for Type B soil and 80 psf per foot for Type C-80 soil. What is the maximum depth for each soil, and can the shield be used in a 12 ft trench in Type C soil?

Show solution
  1. Type B: \( 800 / 45 \approx 17.8 \) ft.
  2. Type C-80: \( 800 / 80 = 10 \) ft.
  3. The trench is 12 ft deep in Type C soil, deeper than the 10 ft rating.
  4. The shield cannot be used alone. Options include a heavier shield, an engineered system, or a combination approved in the tabulated data.

Answer: About 17.8 ft in Type B and 10 ft in Type C; it is not rated for a 12 ft trench in Type C soil.

These pressure figures are illustrative; real ratings come only from the manufacturer's tabulated data for the specific box, and some manufacturers state depth ratings directly rather than pressures.

Using a box correctly

  • Check the box before use: welds, pins, collars, spreaders and the data plate showing the manufacturer and model. A bent panel or a missing pin can halve its strength.
  • Use only spreaders, pins and stacking arrangements allowed by the tabulated data. Homemade spreaders and mismatched boxes are a common cause of failure.
  • Dig the trench and set the box in stages, pushing it down as the excavation deepens, so that nobody is ever in an unprotected section.
  • Keep the gap between the box and the trench wall small, and backfill it if the data require, so that a collapsing wall cannot gain momentum or tip the box.
  • Keep workers inside the box. Laying pipe at the end of the box is safe only if the pipe end is still within the box or the end is protected by an end shield or sloped.
  • Provide a ladder inside the box, and make sure workers can get out without leaving its protection.
  • Move the box only when nobody is inside it, and never ride a box as it is dragged or lifted.

Worked problem

The gap between box and wall

A shield with an outside width of 5 ft is placed in a trench dug 7 ft wide. What is the gap on each side, and why does it matter?

Show solution
  1. Gap on each side: \( (7 - 5) / 2 = 1 \) ft.
  2. If a wall slides, soil travels a foot and strikes the shield with momentum rather than resting against it.
  3. An uneven gap can let a collapse on one side push the shield sideways.
  4. Backfilling the gaps, or digging the trench closer to the shield width, reduces both effects, as 1926.652(g) requires the shield to restrict lateral movement.

Answer: 1 ft on each side; it should be minimized or backfilled.

Installation and removal

OSHA 1926.652(e) requires support members to be securely connected, installed in a way that protects workers from cave-ins and structural collapse, and never subjected to loads beyond their design. Installation proceeds from the top down as the excavation deepens, and removal from the bottom up, with backfill following removal closely. Removal is often more dangerous than installation, because the trench has been open for a long time, the soil may have relaxed, and crews are in a hurry to finish. Workers must never enter an unprotected section of trench to install or remove a system.

Engineered systems

Excavations 20 ft or deeper, excavations next to structures, and any system outside Appendices C and D or a manufacturer's tabulated data need a registered professional engineer's design. Engineered systems include sheet piling, soldier piles and lagging, secant piles and braced or anchored walls. The design must be in writing, identify the engineer, and be kept at the jobsite. Any change in conditions, such as a different soil, more depth or a nearby surcharge, sends the design back to the engineer.

Comparison of protective systems.
SystemHow it worksTypical useKey limits
Sloping or benchingRemoves the soil that could slideOpen sites with room and good soilSpace, soil type, volume
Timber shoringStruts and wales hold sheathing against wallsIrregular trenches, small jobsTable limits; labor; no hydrostatic pressure
Hydraulic shoringCylinders pre-load rails or sheeting against wallsUtility trenches of moderate depthSpacing and pressure must be maintained
Trench box or shieldProtects workers if walls movePipe laying in long trenchesWorkers must stay inside; rated depth by soil
Slide railPanels slide down posts as digging proceedsLarge, deep or long-duration excavationsEngineered; skilled installation
Engineered wall systemsPiles, lagging, anchors or bracesDeep or congested sites, near structuresDesign, monitoring, cost

Choosing between systems

The choice between sloping, shoring and shielding is usually made by weighing soil, depth, space, duration, nearby structures and cost. Long pipe runs in open country often favor sloping or trench boxes; urban utility work beside buildings favors shoring that prevents ground movement; very deep or wet excavations need engineered systems from the start. Whatever is chosen, it should be decided before digging, with the equipment on site and inspected, rather than improvised once the trench is already open.

Common mistakes

  • MistakeLaying pipe beyond the end of the trench box.

    InsteadKeep the work and the workers inside the box, or protect the open end.

  • MistakeUsing a box in soil or depth beyond its tabulated data.

    InsteadCheck the data plate and tabulated data for the actual soil and depth before use.

  • MistakeEntering the unsupported part of a trench to install the next shore.

    InsteadInstall hydraulic shores from the surface and timber from the top down, never from unprotected ground.

  • MistakeReplacing a lost spreader with a homemade one.

    InsteadUse only components specified in the manufacturer's data.

  • MistakePulling all the shoring before starting to backfill.

    InsteadRemove supports from the bottom up with backfill following closely.

Summary and key terms

  • Shoring prevents wall movement; shielding protects workers if walls move.
  • OSHA Appendices C and D give timber and aluminum hydraulic shoring tables.
  • Hydraulic shores are installed from the surface and must keep their pressure and spacing.
  • Trench boxes are rated by soil type and depth in the tabulated data.
  • Shields may sit up to 2 ft above the floor only if designed for full depth; workers stay inside.
  • Install from the top down and remove from the bottom up.
  • Deep, wide or unusual excavations need an engineered design kept on site.
Shoring
A structure that supports the sides of an excavation and prevents movement.
Shield
A structure that withstands cave-in forces and protects workers inside it, also called a trench box.
Sheathing
Boards or panels placed against the excavation wall to retain soil.
Wale
A horizontal member that distributes the load from struts along the sheathing.
Strut
A horizontal compression member spanning the trench between wales or rails.
Spreader
A member that holds the two sides of a trench box apart.
Equivalent fluid pressure
A simplified way of expressing lateral earth pressure as increasing with depth like a fluid.
Slide rail system
A shoring system in which panels slide down vertical posts as excavation proceeds.
Hydrostatic pressure
Pressure from groundwater acting on a wall or support system.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. What is the difference between shoring and shielding?

    Show answer

    Shoring prevents wall movement; shielding protects workers if the walls move.

  2. Where must tabulated data for a shoring system be kept?

    Show answer

    In writing at the jobsite while the system is in use.

  3. Why are hydraulic shores installed from the surface?

    Show answer

    So workers never enter an unprotected trench to install them.

  4. How far may a trench shield be above the trench floor?

    Show answer

    Up to 2 ft, if designed for the full depth and no soil is lost from behind or below.

  5. A shield is rated for 900 psf and soil exerts 45 psf per foot. What is the maximum depth?

    Show answer

    20 ft.

  6. Why should gaps between a box and the trench wall be backfilled?

    Show answer

    To stop collapsing soil gaining momentum or pushing the box sideways.

  7. In what order are supports installed and removed?

    Show answer

    Installed top down, removed bottom up.

  8. Name two components that should be checked on a trench box before use.

    Show answer

    Panels, welds, pins, collars, spreaders and the data plate.

  9. When does a system need an engineer's design?

    Show answer

    Excavations 20 ft or deeper, or any system outside the appendices or tabulated data.

  10. What is the most common way shields fail to protect workers?

    Show answer

    Workers step outside the protected area.

Lesson quiz · 5 questions

Score 60% or more to complete this lesson.

Take the quiz