In late October, Farah and Daniel Okoye called Bayline about the furnace in their 1958 one-and-a-half-storey house on Dunsmure Road in Crown Point. It was a 1999 mid-efficiency furnace with an input of 29.3 kW, and on its last service the technician had found heavy rust on the burners and flaking scale inside the heat exchanger openings. It still ran, but it was 27 years old. Their water heater, an atmospheric 151-litre tank from 2012, shared the house's masonry chimney with it. The Okoyes wanted a quote for a new furnace. This case study follows the job from that call to the start-up sheets on Tuesday, November 10, and shows how the decisions in this course fit together.

The first visit

Hank Morrow made the estimating visit himself, with Jonah along to learn how it is done. Before talking about equipment, Hank measured the house: room dimensions, window and door sizes, wall and attic insulation where he could see it, and the basement walls. Back at the office he ran a room-by-room heat loss calculation to CSA F280. The result was a design heat loss of 12.9 kW at Hamilton's winter design temperature, far below the old furnace's output. The house had been insulated and re-windowed since 1999, and the old furnace had probably been oversized even then.

Hank also measured the existing duct system's external static pressure with the old furnace's blower on its heating speed: 105 Pa. The ducts were sheet metal, mostly sealed, with one undersized return in the living room. He checked the gas piping: a 3/4-inch line from the meter to the furnace and water heater, with the range on its own branch. He measured CO in the house and at the appliances, all clear, and tested the water heater for spillage under worst-case conditions. It drafted properly with the furnace running, which, as lesson 4 explained, was partly because the furnace's hot flue gas kept the chimney warm.

Choosing the furnace

With a heat loss of 12.9 kW, Hank chose a two-stage condensing furnace with a high-fire input of 17.6 kW and an output of 16.9 kW, the furnace from lesson 1's first example, with an AFUE of 96. A condensing furnace was the only choice for a new installation in Ontario under the federal efficiency rules. Its low fire, about 65 in every 100 units of its full input, would carry the house through most of the season in long cycles.

Worked problem

Is the new furnace the right size?

The new furnace delivers 16.9 kW at high fire and the house loses 12.9 kW on a design day. The old furnace delivered about 23.4 kW. Compare each with the heat loss.

Show solution
  1. New furnace:
  2. \[\frac{16.9}{12.9} \approx 1.31\]
  3. Old furnace:
  4. \[\frac{23.4}{12.9} \approx 1.81\]

Answer: The new furnace has a margin of about 1.3 times the design heat loss, which allows for recovery after setbacks without gross oversizing, and its low fire is close to the house's average winter load. The old furnace was about 1.8 times too large, which explained the Okoyes' complaint of short, noisy cycles and uneven rooms.

The new furnace's blower was rated to deliver the airflow it needed at up to 125 Pa of external static pressure. The existing ducts had measured 105 Pa with the old blower, so Hank expected to stay within the limit, but he recommended adding a second return in the living room to bring the static pressure down and quiet the system. The Okoyes agreed, and Bayline's sheet metal crew added it on the Monday morning.

The water heater decision

The furnace choice created a second decision. With the old furnace gone, the water heater would sit alone in the masonry chimney, the orphaned water heater problem GAS-120 described and the Westdale job in lesson 4 showed in practice. There were two sound options. Bayline could install a liner sized for the water heater alone, as on the earlier job, and leave the 14-year-old water heater in place. Or it could replace the water heater with one that did not need the chimney at all, and take both appliances out of it.

Hank set out both options for the Okoyes with their costs and the water heater's age: storage water heaters commonly last somewhere in the range of 8 to 15 years, and theirs was near the end of that range, with a little rust at the base of the jacket. Lining the chimney for an old water heater and replacing the water heater a year or two later would mean paying twice. The Okoyes chose to replace it with a power-vent storage water heater, vented in plastic through the basement wall beside the furnace's pipes, which meant the chimney would no longer serve any gas appliance.

Worked problem

Checking the water heater size

The household of four has a peak hour demand estimated at about 290 L: two showers, a dishwasher and a sink. The new 189 L power-vent water heater has an input of 11.7 kW, a recovery efficiency of 0.80 and a first-hour rating of 310 L. What is its recovery rate through a 50 °C rise, and does its FHR meet the demand?

Show solution
  1. Heat delivered:
  2. \[11.7 \times 0.80 = 9.36 \text{ kW}\]
  3. Recovery:
  4. \[\frac{9.36 \times 3600}{4.186 \times 50} = \frac{33\,696}{209.3} \approx 161 \text{ L/h}\]
  5. Compare the FHR with demand:
  6. \[310 \text{ L} > 290 \text{ L}\]

Answer: The tank recovers about 161 L per hour, and its first-hour rating of 310 L covers the household's busiest hour with a small margin. A larger tank was not needed.

With two appliances changing, the gas load changed too. The new furnace and water heater together had an input of 29.3 kW, the same as the old furnace alone and less than the old pair's 41 kW. Hank checked the 3/4-inch line against Bayline's sizing tables for the new loads and the range; it was adequate with margin, so no piping changes were needed beyond the connections at each appliance. Bayline's office opened the job file and booked the work, and Bayline's electrical partner would file the ESA notification for the water heater's receptacle.

Monday: removal and installation

On Monday, November 9, Rosa and Jonah arrived at 7:30. Jonah took CO readings at the door and in the basement, all zero, and photographed the old installation. They shut off and locked out both appliances, proved them dead, drained the old water heater through a hose to the floor drain, and disconnected and capped the gas lines. The old furnace came out in pieces through the basement stairs. The air-conditioning coil on top of the old furnace was nearly new and was supported while the furnace under it was swapped, with no refrigerant work needed.

The two vent connector openings into the chimney were sealed at the basement thimble with a masonry patch, and Jonah fixed a label to it saying the chimney no longer served any gas appliance. Rosa recommended that the Okoyes have a mason cap the chimney top, which they booked for later in the month, and noted it on the job sheet. A chimney left open but unused is not a gas hazard, but it lets rain in and warm air out.

The new furnace went on a new pad, levelled and pitched as its instructions required for the condensate. Rosa and Jonah connected the gas supply with a new manual valve, a union and a sediment trap, supported independently. The exhaust and intake pipes, ULC S636 PVC, ran 4.6 m with three elbows to a two-pipe sidewall termination on the side wall. Before drilling, Jonah measured every clearance the instructions and the code required: from the gas meter and its regulator vent, the nearest window, the property line, the ground and the expected snow level, and from the water heater's terminal. The condensate drained through a neutralizer to the floor drain.

The new water heater went where the old one had been, on a fresh pad. Jonah connected the gas with a new valve, union and sediment trap, and the water lines with new dielectric fittings. He fitted the T&P valve's discharge line full size to 150 mm above the floor drain. The house had a check valve on its water service, so he added a thermal expansion tank on the cold line, charged to the house's water pressure. The power-vent's PVC pipe ran 3.0 m with two elbows to its own terminal, sloped as the instructions required. Bayline's electrical partner installed the receptacle for its blower in the afternoon.

A plan of the Okoye basement after the job. The chimney at one end is sealed and labelled as no longer serving gas appliances. The new condensing furnace has two PVC pipes running to a sidewall termination, with clearance dimensions to the meter, a window and the ground marked. The new power-vent water heater has its own PVC vent to a separate terminal. The condensate runs through a neutralizer to the floor drain, the T&P discharge line drops to the drain, and an expansion tank sits on the cold water line. A new return is shown in the living room above. Start-up readings are listed in a box.
The Okoye basement after the replacement, with the key start-up readings.

Tuesday: start-up

On Tuesday morning the new return was finished and the gas connections were leak tested and purged. Jonah primed the furnace's condensate trap, filled the water heater, and checked that air had been bled from the hot water lines. Then he started each appliance in turn, following its instructions and Bayline's start-up sheet, with Rosa watching. He measured the inlet pressure at the furnace: 1.74 kPa static and 1.64 kPa with the furnace, the water heater and all four range burners running, well above the plate minimum. He set the manifold pressures to the plate values, 0.87 kPa at high fire and 0.42 kPa at low fire.

Worked problem

Clocking the new furnace

With only the furnace running at high fire, the meter's 0.1 cubic metre test dial takes 216 s per revolution. The gas is 37.5 MJ per cubic metre and the plate input is 17.6 kW. What is the measured input, and how close is it to the plate?

Show solution
  1. Flow:
  2. \[\frac{0.1 \times 3600}{216} = 1.667 \ \text{m}^3\text{/h}\]
  3. Input:
  4. \[1.667 \times 37.5 = 62.5 \text{ MJ/h} \qquad \frac{62.5}{3.6} = 17.4 \text{ kW}\]
  5. Difference:
  6. \[\frac{17.6 - 17.4}{17.6} \approx 0.011\]

Answer: The measured input is about 17.4 kW, roughly 1 in 100 below the plate, within the instructions' allowance. The orifices, manifold pressure and gas were as expected.

The flames were steady and blue and entered the heat exchanger cleanly. After ten minutes at high fire, Jonah measured a supply temperature of 51 °C and a return of 21 °C, a temperature rise of 30 °C, inside the plate's range of 20 to 35 °C. The external static pressure, with the new return in place and a clean filter, was +70 and −45 Pa, a total of 115 Pa, under the maximum. The combustion analysis at the furnace's test port gave readings inside the instructions' ranges, with an air-free CO of 22 ppm. He checked the low-fire stage the same way, then tested the safety controls as the instructions described.

Worked problem

Estimating airflow from the rise

The furnace delivers 16.9 kW at high fire, and the measured temperature rise is 30 °C. Using 1.21 kJ per cubic metre per °C, what airflow is the blower moving?

Show solution
  1. Rearrange the heat equation for airflow:
  2. \[\dot V = \frac{Q}{1.21 \times \Delta T} = \frac{16.9}{1.21 \times 30} = \frac{16.9}{36.3} = 0.466 \ \text{m}^3\text{/s}\]
  3. In litres per second:
  4. \[0.466 \times 1000 \approx 466 \text{ L/s}\]

Answer: About 466 L/s, close to the airflow the blower table gives for the heating speed Jonah had selected at this static pressure. The two methods agreeing is a good sign that the readings are sound.

The water heater was next. Jonah confirmed its inlet pressure with the furnace running, watched its power venter and igniter sequence, checked the flame, measured the manifold pressure, and took a combustion reading at the vent's test port: air-free CO 35 ppm, within the maker's range. He lifted the T&P valve's lever to prove it, checked the expansion tank, and set the gas control so the water at the kitchen tap came out at 49 °C through the house's existing mixing valve. With both appliances running and the house's exhaust fans and dryer on, he checked CO in the basement and on the main floor: zero.

Handing over

The last hour went to the Okoyes. Jonah showed them the furnace filter and how to change it, the manual valves for both appliances, the condensate trap and neutralizer, the water heater's T&P valve and why it must never be capped, and the two new vent terminals, which must be kept clear of snow, leaves and new plantings. He tested the CO alarms and added one in the basement near the appliances, where there had been none. He explained the thermostat's two-stage operation and why the new furnace would run longer, quieter cycles. Rosa left the instructions for both appliances in a sleeve on the furnace and the start-up sheets with the Okoyes.

Bayline's office registered both warranties and filed the start-up sheets with the job record; the electrical partner filed the ESA notification for the receptacle. Bayline's plan for the house was its first annual service in the fall of 2027, with the neutralizer media checked then.

Worked problem

What the replacement saves

The house needs about 55 GJ of heat a year. The old furnace had an AFUE of 78; the new one has 96. Ignoring the water heater, how much less gas, in cubic metres, will the house use? Use 37.5 MJ per cubic metre.

Show solution
  1. Gas used by each furnace:
  2. \[\frac{55}{0.78} = 70.5 \text{ GJ} \qquad \frac{55}{0.96} = 57.3 \text{ GJ}\]
  3. Difference in megajoules, then cubic metres:
  4. \[(70.5 - 57.3) \times 1000 = 13\,200 \text{ MJ} \qquad \frac{13\,200}{37.5} = 352 \text{ m}^3\]

Answer: About 352 cubic metres a year less, close to a fifth of the old furnace's use, before counting the benefit of the right-sized, two-stage operation.

What the job shows

The case study decisions and where each comes from in the course.
DecisionLessonWhy it was made
Size the furnace from a heat loss calculation1, 12The old furnace was 1.8 times too large
Measure duct static pressure before choosing4A blower can only deliver its airflow if the ducts allow it
Choose a two-stage condensing furnace2, 3Efficiency, long low-fire cycles, no chimney needed
Replace the water heater rather than line the chimney4, 5An orphaned water heater near the end of its life
Check piping against the new loads1, 12Inputs changed; the line had to be proved adequate
Measure every termination clearance before drilling3, 5Flue gas must not re-enter the house or reach the meter
Record every start-up reading4, 11The next service technician needs a baseline

Jonah's notes on the job ended with a line Rosa liked enough to repeat at Hank's next shop training: "Two appliances out of a chimney, two appliances in, and the hard part was deciding, not installing." Every measurement on the start-up sheets came from a lesson in this course, and so did every decision. GAS-220 takes the controls and ignition systems that ran each appliance's start-up sequence and opens them up.

Common mistakes

  • MistakeMatching the old furnace's input instead of calculating the heat loss.

    InsteadCalculate the heat loss and choose the furnace from it.

  • MistakeRemoving a furnace from a shared chimney and leaving the water heater as it is.

    InsteadLine the chimney for the water heater or take the water heater out of the chimney.

  • MistakeDrilling the vent hole before measuring the termination clearances.

    InsteadMeasure every clearance from the instructions and code first.

  • MistakeForgetting the expansion tank on a house with a check valve.

    InsteadFit a thermal expansion tank on a closed water system.

  • MistakeLeaving without explaining the new equipment.

    InsteadWalk the customer through filters, valves, terminals, condensate, the T&P valve and CO alarms.

Summary and key terms

  • The Okoye job replaced a 27-year-old, oversized mid-efficiency furnace and a 14-year-old atmospheric water heater sharing a masonry chimney.
  • A heat loss calculation set the new furnace's size: a two-stage condensing furnace with about 1.3 times the design heat loss.
  • Duct static was measured first, and a return was added.
  • Rather than orphan the water heater in the chimney, the owners replaced it with a power-vent model sized by first-hour rating, and the chimney was sealed and labelled.
  • The piping was checked against the new loads.
  • Start-up recorded inlet and manifold pressures, the clocked input, temperature rise, static pressure, airflow, combustion readings and CO, all within the instructions' limits.
  • The customer was shown everything and the warranties and records were filed.
Orphaned water heater
A water heater left alone in a chimney or vent sized for more than one appliance.
Design heat loss
The heat a house loses on the coldest day it is designed for.
Peak hour demand
The most hot water a household uses in its busiest hour.
Thimble
The opening in a chimney wall where a vent connector enters.
Dielectric fitting
A fitting that separates dissimilar metals in water piping to slow corrosion.
Handover
The explanation of new equipment, its controls and its care given to the customer at the end of a job.
Baseline
The readings recorded at start-up against which later service readings are compared.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. Why did Hank not size the new furnace from the old one?

    Show answer

    The old furnace was far larger than the house's heat loss.

  2. What problem would removing the furnace have caused for the old water heater?

    Show answer

    It would have been orphaned in a chimney too large for it alone, risking poor draft and spillage.

  3. Why was a thermal expansion tank added?

    Show answer

    The water service had a check valve, making it a closed system.

  4. What airflow corresponds to 16.9 kW at a 28 °C rise?

    Show answer

    16.9 ÷ (1.21 × 28) = 0.499 m³/s, about 499 L/s.

  5. Name three readings recorded on the furnace start-up sheet.

    Show answer

    Inlet and manifold pressure, clocked input, temperature rise, static pressure, combustion readings or CO.

Lesson quiz · 5 questions

Score 60% or more to complete this lesson.

Take the quiz