IRW-340 · Lesson 7 of 12 · 27 min
Review: decking, joists and precast
▶ Video coming soon A video version of this lesson is on the way.
Ilona Benedek, who ran Crossbeam's deck crew and its Tuesday deck nights, took the second half of the November 1 session. She brought a short offcut of 1-1/2 in roof deck, a weld washer, a bundle tag and the sheet she used for her own self-inspections. "Deck is where young ironworkers get hurt," she said. "It's flat, it looks easy, and there's always an edge or a hole you've stopped seeing." Corwin Haldane stayed for the last half hour to talk about metal buildings, which most exams treat as part of erection.
This lesson reviews IRW-230 and IRW-330: steel joists and bridging, metal deck and its fastening, shear studs, openings and edges, precast concrete, and the main points of pre-engineered metal buildings.
Steel joists and joist girders
Open-web steel joists are light trusses made of angles or bars, shop-built to carry floors and roofs over long spans. Joist girders carry joists at their panel points and span between columns. In the United States, joists are made to Steel Joist Institute standards in K, LH and DLH series. OSHA 1926.757 sets the erection rules: joists at columns are field-bolted, with a stabilizer plate, before release; joists of 40 ft or more at columns are bolted; erection bridging is required on longer spans, with one row near midspan for the spans in the standard's tables, two rows at the third points for spans of 60 to 100 ft, and more for longer spans; and no load is placed on a joist until the bridging and end attachments are complete.
Bridging keeps the joists' top and bottom chords from buckling sideways. Horizontal bridging is a continuous angle welded or bolted to the chords; diagonal or cross bridging is a pair of members between adjacent joists. Bridging runs must end at a wall, a beam or a braced point, never at a loose joist. The erection drawings show the rows; IRW-230 worked out the length of horizontal bridging for a warehouse roof, two rows by two chords across four lines of joists, as 6,400 ft.
Worked problem
A joist girder and its panel points
A joist girder spans 40 ft with joists at 5 ft centers. How many interior panel points carry joists?
Show solution
- Number of spaces: 40 ÷ 5 = 8.
- Interior panel points are one fewer than the spaces: 8 − 1 = 7.
Answer: 7 interior panel points. The trap is counting the spaces instead of the points, or counting the ends.
Metal deck
Roof deck is commonly 1 1/2 in deep, with wide or narrow ribs; composite floor deck is deeper and embossed so it bonds to the concrete; form deck only holds wet concrete. The Steel Deck Institute's standard, ANSI/SDI SD, covers design and installation. Deck sheets are landed in bundles on the structure, spread, aligned and fastened to the supports in the pattern on the drawings, and the side laps between sheets are fastened as specified.
Bundles are landed where the structure can carry them. OSHA 1926.757 limits bundles of decking landed on joists to 4,000 lb, on at least three joists that are attached at both ends, within 1 ft of the secured end, with at least one row of bridging installed, unless a qualified person has approved a different arrangement in the erection plan.
Worked problem
Is the deck bundle too heavy for the joists?
A bundle holds 30 sheets, each 120 ft², of deck weighing about 1.6 psf (typical). What does it weigh, and is it within OSHA's 4,000 lb limit on joists?
Show solution
- Area: 30 × 120 = 3,600 ft².
- Weight: 3,600 × 1.6 = 5,760 lb.
- Over 4,000 lb, so the bundle is split: 20 sheets weigh 20 × 120 × 1.6 = 3,840 lb.
Answer: 5,760 lb is over the limit; land 20 sheets at a time, 3,840 lb.
Deck is fastened with arc spot welds (puddle welds), screws or powder-actuated pins, in the pattern and at the spacing the drawings require, with side laps screwed or button-punched. Thin deck often needs weld washers so the weld does not burn through. Powder-actuated tools need training and the right load and pin for the steel; IRW-230's deck crew fastened every sheet in its pattern of welds at the supports and screws at the side laps.
Shear studs and composite floors
Shear studs are welded through the deck to the top flange of the beam with a stud gun, so the concrete slab and the beam act together. Each stud is checked by eye for a full weld collar, and some are bent as a test: the common practice is to bend sample studs about 30 degrees before production and about 15 degrees in the field for any stud that looks doubtful, and a stud that breaks is replaced. Studs are welded only after the deck is fastened, and the stud welder's power and settings are set from test studs each day.
Worked problem
Studs on a beam
Beam B2-14 is 30 ft long under deck with ribs at 12 in centers, and one stud goes in each rib except the two ribs at the ends. How many studs?
Show solution
- Ribs: 30 × 12 ÷ 12 = 30 ribs.
- Less 2 end ribs: 30 − 2 = 28 studs.
Answer: 28 studs, as in IRW-230.
Openings and edges
Holes in deck and floors are among the most dangerous hazards on a site. OSHA 1926.754(e) requires covers that support twice the weight of the workers, equipment and materials that may be on them, are secured against displacement, and are painted with high-visibility paint or marked with the word HOLE or COVER. Deck over an opening is cut only just before the opening is filled or framed, and openings around columns are planked or decked.
Controlled decking zones, which Subpart R allows between 15 and 30 ft under strict conditions (a zone no larger than 90 ft by 90 ft, no more than 3,000 ft² of unsecured deck, two safety attachments per panel and no final deck attachments or shear connectors installed in the zone), are not used on Crossbeam's jobs. Every decker on a Crossbeam job is tied off or protected by guardrail above 6 ft.
Precast concrete
Precast members are cast in a plant and erected like steel: hollow-core planks for floors and roofs, double tees for parking decks and long roofs, beams, columns and wall panels. They are heavy for their size, they cannot be bent or trimmed to fit, and they are lifted only at the inserts or lifting loops the precaster designed. Inserts and hardware have their own safety factors.
OSHA 1926.704 requires lifting inserts embedded in tilt-up members to carry at least two times the maximum intended load, inserts in other precast members four times, and lifting hardware five times, and allows only essential employees under precast members being lifted.
Worked problem
Load on a precast insert
A double tee weighs about 40,800 lb and is lifted at four inserts. The precaster's rigging sheet adds a dynamic allowance of 1.2. What load is used for each insert, and is it within an insert rating of 16,500 lb?
Show solution
- Equal share: 40,800 ÷ 4 = 10,200 lb.
- With the allowance: 10,200 × 1.2 = 12,240 lb.
Answer: About 12,240 lb per insert, within the 16,500 lb rating. The insert rating already includes the factor the standard requires; the allowance covers the shock of lifting.
Precast connections are welded plates, grouted dowels, bolted angles and bearing pads. The bearing length at each support is checked, the pads are the right type and placed where shown, and temporary bracing holds wall panels and columns until the connections and grout are complete. At Tidewell House in IRW-230, the crew set 280 hollow-core planks in August and checked every bearing before the planks were grouted.
Pre-engineered metal buildings
Metal buildings appear on exams as a part of erection. A pre-engineered metal building is a system of rigid frames, cold-formed purlins and girts, bracing, panels and trim designed and supplied together by one manufacturer for one building. The erector builds it from the manufacturer's erection drawings and guide, starting at a braced bay so the first two frames and their bracing form a stable box.
OSHA 1926.758 sets the rules for systems-engineered metal buildings: four anchor rods per column, at least 50 in 100 of the bolts or the manufacturer's number, if greater, installed before a rigid frame is released, a bolt shared by two members kept engaged on one side when the other is attached, and purlins and girts not used as anchorage for fall arrest unless a qualified person approves it in writing. Crossbeam adds its own wind rule: frames are not set in gusts over 25 mph.
Roof panels are through-fastened or standing seam. Standing seam roofs use clips that let the panels move with temperature and can be used at very low slopes, commonly as low as 1/4 in 12; through-fastened panels need steeper slopes, commonly 1/2 in 12 or more, and the manufacturer's minimum governs. Insulation is a faced blanket with a continuous vapor retarder toward the warm side. On the Brannock building in IRW-330, the crew checked the diagonals of the anchor rod layout, 144.222 ft for a 80 ft by 120 ft building, and found and reported an endwall rod group out of position before the steel shipped.
Deck and precast close-out
Ilona finished her part of the session with her self-inspection sheet. On the Ashcroft deck, her own walk on November 5 found eleven defects before the general contractor's inspector arrived, from missing welds and side-lap screws to studs with incomplete collars, and every one was fixed before the inspection. Her point was that a crew that inspects its own work first never argues with an inspector.
Precast has its own close-out: grouting the keyways between hollow-core planks, welding connection plates, checking bearing pads, removing temporary bracing only when the precaster's engineer allows it, and handing over a record of the pieces erected. IRW-230 worked out the grout for the keyways at Tidewell House; the same arithmetic, length times width times depth of each keyway times the number of keyways, appears on exams as a quantity question.
Practice questions
Question 1. A bridging run on a joist roof ends at the last joist in a bay, which is not yet connected to anything else. Is that acceptable? Options: (a) yes; (b) no, a bridging run must end at a wall, beam or braced point; (c) only on short joists; (d) only if welded.
Answer and reasoning: (b). Bridging anchored to a loose joist does not brace anything.
Question 2. Deck over a mechanical opening is cut at the start of the day so the plumbers can work later. What is wrong? Options: (a) nothing; (b) the opening becomes a fall hazard for the whole day; deck is cut only just before the opening is filled or framed, and protected at once; (c) the deck should be welded first; (d) the plumbers should cut it.
Answer and reasoning: (b). An open hole all day is exactly the hazard the rule prevents.
Question 3. Why are shear studs welded after the deck is fastened? Options: (a) so the deck is held in place and the studs weld through it to the beam; (b) because studs are heavy; (c) to save electricity; (d) it does not matter.
Answer and reasoning: (a). Studs weld through fastened deck to the top flange; welding them first would leave nothing to hold the deck down.
Question 4. A precast wall panel is set and the crane is about to release it. What must be in place? Options: (a) only the bearing; (b) the temporary braces shown on the precaster's erection drawings, installed and secured; (c) nothing, because it is heavy; (d) the roof.
Answer and reasoning: (b). Panels are braced until their permanent connections and grout are complete.
Question 5. On a metal building, a frame is set at the end of the day without its bracing complete and a storm is forecast. What should the crew do? Options: (a) leave it; (b) add temporary cables or guys as the erection guide requires before leaving; (c) remove the purlins; (d) loosen the bolts.
Answer and reasoning: (b). Unbraced metal building frames are vulnerable to wind; at Brannock, the crew cabled frames 6 and 7 before the July 10 storm.
Question 6. A cover over a floor opening is sound but has no marking. What is missing? Options: (a) nothing; (b) the identification the rules require, such as a marking that it covers an opening; (c) a second cover; (d) paint on the floor around it.
Answer and reasoning: (b). An unmarked cover can be lifted or moved by someone who does not know there is a hole under it.
Common mistakes
MistakeLanding a deck bundle on joists that are not fully attached.
InsteadLand it on at least three attached joists, with bridging installed, near a bearing, within the weight limit.
MistakeCutting deck over an opening at the start of the day.
InsteadCut it only just before the opening is filled or framed, and cover or guard it immediately.
MistakeLifting a precast member by a sling around its body.
InsteadLift only at the designed inserts with the rigging on the precaster's sheet.
MistakeEnding a bridging run at a loose joist.
InsteadEnd it at a wall, beam or braced point.
MistakeUsing a purlin as a fall arrest anchor.
InsteadUse approved anchors; purlins are not anchors unless approved in writing.
Summary and key terms
- Joists and joist girders need complete end connections and bridging before they carry load.
- OSHA 1926.757 sets joist erection, bridging and bundle landing rules.
- Deck is fastened in the pattern on the drawings with welds, screws or pins, and studs are welded through it after fastening.
- Covers must carry twice the load, be secured and be marked HOLE or COVER.
- Precast is lifted only at its designed inserts; connections and bracing hold it until grouted.
- Metal buildings start at a braced bay and follow the manufacturer's guide and bolt rules.
- Open-web steel joist
- A light shop-built truss that supports a floor or roof.
- Joist girder
- A heavier truss that carries joists at its panel points.
- Bridging
- Members that brace joist chords against buckling.
- Arc spot weld
- A weld that fastens deck to its support through a hole melted in the sheet.
- Shear stud
- A steel stud welded to a beam so the slab and beam act together.
- Hollow-core plank
- A precast floor or roof slab with long voids that reduce its weight.
- Braced bay
- The bay of a metal building with bracing that makes it stable first.
Practice problems
Work each problem on paper first, then reveal the answer to check.
Why must deck over an opening be cut only just before it is filled or framed?
Show answer
So the opening is not left as a fall hazard.
What must a hole cover carry under OSHA 1926.754(e)?
Show answer
Twice the weight of workers, equipment and materials on it.
A girder spans 50 ft with joists at 5 ft. How many interior panel points?
Show answer
50 ÷ 5 = 10 spaces, so 9 points.
What safety factor does OSHA require for lifting inserts in tilt-up members?
Show answer
Two times the maximum intended load.
Where does a metal building's erection start?
Show answer
At a braced bay.
Lesson quiz · 5 questions
Score 60% or more to complete this lesson.
Create a free account to save your progress, take quizzes and earn a certificate.