ROOF-120 · Lesson 11 of 12 · 26 min
Roofing in the National Building Code
▶ Video coming soon A video version of this lesson is on the way.
A week of steady rain in October kept the crews off the roofs, so Anjali Mukherjee booked the shop for two mornings of code training. She put a thick binder on the table in front of Rory. It was the Ontario Building Code, with yellow tabs sticking out of Part 9. "Nobody memorizes this," she said. "But every roofer needs to know how it's put together, where roofing lives in it, and what it actually asks of us. Then you know when to look something up, and you can talk to an inspector without guessing."
Building codes set the minimum legal requirements for how buildings are designed and built, including their roofs. Codes are written to protect health and safety, keep buildings standing and dry, limit fire spread and save energy. This lesson explains where the codes that govern roofing come from, how they are adopted into law, how they are organized, and what they require of roofs, in plain language. It does not reproduce code text: the adopted code itself, read alongside the manufacturer's instructions, is always the authority.
Model codes and adopted codes
In Canada, building regulation is a provincial responsibility. The national codes are model codes, developed by the Canadian Commission on Building and Fire Codes with technical support from the National Research Council. The National Building Code of Canada (NBC) is updated on a regular cycle; the 2020 edition is the current base for most provinces. A model code has no legal force until a province adopts it, sometimes with changes. In Ontario, the Building Code Act gives the province the power to make the Ontario Building Code (OBC), a regulation under that Act. The current code, often called the 2024 OBC, is Ontario Regulation 163/24. It took effect on January 1, 2025, and is based closely on the 2020 NBC, with Ontario changes. Projects permitted under the earlier code could continue under it for a transition period.
The OBC is enforced by the local municipality. In Hamilton, the City's building division reviews permit applications, issues permits and sends inspectors. The chief building official in each municipality has the authority to interpret the code there. Other laws also touch roofing work: the Fire Code (kettles and torches), the Occupational Health and Safety Act and its construction regulation (O. Reg. 213/91, covered in ROOF-110), and municipal by-laws.
How the code is organized
The NBC and the OBC share the same three-division layout:
| Division | What it covers |
|---|---|
| Division A | compliance, the objectives the code is meant to achieve, and definitions |
| Division B | the technical requirements, in Parts: Part 3 fire protection, Part 4 structural design, Part 5 environmental separation, Part 9 housing and small buildings, and others |
| Division C | administration: permits, inspections, and the qualifications of designers and officials |
Part 9 applies to houses and small buildings: in general, buildings of three storeys or less with a building area of 600 m² or less, in residential, business, mercantile and light industrial uses. Most of Ridgecap's steep-slope work, including every Linden Street house, falls under Part 9, where the roofing rules are in Section 9.26 and the rules for attic and roof space ventilation are in Section 9.19. Larger buildings such as Ashgrove Plaza, the warehouse and Northgate are designed under Parts 3, 4 and 5 by architects and engineers. For those, Part 3 sets the fire classification of the roof covering, Part 4 sets the snow, rain and wind loads, and Part 5 covers the roof as a barrier to water, air, vapour and heat, including wind uplift of membrane roofs.
The code is objective-based. It sets out what each requirement is trying to achieve and offers acceptable solutions, the detailed rules most buildings follow. A designer may propose an alternative solution instead, but must show the building official that it performs at least as well. Roofers follow the code and the approved drawings; alternatives are a decision for the designer and the building official, not for the crew on the roof.
What the code asks of roofs
Part 9's roofing section starts with the purpose of roofing in your own words: the roof covering and flashings must shed water, keep water and moisture out of the building assemblies and the occupied space, and reduce ice damming. The rest of the section explains how. In outline, it covers:
- Roofing materials: they must meet the referenced standards, and listed materials must be installed following the manufacturer's written instructions.
- Slopes: minimum (and some maximum) slopes for each type of covering, as described in lesson 2.
- Flashing: at the intersections of roofs with walls, chimneys and other roofs, and at valleys.
- Eave protection: where it is required, how far up the roof it must go, and which materials qualify, as covered in lesson 4.
- Underlay: which materials are acceptable if underlay is used beneath shingles. Part 9 does not make full underlay mandatory under asphalt shingles on normal slopes, but nearly every shingle manufacturer requires it for the warranty, and Ridgecap installs it on every roof.
- Each type of covering: separate rules for asphalt shingles on normal and low slopes, wood shingles, cedar shakes, built-up roofs, selvage roofing, sheet metal roofing, glass reinforced polyester panels, hot-applied rubberized asphalt, PVC sheet roofing and concrete tiles.
- Roof drains and downspouts: where water must be carried and how it must be kept away from the building.
Ventilation of attics and roof spaces sits in a separate section from the coverings, and so do the energy rules for insulation and air barriers. A roofer working on a house needs all three.
Reroofing
Part 9 says little directly about installing new roofing over old. In practice, the shingle manufacturer's instructions control: most allow one new layer over one existing layer of asphalt shingles only if the old roof is flat, dry and sound, and some do not allow it at all for their best warranties. The roof structure must also be able to carry the extra weight. Ridgecap's policy is to tear off to the deck on every re-roof, so the deck can be inspected, eave protection and underlay installed properly, and ventilation checked. Whether a permit is needed depends on the work: in many Ontario municipalities, including Hamilton, replacing shingles with similar shingles does not need a permit, but structural repairs, new or replaced decking in some cases, changes to the roof shape and many commercial re-roofs do. Always check with the building department before the job.
Standards: the code's long arm
The code does not describe every material in detail. Instead, it references standards: documents written by standards organizations that set out what a product must be and how it must be tested. When the code says a material must conform to a standard, that standard becomes part of the legal requirement. In roofing, the referenced standards include:
| Product | Standards commonly referenced |
|---|---|
| Asphalt shingles | CSA A123.5 (glass mat) |
| Roll roofing and felts | CSA A123.2, CSA A123.3 and related CSA A123 standards |
| Bitumen for built-up roofs | CSA A123.4 |
| Eave protection membranes | CSA A123.22 (self-adhering, for ice-dam protection) |
| Modified bitumen sheets | CSA A123.23 |
| Membrane wind uplift | CSA A123.21 (dynamic testing of membrane roof assemblies) |
| Fire tests of roof coverings | CAN/ULC-S107 |
| Insulation | CAN/ULC-S701 (polystyrene), CAN/ULC-S704 (polyiso) |
| Wood panels | CSA O121, CSA O151, CSA O325 |
Products that do not fit an existing standard, such as many synthetic underlayments and new membrane types, are accepted through product evaluations. In Canada, the Canadian Construction Materials Centre (CCMC) evaluates such products and publishes evaluation reports that building officials rely on. The report says how the product must be installed to comply, and it usually points back to the manufacturer's instructions.
Manufacturer's instructions, specifications and warranties
Three other documents sit beside the code on every job, and roofers must keep them straight:
- The manufacturer's installation instructions: printed on the wrapper or in the technical manual. The code requires listed products to be installed following them, so ignoring the wrapper can be a code violation as well as a warranty problem. Where the instructions are stricter than the code (six nails instead of four, underlayment where the code does not require it), follow the instructions.
- The project specification and drawings: on commercial jobs, the architect's or engineer's documents describe exactly which system, products and details to use. They usually exceed the code minimum. Changes need the designer's written approval.
- The warranty: the manufacturer's promise to repair or replace the roof under stated conditions. Many warranties require the roofing contractor to be approved by the manufacturer, the installation to be inspected and every component to come from the same system. A roof can meet the code and still have no warranty if the rules were not followed.
The code is the minimum. A roof built only to the code minimum will be legal, but the best roofs follow the manufacturer's full system, the specification and good trade practice as described in industry manuals.
Inspections
On jobs with a permit, the building department inspects at the stages it sets out, and roofers must leave work open for inspection where required. For a Part 9 house, roofing inspections are often limited, but where a permit was issued, an inspector may want to see the deck repairs, eave protection or flashings before they are covered. On larger buildings, the designer usually carries out general review of the roofing and may hire a roofing consultant to inspect it, and the manufacturer may also inspect for the warranty. Have the permit, approved drawings and product information on site.
When an inspector or consultant points out a problem, listen, ask where the requirement is so you can read it, and report it to your foreperson. Arguing on the roof helps no one. If there is a genuine disagreement, the company resolves it with the building official.
Checking a job against the code
Anjali finished the second morning with three exercises. Rory's answers are below.
Worked problem
Which part of the code applies?
Ridgecap is bidding on two jobs: a two-storey office with a building area of 450 m², and the Northgate Medical Building, two storeys with a building area of about 1,400 m². Which part of the OBC governs the roofs?
Show solution
- Part 9 applies, in general, to buildings of three storeys or less with a building area of 600 m² or less, in the common uses.
- The office: two storeys and 450 m², a business use, so Part 9.
- Northgate: two storeys but about 1,400 m² of building area, more than 600 m², so it is designed under Parts 3, 4 and 5.
Answer: The office roof follows Part 9 (Section 9.26). Northgate's roof follows the Part 3, 4 and 5 requirements, as shown on the architect's and engineer's drawings.
Worked problem
Is the slope allowed?
A porch roof on a Linden Street house is 3 in 12. The owner wants it shingled to match the house. Is that allowed?
Show solution
- 3 in 12 = 3 ÷ 12 = 0.25, which is 1 in 4.
- Normal asphalt shingle application needs at least 1 in 3 (0.333). 1 in 4 is flatter, so normal application is not allowed.
- The low-slope shingle method is allowed down to 1 in 6 (0.167). 1 in 4 is steeper than that, so the low-slope method can be used.
- Check that the shingle manufacturer also allows its product on this slope.
Answer: Yes, but only with the low-slope method (extra coverage and cemented tabs) and the manufacturer's approval. A membrane would be the better roof.
Worked problem
Ventilation for a cathedral ceiling
An addition has a 40 m² cathedral ceiling built with roof joists, insulated between the joists with a vented space above. What minimum vent area does Part 9 require?
Show solution
- Roofs built with roof joists use the 1/150 ratio, not 1/300.
- Vent area = 40 ÷ 150 ≈ 0.267 m².
- At least a quarter at the top and a quarter at the bottom, spread on opposite sides; the joist spaces must be interconnected or each vented.
Answer: About 0.27 m² of vent area. Ridgecap would also check the clear air space above the insulation the code requires.
Keeping current
Codes change. New editions arrive every few years, and amendments in between. Rules that were true when you trained may not be true now, and different cities can be on different editions during a changeover. Good habits for keeping current:
- Know which edition applies to each job; it is usually the one in force when the permit was applied for.
- Use the official version of the code, not a summary or a forum post.
- Read the manufacturer's current instructions; they change more often than the code.
- Watch for industry bulletins from roofing contractors' associations and manufacturers.
- When in doubt, ask the building department. Its answer for that job is the one that counts.
"The code is the floor, not the ceiling," Anjali said, closing the binder. "Build every roof as if you'll be the one called back when it leaks, because sometimes you will be."
Common mistakes
MistakeAssuming the code requires only what the crew has always done.
InsteadLook up the requirement in the adopted code and the manufacturer's instructions for each job.
MistakeTreating manufacturer's instructions as optional extras.
InsteadThe code requires listed products to be installed following them; where they are stricter, they rule.
MistakeRecovering an old roof without checking the limits.
InsteadCheck the code, the manufacturer's rules and the structure; when in doubt, tear off to the deck.
MistakeQuoting rules from an old edition or a website summary.
InsteadUse the edition in force for the job, from the official source.
MistakeArguing with an inspector on the roof.
InsteadAsk where the requirement is, report it to the foreperson, and let the company resolve disagreements with the building official.
Summary and key terms
- The NBC is a model code; Ontario adopts it as the OBC (O. Reg. 163/24, in force January 1, 2025), enforced by municipalities.
- Part 9 covers houses and small buildings, with roofing in Section 9.26 and roof space ventilation in Section 9.19; larger buildings follow Parts 3, 4 and 5.
- The code sets slopes, flashing, eave protection, underlay or underlayment, covering-specific rules, fire classes and wind performance.
- Referenced standards and product evaluations become part of the legal requirement.
- Manufacturer's instructions, specifications and warranties often exceed the code; follow the strictest.
- Check permits, inspections and the edition in force for every job.
- Model code
- A code written for adoption by governments; it has no legal force until adopted.
- Ontario Building Code
- The building regulation in force in Ontario, based on the National Building Code.
- Part 9
- The part of the code covering houses and small buildings.
- Acceptable solution
- A detailed code requirement that is deemed to meet the code's objectives.
- Alternative solution
- A design shown to perform at least as well as an acceptable solution, approved by the building official.
- Referenced standard
- A standard named in the code, which becomes part of the requirement.
- Product evaluation
- A report showing how a product not covered by a standard can comply with the code.
- Chief building official
- The person with authority to enforce and interpret the building code in a municipality.
Practice problems
Work each problem on paper first, then reveal the answer to check.
Which regulation is the current Ontario Building Code?
Show answer
Ontario Regulation 163/24, in force since January 1, 2025.
What are the size limits for Part 9, in general?
Show answer
Three storeys or less and a building area of 600 m² or less, in the common uses.
Does Part 9 require full underlay under asphalt shingles on normal slopes?
Show answer
No, but manufacturers almost always do, and Ridgecap installs it.
A porch roof is 1 in 5. Can normal shingle application be used?
Show answer
No; normal application needs 1 in 3. The low-slope method (down to 1 in 6) could be used.
Who enforces the OBC on a Hamilton job?
Show answer
The City of Hamilton's building division.