MELC-204 · Lesson 2 of 12 · 22 min
Eligibility for the Electrical Contractor Licence
▶ Video coming soon A video version of this lesson is on the way.
Before Nadia books a seat at the exam, she needs to be sure she is eligible to write it. In Manitoba this question has two layers. The City of Winnipeg decides who may hold one of its electrical contractor licences, and it bases that decision largely on what the Province has already decided about who may do electrical work. So the first step is always the provincial licence, and the second is the City licence that sits on top of it. This lesson walks through both layers, explains the difference between the A and C licences, and looks at the situations that cause the most confusion: people coming from other provinces, people with limited licences and people who work only outside Winnipeg.
The two City licences
The City of Winnipeg issues two classes of electrical contractor licence. The A licence covers any electrical construction, and holding it allows the licence holder to take out electrical permits for any kind of electrical work under the Manitoba Electrical Code and the Winnipeg Electrical By-law. The C licence is for people who hold one of the provincial limited specialized trade licences and want to take out permits for the limited work that licence allows, such as electric signs, alarm systems, refrigeration equipment, fire alarm servicing or voice, data and video systems. Each licence has a one-year term and must be renewed to stay active.
The City's licensing page is clear on one point that surprises people who have worked elsewhere: licences are issued to individuals, not to companies or other entities. A company that wants to take out permits in Winnipeg does so through a licensed individual, usually an owner or senior employee. That individual, not the company, holds the licence and carries the responsibility for the permits taken out under it. Lesson 7 looks closely at that responsibility.
Eligibility for the A licence
To write the A licence exam, an applicant must hold a current Manitoba journeyperson electrician licence. The City's page lists the acceptable licences as H, HC and HI: the general journeyperson licence carried by older licence holders, the construction electrician licence and the industrial electrician licence. The applicant includes a copy of the Manitoba licence with the application. The City does not set a separate experience requirement for the A licence, because the provincial journeyperson licence already reflects a completed apprenticeship or an equivalent route.
Two consequences follow. First, a power electrician with only a PE licence, which is restricted to power generation, transmission and supply equipment, is not on the City's list for the A licence. Second, an apprentice, however experienced, cannot write the A exam until the provincial journeyperson licence has been issued. Ben, Red River Electric's third-year apprentice, often asks Nadia whether he could write the exam early to get it out of the way. The answer is no: the City needs to see the journeyperson licence first.
Keep the provincial licence valid. The City's page states that a valid Manitoba electrician licence is a condition of the City licence. If a licence holder's provincial licence expires and a new one is not provided to the City, the City licence is suspended and no electrical permits can be obtained until it is reinstated. A lapse at the provincial level therefore stops work at the City level too.
Worked problem
Can these people write the A exam?
Red River Electric has three people interested in the A licence: Nadia, who holds an HC licence; Luc, who holds an older H licence; and Ben, a third-year apprentice who has passed his level exams so far.
Show solution
- Nadia's HC licence is on the City's list, so she is eligible.
- Luc's H licence is also on the list, so he is eligible as well.
- Ben does not yet hold any journeyperson licence; registration as an apprentice is not enough.
- Ben becomes eligible only after the Province issues his journeyperson licence.
Answer: Nadia and Luc can apply now; Ben must wait until he holds a Manitoba journeyperson licence.
Eligibility for the C licence
The C licence is for holders of certain provincial limited specialized trade licences. The City's page names the M-B licence for electric signs, the M-F licence for alarm installers, the M-G licence for refrigeration, the M-S licence for fire alarm technicians and the M-V licence for voice, data and video systems. The C exam is shorter, two hours rather than three, and the licence lets the holder take out permits only for the limited work that the provincial licence allows.
Arjun, Red River Electric's refrigeration mechanic, holds an M-G licence. Under the ITS bulletin, the Red Seal version of that licence allows maintenance and repair of refrigeration and air-conditioning equipment, plus limited circuit wiring: a circuit of up to 30 amperes and 150 volts to ground, connected to an existing panel in a single dwelling. A C licence would let Arjun take out City permits for that limited work on his own service calls. It would not let him take out permits for a new panel, a service upgrade or general wiring. For those, the work needs a journeyperson and a permit under an A licence.
| Provincial licence | City licence available | Permits allowed |
|---|---|---|
| H, HC or HI journeyperson | A licence (3-hour exam) | Any electrical construction |
| M-B, M-F, M-G, M-S or M-V | C licence (2-hour exam) | Only the limited work of the M licence |
| PE journeyperson | Not listed for the A licence | Ask the City |
| Apprentice registration | None | None |
Working outside Winnipeg
Red River Electric does a lot of work outside the city, such as the grain dryer upgrade near Steinbach. None of that work needs a City licence. Outside Winnipeg, Manitoba Hydro issues electrical permits through its ePermits system, and its contractor page says that a contractor needs a valid Manitoba journeyperson's electrician licence to set up an ePermits account. The account holder agrees to terms and conditions that make them responsible for the installations covered by permits under the account. There is no separate contractor exam for work outside Winnipeg.
This means that a journeyperson in Brandon, Thompson or Portage la Prairie can take out permits and run a contracting business without ever writing the City exam, as long as they never take out permits inside Winnipeg. Many Manitoba contractors do exactly that. For a company like Red River Electric, which works on both sides of the city limit, the practical setup is an ePermits account for rural work and at least one City licence holder for city work.
Manitoba Hydro's contractor page also lists kinds of work that only a licensed electrician may do, even where someone else might hold a permit: work in hazardous locations, on hot tubs and pools, on renewable energy systems and generators, on the consumer's service and inside a national park. A homeowner with a permit for a garage circuit, for example, may not install the service equipment or connect a generator.
Coming from another province
Section 5 of The Electricians' Licence Act allows the Province to recognize people who hold substantially equivalent credentials from another Canadian jurisdiction. A Red Seal construction electrician moving to Manitoba applies to ITS for recognition and, once the Manitoba journeyperson licence is issued, becomes eligible for the City exam in the usual way. The City does not accept an out-of-province licence directly; it needs the Manitoba licence. Interprovincial mobility rules change, so anyone in this position should contact ITS before assuming how long recognition will take or what documents are needed.
Technologists are another special case. ITS issues an M-T limited licence to registrants certified by the Certified Technicians and Technologists Association of Manitoba, allowing work on electrical equipment other than building wiring within their classification. M-T is not one of the licences the City lists for the C licence, so a technologist who wants to take out City permits should ask the City what, if anything, is available.
The provincial master electrician licence
Some candidates ask whether they should get a provincial master electrician licence first. The Act does list one, for a person with at least two years as a journeyperson who has passed an examination in design and layout. But the City's A licence requirements refer only to journeyperson licences, and the current ITS licence bulletin does not describe a master licence. A master licence is not needed for the City exam. If you want one for other reasons, contact ITS and ask whether it is being issued, what the examination covers and what it would allow you to do that a journeyperson licence does not.
Planning licence coverage for a company
Because City licences belong to individuals, a contracting company has to think about coverage the way it thinks about any other key-person risk. Red River Electric has relied on Raymond's licence for twenty years. If Raymond were injured, retired suddenly or simply let his licence lapse, the company could not take out a single new permit inside Winnipeg until another person in the company held a City licence. Jobs already under permit would not disappear, because Raymond would remain responsible for them, but the company's ability to bid and start new city work would stop. That is the real reason Raymond wants Nadia licensed well before he retires, and it is why some companies keep two or three licence holders on staff.
Licence coverage also matters for the company's customers. A general contractor such as Prairie Build Co., which hired Red River Electric for the Corydon Avenue café, needs to know that the electrical subcontractor can take out the permit on the day the schedule calls for it. Larger general contractors sometimes ask for the licence holder's name and licence number in the tender documents. Jasmine keeps a short register that lists each licence holder, the licence class, the expiry date of the City licence and the expiry date of the provincial licence behind it, so that nothing lapses unnoticed.
Worked problem
Covering a gap in licence holders
Raymond tells the office in October that he plans to stop working at the end of the following June. The next City exam sittings are in November and March. Nadia is eligible now; Luc is eligible but has never written an open-book exam.
Show solution
- Nadia should book the November sitting, which leaves the March sitting as a backup if she does not pass the first time.
- Luc could book March, giving the company a second licence holder before Raymond leaves.
- Raymond should plan to close or hand over open permits before he retires, because responsibility for permits under his licence continues until they are closed.
- Jasmine should update the licence register and the company's contact details with the City as each new licence is issued.
Answer: Booking Nadia for November and Luc for March gives Red River Electric two chances to have a new licence holder in place before June.
# Red River Electric eligibility checker for the City of Winnipeg licences
A_LIST = {"H", "HC", "HI"}
C_LIST = {"M-B", "M-F", "M-G", "M-S", "M-V"}
staff = [("Nadia Kowalchuk", "HC"), ("Luc Gagne", "H"), ("Ben Friesen", "apprentice"),
("Arjun Sidhu", "M-G"), ("Dana Ross", "PE")]
for name, licence in staff:
if licence in A_LIST:
result = "eligible for the A licence exam"
elif licence in C_LIST:
result = "eligible for the C licence exam"
else:
result = "not on the City list: check with the City"
print(f"{name:<16} {licence:<11} {result}")Nadia Kowalchuk HC eligible for the A licence exam Luc Gagne H eligible for the A licence exam Ben Friesen apprentice not on the City list: check with the City Arjun Sidhu M-G eligible for the C licence exam Dana Ross PE not on the City list: check with the City
The checker is a planning aid, not a ruling. The City decides eligibility on the application, and its rules can change between sittings.
Common mistakes
MistakeApplying for the A exam while still an apprentice.
InsteadThe City requires a Manitoba journeyperson licence (H, HC or HI) before you apply.
MistakeAssuming a C licence allows general wiring permits.
InsteadA C licence covers only the limited work of the holder's M licence.
MistakeApplying with an out-of-province licence.
InsteadGet the Manitoba licence from ITS first; the City needs a Manitoba licence.
MistakeLetting the provincial licence lapse.
InsteadA lapsed Manitoba licence suspends the City licence and blocks new permits.
Summary and key terms
- The City of Winnipeg issues A licences for any electrical construction and C licences for limited trade work, each for a one-year term.
- City licences are issued to individuals only, never to companies.
- The A exam requires a current Manitoba H, HC or HI journeyperson licence; the C exam requires an M-B, M-F, M-G, M-S or M-V licence.
- Outside Winnipeg, a valid journeyperson licence supports a Manitoba Hydro ePermits account; no City licence is needed.
- Out-of-province electricians need Manitoba recognition from ITS before applying to the City.
- A licence
- The City of Winnipeg contractor licence for any electrical construction.
- C licence
- The City of Winnipeg contractor licence for the limited work of a specialized trade licence.
- ePermits
- Manitoba Hydro's online system for electrical permits outside Winnipeg.
- Recognition
- Provincial acceptance of a substantially equivalent licence from another Canadian jurisdiction.
- M-T licence
- A limited licence for certified technologists and technicians, excluding building wiring.
Practice problems
Work each problem on paper first, then reveal the answer to check.
Which provincial licences make a person eligible for the A exam?
Show answer
H, HC or HI journeyperson licences.
Arjun holds an M-G licence. Which City licence can he apply for?
Show answer
A C licence, limited to the refrigeration work the M-G licence allows.
Does a contractor in Brandon need a City licence?
Show answer
No, unless they take out permits inside Winnipeg; Manitoba Hydro permits need a journeyperson licence and an ePermits account.
What happens to a City licence if the holder's Manitoba licence expires and is not replaced?
Show answer
The City licence is suspended and no permits can be taken out until it is reinstated.
How long is the C exam?
Show answer
Two hours.
Lesson quiz · 5 questions
Score 60% or more to complete this lesson.
Create a free account to save your progress, take quizzes and earn a certificate.