RCDD-116 · Lesson 7 of 12 · 23 min

Needs analysis and project scope

▶ Video coming soon A video version of this lesson is on the way.

The college library project begins with a kickoff meeting in a borrowed classroom. The college's facilities director wants to know how big the telecommunications rooms must be so that the architect can finish the floor plans. The head librarian wants wireless that works everywhere and enough outlets for a maker space. The IT manager wants the new building tied into the campus network with no single point of failure. The finance officer wants a number. Daniel fills four pages of notes and realizes that nobody in the room has said the same thing twice. Turning those four pages into a scope that everyone can approve is the work of this lesson.

What a needs analysis is

A needs analysis is the structured process of finding out what the owner and users need from the ICT infrastructure, now and over its life, and turning those needs into requirements that a design can meet. It comes first because every later decision depends on it. A design that meets the wrong requirements perfectly is still the wrong design. And because ICT infrastructure lasts much longer than the equipment that uses it, the analysis must look ahead: not just at today's devices and applications, but at how the building's use may change over the next fifteen or twenty years.

The needs analysis is also where the designer manages expectations. Owners often begin with goals that conflict with each other or with the budget. Uncovering those conflicts early, while they can still be resolved by discussion, is far cheaper than discovering them in a bid that comes in over budget or a building that disappoints its users.

Identifying stakeholders

The first step is to find out who has a stake in the outcome. On most projects, stakeholders include the owner's executives, who set goals and budgets; facilities staff, who will operate the building; IT and network staff, who will run the systems that use the cabling; end users, such as clinicians, teachers, librarians and office staff; security staff; and outside parties such as service providers, regulators and neighbouring tenants. Each group sees the project differently and knows things the others do not.

The designer should also identify who has authority to decide. A long list of stakeholders with conflicting wishes needs a single owner's representative who can resolve conflicts and approve the scope. On Harbourview, that was Ines Kowalczyk for technology, with the architect coordinating everything else. On the library project, Daniel asks the facilities director to name one person, and the college appoints its IT manager.

Gathering information

Information comes from several sources, and a thorough analysis uses all of them.

  • Interviews with each stakeholder group, using prepared questions so that nothing important is missed.
  • Questionnaires for larger groups of users, such as faculty or clinical staff, whose needs vary by department.
  • Workshops that bring groups together to agree priorities and resolve conflicts.
  • Review of existing documents: the owner's standards, network plans, previous projects and technology strategy.
  • A survey of existing conditions when the project involves an existing building or campus.
  • Benchmarks from similar buildings that the designer or owner has experience with.

Good interview questions ask about activities, not technology. Asking a librarian how many outlets she wants produces a guess. Asking what happens in each space, how many people use it at the busiest time, what devices they bring, what equipment the library lends, and what the library expects to do in five years produces information the designer can turn into outlet counts, wireless density and pathway capacity.

Surveying existing conditions

When a project connects to or reuses existing infrastructure, the designer must find out what is really there, which is often different from what the old drawings show. A site survey inspects existing telecommunications spaces, entrance facilities, pathways, outside plant, bonding and the condition of existing cabling. It records available space, power and cooling in each room, spare capacity in conduits and duct banks, the type and condition of cables, and any hazards such as abandoned cable, missing firestopping or overloaded pathways.

The library project connects to the campus network at an existing building 300 metres away. Daniel's survey finds that the campus duct bank between the two buildings has two spare 100-millimetre ducts, but one is blocked by a collapsed section near the old building. The college's drawings show both as clear. That single finding changes the campus link design and the cost estimate, and it is exactly the kind of fact that a desk study would miss.

Abandoned cable deserves special attention. The Canadian Electrical Code and many provincial and municipal requirements generally require accessible portions of abandoned cable to be removed, because abandoned cable adds fuel load and clutter to ceilings and shafts. A survey that finds abandoned cable should note it, because removing it adds cost to the project.

From needs to requirements

Needs are what the users say. Requirements are what the design must achieve, stated clearly enough to be measured. The designer translates one into the other. A librarian's need for wireless that works everywhere becomes a requirement for coverage at a defined signal level and capacity throughout the public floors. An IT manager's need for no single point of failure becomes a requirement for two diverse campus pathways and two backbone routes to each telecommunications room. A finance officer's need for a number becomes a construction budget with a stated contingency.

Requirements should be specific, measurable, achievable and tied to a reason. They should also be ranked. Not every requirement is equal: some are mandatory because of codes, standards or the owner's policies, some are strongly desired, and some are nice to have if the budget allows. Ranking them early makes later value engineering, covered in lesson 10, much easier.

Turning stated needs into ranked, measurable requirements.
Need as statedRequirementPriority
Wireless that works everywhere.Coverage at a defined signal level on all public floors, with two Category 6A cables to each access point location on an 18 m grid.Mandatory
No single point of failure.Two physically diverse campus pathways and diverse backbone to each telecommunications room.Strongly desired
Outlets for the maker space.Six outlets per workbench and ceiling drops for equipment, as shown in the outlet schedule.Strongly desired
Digital signs at each entrance.One Category 6A outlet and one power outlet at each sign location.Nice to have
Cabling that lasts.A warranted Category 6A system with a 25-year manufacturer warranty.Mandatory

The basis of design and the owner's project requirements

The results of the needs analysis are recorded in a document that the owner approves. Different organizations use different names. A basis of design document, or design brief, records the requirements and the design concepts chosen to meet them, with the reasons. Many projects also use an owner's project requirements document, a term from building commissioning practice. In Canada, CSA Z320 describes building commissioning and the role of the owner's project requirements, and ASHRAE Guideline 0 is widely used as well. Whatever it is called, the approved document becomes the standard against which the design and the finished building are judged.

A funnel diagram. At the wide top, inputs from stakeholders: interviews, questionnaires, workshops, existing documents, site survey, benchmarks. The funnel narrows through a band labelled Needs, then Requirements ranked mandatory, desired, optional. At the narrow bottom, an output box labelled Approved scope and basis of design.
A needs analysis funnels many inputs into ranked requirements and an approved scope.

Defining the scope

The scope defines what the ICT project includes and, just as important, what it does not. A good scope statement lists the systems in the project, such as structured cabling, pathways, telecommunications spaces, bonding, outside plant, wireless cabling and cabling for security and audiovisual systems; the areas covered; the interfaces with other work, such as power for telecommunications rooms or furniture feeds; and the items explicitly excluded, such as network switches, wireless access points or audiovisual equipment, if those are purchased separately.

Interfaces cause more disputes than anything else. Who provides the conduit from a ceiling to an outlet in a wall: the electrical contractor or the cabling contractor? Who provides the power outlets in the telecommunications room? Who installs the access points that the cabling serves? A responsibility matrix answers these questions by listing each item and assigning it to a party for design, supply and installation. Writing that matrix during the needs analysis avoids a great deal of argument during construction.

Planning for growth

A needs analysis must look beyond opening day. Owners rarely know how their use of a building will change, but they can usually describe trends: more wireless devices, more Power over Ethernet equipment, more cameras, more building systems on the network, more space used flexibly. The designer turns those trends into allowances for growth. Typical allowances include spare outlets in flexible spaces, spare capacity in pathways and sleeves, spare rack space and power in telecommunications rooms, and spare backbone strands. The allowance should be stated as a requirement, such as pathways sized for a stated amount of future cable, so that it is not cut later as if it were waste.

Growth allowances need reasons as well as numbers. When the library's budget tightens, the finance officer asks why the pathways are bigger than today's cable needs. Daniel points to the requirement in the approved basis of design and to the cost of adding pathway later in finished ceilings, and the allowance stays.

Reading the owner's standards

Many owners, especially universities, hospitals and governments, have written standards for telecommunications design and installation. These standards may specify cable types, manufacturers, outlet counts, room sizes, labelling schemes and testing. They save the designer work and make the owner's buildings consistent, but they can be out of date or conflict with current codes and industry standards. The designer should read the owner's standards early, note any conflicts with codes or with the project's requirements, and agree with the owner how each conflict will be resolved. Where an owner's standard is stricter than an industry standard, it usually governs; where it conflicts with a code, the code governs.

Worked problem

Estimating outlet counts from a needs interview

The head librarian says the main reading room will have 140 seats, of which a quarter will be at tables with outlets, plus 12 public computers and 4 staff desks. The owner's standard gives 2 outlets per table seat, 1 per public computer and 3 per staff desk. How many outlets does the reading room need?

Show solution
  1. Table seats with outlets: 140 × 0.25 = 35.
  2. Seat outlets: 35 × 2 = 70.
  3. Public computers: 12 × 1 = 12.
  4. Staff desks: 4 × 3 = 12.
  5. Total: 70 + 12 + 12 = 94 outlets.

Answer: 94 outlets, before wireless access points, security and building systems are added.

Worked problem

An order-of-magnitude budget

Lakehead Signal's records show that similar libraries cost about 95 Canadian dollars per square metre of gross floor area for structured cabling, pathways and telecommunications rooms. The library will be 6,400 square metres. With a design contingency of 0.15, what budget should be carried?

Show solution
  1. Base: 6,400 × 95 = 608,000.
  2. Contingency: 608,000 × 0.15 = 91,200.
  3. Budget: 608,000 + 91,200 = 699,200.

Answer: About 700,000 dollars at this stage. The estimate will be refined at each design phase as quantities become known.

Managing scope change

Scope rarely stays fixed. Users think of new needs, budgets change and other designers move things. Changes during design are normal, but they must be managed. Every change to the approved scope should be recorded, its effects on cost, schedule and other systems assessed, and the owner's approval obtained before the design changes. Uncontrolled growth in scope, often called scope creep, is a common cause of budget overruns and of designs that try to do too much with too little.

On the library project, the head librarian asks in design development for a recording studio. Daniel records the request, estimates its effect on cabling, pathways and cost, and sends it to the IT manager as the owner's representative. The college approves the studio but drops the digital signs, which were ranked nice to have, to stay within budget. Because the requirements were ranked, the decision takes one meeting instead of a month.

Common mistakes

  • MistakeAsking users how many outlets they want.

    InsteadAsk about activities, people and devices, and derive the outlets from them.

  • MistakeTrusting old drawings of existing infrastructure.

    InsteadSurvey existing conditions and record what is really there.

  • MistakeRecording needs without turning them into measurable requirements.

    InsteadState requirements clearly enough to design and test against.

  • MistakeTreating every requirement as equal.

    InsteadRank requirements as mandatory, desired or optional.

  • MistakeLeaving interfaces between trades undefined.

    InsteadUse a responsibility matrix for design, supply and installation of each item.

Summary and key terms

  • A needs analysis finds what owners and users need and turns it into requirements a design can meet.
  • Identify all stakeholders and a single representative with authority to decide.
  • Gather information through interviews, questionnaires, workshops, document review, site surveys and benchmarks.
  • Survey existing conditions rather than trusting old drawings.
  • Requirements should be specific, measurable, tied to a reason and ranked by priority.
  • The scope states what is included, excluded and how interfaces are divided, and changes to it are managed formally.
Needs analysis
The process of finding out what an owner needs and turning it into requirements.
Stakeholder
Any person or group affected by or with an interest in the project.
Basis of design
A document recording requirements and the design concepts chosen to meet them.
Owner's project requirements
A commissioning document stating what the owner needs the building to achieve.
Responsibility matrix
A table assigning design, supply and installation of each item to a party.
Scope creep
Uncontrolled growth of a project's scope.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. Why ask about activities rather than outlet counts?

    Show answer

    Users can describe what they do; the designer derives the counts.

  2. What should a site survey of an existing campus record?

    Show answer

    Space, power, cooling, spare pathway capacity, cable condition and hazards.

  3. Turn 'reliable campus network' into a requirement.

    Show answer

    Two physically diverse campus pathways.

  4. A room has 80 seats, half with 2 outlets each. How many outlets?

    Show answer

    80.

  5. What does a responsibility matrix prevent?

    Show answer

    Disputes over who designs, supplies and installs each item.

  6. Why rank requirements?

    Show answer

    So value engineering can protect mandatory items and cut optional ones.

Lesson quiz · 5 questions

Score 60% or more to complete this lesson.