IRW-110 · Lesson 12 of 12 · 25 min

Case study: a first week on an erection crew

▶ Video coming soon A video version of this lesson is on the way.

This lesson follows Shay Donnelly through his first week at Crossbeam Steel & Rebar, Monday, September 14, to Friday, September 18, 2026, on the first tier of the Ashcroft Medical Building in Westerville, north of Columbus. Each day brings together ideas from the earlier lessons: the trade and its crews, the tools, PPE, fall protection, lifts, the hazards of erection, site layout and rescue. As you read, look for the decisions Shay and the crew made, and ask what could have gone wrong if they had made them differently.

The job

Ashcroft is a three-story medical office building with a steel frame about 100 ft by 160 ft in plan. The frame has moment frames at the two ends and braced bays in the middle, and the floors and roof are composite metal deck with concrete. The floor-to-floor height is about 14 ft. Tallcorn Builders is the general contractor, and Crossbeam is erecting the steel for the fabricator. Carla Duquette runs the raising gang, with Andy Pruszynski and Marco Bellini connecting; Nate Okonkwo leads bolt-up; Grace Ndlovu is the safety coordinator; Dwayne Mercer runs the 100-ton hydraulic truck crane from Summitline Crane Rental.

The first tier at Ashcroft.
ItemAshcroft first tier
Columns20 columns, two-tier lengths, about 28 ft long
Floor 2 beams and girdersAbout 70 pieces, mostly W12 and W16 shapes
Bolts3/4 in in shear tabs, 7/8 in in moment and bracing connections
Crane100-ton hydraulic, set on the east side
Fall protectionColumn SRLs for connectors, beam clamps and SRLs, boom lifts for bolt-up
RescueBoom lift primary, rescue kit backup, target under 6 minutes

Monday: orientation and shakeout

Shay's day began at seven with Grace in the Crossbeam yard: company rules, the right to refuse unsafe work, the harness fitting and his first equipment inspection, the kit issue and the hours log. At ten he was on site for Tallcorn's site orientation, which covered the site rules, the muster point, first aid, traffic routes and the controlled access zones. Then Carla's crew walked him through the Ashcroft fall protection and rescue plan and showed him where the rescue kits were.

The afternoon was the shakeout. Two trucks of first-tier steel had arrived that morning, and Shay worked with Marco on the ground, checking each piece against the shipping list as it came off, laying it on dunnage in erection order with its piece mark facing out, and leaving walkways between the rows. When a truck had to reverse to the unloading area, he stood clear and watched Marco signal it in. At the end of the day he wrote his hours and the skills he had practiced in his log.

  • Lessons in play: the crew roles (lesson 1), PPE (lesson 5), site layout and shakeout (lesson 10).

Tuesday: anchor rods and the first columns

Tuesday started with a toolbox talk on the day's work: setting the first eight columns. Before any column went up, Carla and Shay walked the anchor rods with the layout drawing and a tape, checking that each group of four rods was in the right place, at the right height above the concrete and not bent. The general contractor had sent the written confirmation that the footings had cured enough to carry the steel. Two rods at one column were about 3/8 in bent; Carla did not let anyone bend them back, and called Priscilla Hahn, who had the engineer review them before that column was set. The other seven were set that morning.

Shay's job was on the ground. He helped the hooker-on attach the rigging, held a tag line on each column as it was raised, and kept his feet clear as it was landed on its anchor rods. Andy climbed each column only after its nuts were on and the column was plumbed and held, using the column-mounted SRL that had been fixed to the column on the ground before it was lifted. "Rig your fall protection on the ground whenever you can," he told him. "It's the easiest place to do it."

Worked problem

Checking the column weight

The first columns at Ashcroft are W10×49, 28 ft long, with a base plate and cap plate that together weigh about 190 lb. The column-mounted SRL bracket adds about 35 lb. What should the hooker-on use as the column's weight for choosing the rigging?

Show solution
  1. Column: 49 lb/ft × 28 ft = 1,372 lb.
  2. Plates and bracket: 190 + 35 = 225 lb.
  3. Total: about 1,597 lb.
  4. Round up: use 1,600 lb, or 1,700 lb to allow for the SRL and rigging hardware.

Answer: About 1,600 lb; the hooker-on used 1,700 lb, well within the sling and the crane chart at that radius.

  • Lessons in play: hazards of erection and column stability (lesson 9), fall protection rigged on the ground (lessons 6 and 7).

Wednesday: rain, a toolbox talk and the first lift

Wednesday morning was wet and gusty. Dwayne would not lift in the gusts, and Carla would not put connectors on wet steel. The crew spent the morning in the trailer, where Andy told the history of the trade (lesson 2), and then Grace went through the rescue kit piece by piece and had each new worker show how to open it and rig it.

By noon the rain had stopped and the wind dropped below Crossbeam's limit. The crew dried the top flanges where they would walk, and connecting began on the floor 2 beams. Shay went up for the first time, in the boom lift with Nate, to snug bolts on the beams already connected. Before going up he watched Nate do the pre-start inspection and function test; he showed him and Marco the ground controls and the emergency lowering, and he attached his lanyard to the platform anchor. They kept the platform load within its rating: two workers, tools and one bag of bolts. Nate snugged bolts with the impact wrench; Shay handed bolts and checked that each connection had all its bolts in. At the end of the afternoon, Nate let him run one nut down with the impact under his eye.

  • Lessons in play: weather limits (lesson 9), MEWPs (lesson 8), power tools (lesson 4).

Thursday: the damaged lifeline

At Thursday's start-of-shift inspection, Shay pulled out his SRL's line and found the split jacket and frayed strands near the snap hook described in lesson 7. He tagged it out and gave it to Grace, who issued a new one and sent the damaged unit to the service center. At the toolbox talk, Carla used it as an example: the line had probably been dragged over a sharp flange edge the day before, when an SRL was anchored low on the steel by someone on the bolt-up crew. Only the leading-edge rated units were to be used at foot level from then on, and the bolt-up crew's units were checked.

That afternoon, Shay worked on the second-floor beams for the first time, with Andy beside him, using a beam clamp on a bolted beam and a leading-edge SRL. He carried a short list of tools, every one tethered: spud wrench, drift pin, tape and a bolt bag tied off to the beam. His job was to help Andy hang the light beams of a bay already framed by girders, by guiding the far end with a tag line, then holding it while he ran the first bolts. When a beam came in slightly long, he did not reach in to feel the holes; he handed Andy a drift pin.

Worked problem

Is there enough clearance?

Shay's beam clamp is on the top flange of a beam at the second floor, 14 ft above the slab, about at his feet. His SRL's maker says that when anchored at foot level, the worker needs 11 ft of clearance below the working surface, including the safety margin. A stack of deck bundles 3 ft high is sitting on the slab under part of the bay. Is the clearance enough everywhere?

Show solution
  1. Clearance to the slab: 14 ft, more than 11 ft.
  2. Clearance to the top of the bundles: 14 − 3 = 11 ft, exactly the required figure, with no extra margin.

Answer: Over the open slab, yes. Over the bundles, only just. Andy had the ground crew move the bundles out from under the bay before Shay worked over them; working right at the limit of clearance leaves nothing for a swing or a longer stop.

  • Lessons in play: anchors, SRLs and clearance (lesson 7), connecting tools and tethering (lesson 3), struck-by and caught-between hazards (lesson 9).

Friday: the rescue drill and the review

Friday morning, the crew finished the first tier and began plumbing up. In the afternoon, Grace ran the rescue drill at the yard's training anchor (lesson 11). Shay hung for 5 minutes 10 seconds before he was standing in the lift basket, and felt for himself how quickly his legs went numb. He used his relief straps for the last minute and felt the difference.

At the end of the day, Andy sat down with him for the end-of-week review that Crossbeam does with every new apprentice. They went through his log: hours, the skills he had practiced and the ones still to come, and anything he had been unsure about. Andy's comments were short. He had tied off every time he was exposed. He had stopped and asked when the anchor rods looked wrong, and when a beam came in long. He had found and tagged the damaged SRL. And he had kept out from under the loads. "That's a good week," he said. "Next week, you rig."

Worked problem

Shay's hours

Shay logged these hours in his first week: Monday 9.0, Tuesday 9.5, Wednesday 8.0 (including 3.5 hours in the trailer during the rain), Thursday 9.5, Friday 9.0. How many hours does he log toward his apprenticeship, and what fraction of a 6,000-hour on-the-job requirement is that?

Show solution
  1. Total: 9.0 + 9.5 + 8.0 + 9.5 + 9.0 = 45.0 hours.
  2. Fraction: 45 ÷ 6,000 = 0.0075, about 3 in 400.

Answer: All 45 hours count as employment hours, including the toolbox talk and rescue training time, as his program allows; the skills log is what shows his progress, and it already had a dozen entries.

What made it a good week

Nothing went wrong in Shay's first week. That was not luck. Look at what the crew did:

  • The steel was laid out and shaken out so that every piece was handled once.
  • The anchor rods were checked before any column was set, and the bent rods went to the engineer, not to a hammer.
  • Fall protection was rigged on the ground, before the steel was lifted, wherever possible.
  • Work stopped for wind and rain, and steel was dried before anyone walked it.
  • The lift was inspected, the ground person knew the controls, and the platform load was within its rating.
  • Every tool at height was tethered and the ground below was controlled.
  • A damaged SRL was caught at inspection, tagged out and replaced, and the cause was found and fixed.
  • Clearance was checked, and the bundles were moved rather than accepted at the limit.
  • The rescue plan was practiced and timed, and the new worker felt for himself why speed matters.

Each of these is an ordinary step. Together they are how an erection crew goes home whole every day. Shay's next weeks would bring rigging and signaling (IRW-120), and later reinforcing steel (IRW-130) and the steel erection courses.

Questions to think about

  • What could have happened if Carla had let the crew bend the anchor rods back and set the column?
  • Why did Andy want the column SRLs fixed on the ground before the columns were lifted?
  • What should Shay do if the lift were parked at the far end of the site when his crew started work at the roof?
  • Why does the damaged SRL matter to the whole crew and not just to Shay?
  • How did the weather on Wednesday change the hazards, and what did the crew do about each one?

Looking ahead

By the end of October, the Ashcroft frame was topped out, with the last roof beam set on Friday, October 23, and by November 13 the deck and the detailing were done. Shay had rigged dozens of pieces under supervision, worked on all three levels with Andy, and taken his turn in two more rescue drills. The concrete on the deck is planned for late November, after Crossbeam's work is complete, and Shay's next job, a parking structure with heavy reinforcing, is planned to start in December.

Andy's own summary for Shay was shorter. Do the boring things every time, he said: inspect, tie off, tether, stay out from under, stop and ask. The steel will teach you the rest.

Common mistakes

  • MistakeTreating a quiet week as luck.

    InsteadA quiet week is the result of ordinary steps done every time.

  • MistakeFixing bent anchor rods on the spot.

    InsteadBent or damaged anchor rods go to the engineer of record.

  • MistakeRigging fall protection at height when it could have been done on the ground.

    InsteadFix SRLs, lines and anchors to the steel before it is lifted wherever possible.

  • MistakeAccepting clearance exactly at the limit.

    InsteadMove the obstruction or change the method; leave a margin.

  • MistakeSkipping the end-of-week review.

    InsteadReview the log, the skills and the questions every week while they are fresh.

Summary and key terms

  • Shay's first week used every topic in this course: crews, tools, PPE, fall protection, lifts, hazards, site layout and rescue.
  • The anchor rods were checked, and damaged rods went to the engineer.
  • Fall protection was rigged on the ground where possible and used 100 in 100 of the time.
  • Weather stopped work until conditions were within limits.
  • A damaged SRL was found at inspection and its cause fixed.
  • The rescue drill met the six-minute target and showed why speed matters.
Toolbox talk
A short safety meeting at the start of a shift about the day's work and hazards.
Plumbing up
Adjusting a frame so its columns are vertical, then fixing it in that position.
Engineer of record
The engineer responsible for the structural design of the building.
Skills log
The apprentice's record of the tasks and skills practiced and signed off.
End-of-week review
A meeting between an apprentice and a mentor to go over the week's work and log.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. Why did Carla stop the column with bent anchor rods?

    Show answer

    Modified or damaged anchor rods need the engineer of record's approval before steel is set.

  2. What does a W10×49 column 28 ft long weigh?

    Show answer

    49 × 28 = 1,372 lb.

  3. Why were the deck bundles moved from under the bay?

    Show answer

    They left clearance exactly at the SRL's limit, with no margin.

  4. How did the crew control the hazards of the wet, windy morning?

    Show answer

    Stopped lifting and connecting, waited for wind to drop and dried the steel.

  5. What fraction of 6,000 hours is 45 hours?

    Show answer

    0.75 in 100.

Lesson quiz · 5 questions