GEOM-420 · Lesson 4 of 12 · 21 min

Earthwork quantities

Moving earth is often the largest single cost on a road or site job, and the contractor is paid by the cubic yard. The quantities in the tender come from the designer's model; the quantities that are paid come from the surveyor's measurements of what was actually moved. Both depend on the same methods: cross-sections at regular stations, areas of cut and fill on each section, volumes between sections, and a running balance that shows where material can be moved from cut to fill and where it must be brought in or hauled away. This lesson covers those methods, the corrections that make them honest, and the surface-to-surface methods that modern software uses.

Cross-sections

A cross-section is a slice through the ground and the design at right angles to the alignment, at a given station. The original ground line comes from the design survey's terrain model or from field shots taken across the line; the design template comes from the road's typical section: the subgrade width, the cross slope, the side slopes in cut and fill, and the ditches. Where the template is below the ground there is cut; where it is above there is fill. The area of each, in square feet, is computed from the coordinates of the section's outline, usually by the same shoelace formula used for parcel areas in GEOM-410.

Three cross-sections along the highway approach: one in full cut with the template below the ground and ditches, one in mixed cut and fill, and one in full fill with side slopes down to the ground; cut areas shaded one color and fill areas another.
Cross-sections in cut, mixed and fill. Each section gives an end area of cut and an end area of fill.

For the highway approach near the canal bridge, Theo cuts sections every 50 ft from 85+00 to 90+00, with extra sections where the ground changes sharply and at the beginning and end of each cut and fill. Field crews check a few sections on the ground before construction, because the end areas are only as good as the original ground they are measured from.

Volumes between sections

The simplest estimate of the volume between two sections is the average of their end areas times the distance between them. The average end area method is used almost everywhere for payment, because it is simple and agreed, but it is exact only when the two end areas are equal. When they differ, the true shape between them is a prismoid, and the prismoidal formula, which uses a middle area as well as the two ends, gives the exact volume for a solid whose sections change smoothly.

\[V_{\text{ea}} = \frac{d}{2}\,(A_1 + A_2) \qquad V_{\text{pr}} = \frac{d}{6}\,(A_1 + 4A_m + A_2)\]

The middle area \(A_m\) is the area of a section halfway between the two ends; it is not the average of the end areas, but must be computed from the dimensions at the middle. The difference between the two volumes is the prismoidal correction. It is usually small, and it is negative for sections that grow or shrink in both width and depth, which is why the average end area method tends to overestimate.

Earthwork in the US is usually measured in cubic yards. A volume in cubic feet is divided by 27 to give cubic yards. Contracts usually specify that the average end area method is used for payment, with or without a prismoidal correction, and agree in advance on the section interval and on who provides the original ground.

Shrink and swell

A cubic yard of earth is not the same amount of material in every state. In the ground, it is bank volume. Dug and loaded into a truck, it swells and takes up more room, the loose volume. Placed and compacted in a fill, it usually takes less room than it did in the bank, the compacted volume. Rock is the exception: it swells and stays swollen. The ratios depend on the soil and the compaction, and the geotechnical report gives them. For balancing cut against fill, the cut volumes are multiplied by a shrinkage factor, so that both are in compacted terms.

\[V_{\text{compacted}} = V_{\text{bank}} \times s \qquad V_{\text{loose}} = V_{\text{bank}} \times (1 + \text{swell})\]

For the clay and silt of the coulee slopes, the geotechnical report gives a factor of 0.88: each bank cubic yard of cut makes 0.88 of compacted fill. That 12 % loss is a large effect on a job with tens of thousands of cubic yards, and getting it wrong is a common reason why a job that balanced on paper needs borrow material at the end.

The mass haul diagram

The mass haul diagram is the earthwork planner's tool. Its ordinate at each station is the running total of adjusted cut minus fill from the start of the job: it rises through cut, falls through fill, peaks where cut changes to fill, and dips where fill changes to cut. Any horizontal line drawn across it cuts the curve at two points between which cut and fill balance, and the material can be moved from one to the other. The final ordinate tells whether the whole job has a surplus to waste or a shortage to borrow.

End-area volumes, shrinkage, the mass haul ordinates and a prismoidal check for the highway approach.
# Earthwork for the highway approach: average end area, prismoidal correction and mass haul (feet, cubic yards)
sta  = [8500, 8550, 8600, 8650, 8700, 8750, 8800, 8850, 8900, 8950, 9000]
cut  = [133, 200, 270, 332, 242, 110,  33,   0,   0,   0,   0]   # end areas, ft2
fill = [  0,   0,   0,   0,  19,  69, 160, 262, 334, 297, 174]
shrink = 0.88                 # 1 yd3 of cut makes 0.88 yd3 of compacted fill
mass, tot_c, tot_f = 0.0, 0.0, 0.0
print(" station   cut yd3  fill yd3   adj cut   mass ordinate")
print(f"{sta[0]//100}+{sta[0]%100:02d}        -         -         -          0")
for i in range(1, len(sta)):
    d = sta[i] - sta[i - 1]
    vc = d * (cut[i - 1] + cut[i]) / 2 / 27
    vf = d * (fill[i - 1] + fill[i]) / 2 / 27
    mass += vc * shrink - vf; tot_c += vc; tot_f += vf
    print(f"{sta[i]//100}+{sta[i]%100:02d}  {vc:8.1f}  {vf:8.1f}  {vc*shrink:8.1f}  {mass:10.1f}")
print(f"total cut {tot_c:.0f} yd3 (bank), total fill {tot_f:.0f} yd3, balance {mass:+.0f} yd3 after shrinkage")

# Prismoidal check on the 85+50 to 86+00 segment, with a measured middle area of 232 ft2
A1, Am, A2, d = 200, 232, 270, 50
v_ea = d * (A1 + A2) / 2 / 27; v_pr = d * (A1 + 4 * Am + A2) / 6 / 27
print(f"average end area {v_ea:.1f} yd3, prismoidal {v_pr:.1f} yd3, correction {v_pr - v_ea:+.1f} yd3")
Output
 station   cut yd3  fill yd3   adj cut   mass ordinate
85+00        -         -         -          0
85+50     308.3       0.0     271.3       271.3
86+00     435.2       0.0     383.0       654.3
86+50     557.4       0.0     490.5      1144.8
87+00     531.5      17.6     467.7      1594.9
87+50     325.9      81.5     286.8      1800.3
88+00     132.4     212.0     116.5      1704.7
88+50      30.6     390.7      26.9      1340.9
89+00       0.0     551.9       0.0       789.0
89+50       0.0     584.3       0.0       204.8
90+00       0.0     436.1       0.0      -231.3
total cut 2321 yd3 (bank), total fill 2274 yd3, balance -231 yd3 after shrinkage
average end area 435.2 yd3, prismoidal 431.5 yd3, correction -3.7 yd3

The table shows the approach in cut up to about 87+50, peaking in the mass haul at 1,800 yd³, and then in fill to 90+00. In total there are 2,321 yd³ of bank cut and 2,274 yd³ of fill. After shrinkage, the cut makes only 2,043 yd³ of compacted fill, so the job ends 231 yd³ short. The contractor will need borrow, or the designers may lower the grade slightly on the fill side; Ruth sends the table to the engineer with that note. The prismoidal check on the 85+50 to 86+00 segment, with a measured middle area of 232 ft², gives 431.5 yd³ instead of 435.2 yd³, a correction of −3.7 yd³ or under 1 %.

A mass haul diagram for the approach: the ordinate rises through the cut to a peak near the middle and falls through the fill, ending below zero; a balance line crosses it at two points, and the shortfall at the end is marked as borrow.
The mass haul diagram for the approach. The curve ends below zero: the job needs borrow.

On a longer job the mass haul diagram also shows haul distance. The horizontal distance between the two points where a balance line crosses the curve is the longest haul for that balanced section, and the area between the curve and the line is the total haul in yard-stations. Contracts often include a free-haul distance, within which hauling is part of the excavation price, and pay overhaul beyond it. The surveyor's diagram is then the basis for payment, and both sides check it.

Worked problem

Average end area and prismoidal volume

Two cut sections 50 ft apart have areas 340 ft² and 190 ft². The middle section, computed from its own dimensions, is 255 ft². Find the average end area and prismoidal volumes in cubic yards.

Show solution
  1. \[V_{\text{ea}} = \frac{50}{2}(340 + 190)/27 = 490.7\ \text{yd}^3\]
  2. \[V_{\text{pr}} = \frac{50}{6}(340 + 4 \times 255 + 190)/27 = 478.4\ \text{yd}^3\]

Answer: The average end area overestimates by about 3 %, a typical size for sections that change sharply.

Surface-to-surface volumes

Modern software can also compute volumes directly between two terrain models: the original ground and the design, or the ground before and after a day's excavation. It builds a third surface of differences and integrates it, triangle by triangle or over a fine grid. The result does not depend on a section interval, and it handles irregular shapes such as stockpiles, ponds and the pump station's excavation better than sections do. Its accuracy depends on the density and quality of both surfaces, and especially on breaklines at the edges of the work.

For payment, surface methods are increasingly accepted, but a contract must say so, and both parties must agree on the surfaces. Ruth's crew uses surface methods for progress estimates on the pump station's excavation, where the shape is too irregular for sections, and drone photogrammetry or lidar (GEOM-310, GEOM-350) for the stockpiles of topsoil and gravel. For the highway, the contract specifies sections every 50 ft and average end area, so that is what is used for payment, and the surface method is a cross-check.

Field measurement of quantities

Quantities for payment must be measured, not assumed from the design. Before stripping, the crew surveys the original ground, or the contract accepts the design survey as the original ground; after stripping topsoil, it surveys again, so that topsoil and common excavation can be paid separately; after excavation and before backfill, it surveys the final surface. Each survey is done from the same control, with the same coding and the same section stations, so that the surfaces can be compared. Disputes are rare when the surveys are well documented, because both sides can see exactly what was measured and when.

Excavations are dangerous places for survey crews. Before anyone enters a trench or the pump station's pit to take a shot, the sides must be sloped, benched or shored as the OSHA excavation standard in 29 CFR 1926 Subpart P require, and the crew stays clear of the swing radius of excavators and the path of haul trucks. A survey pole held at the edge of an excavation by someone standing well back is better than a perfect shot taken from the bottom of an unprotected trench.

Topsoil, rock and unsuitable material

Not all excavation is the same, and the contract usually pays for it differently. Topsoil is stripped first and stockpiled for later reuse on slopes and ditches, so its volume is measured separately: the crew surveys the ground before and after stripping, or the contract sets a nominal stripping depth. Rock excavation costs far more than common excavation, so where the geotechnical report expects rock, the crew surveys the top of rock once it is exposed and computes rock volumes separately. Unsuitable material, such as wet clay or organic soil that cannot be used in a fill, is removed below the design subgrade and replaced, and the survey must record the bottom of every such excavation before it is backfilled.

Each of these classes needs its own surfaces and its own volumes, and the classification must be agreed on site with the contractor and the engineer's inspector when the material is exposed, not argued about afterwards. Ruth's crew photographs every exposed rock surface and every unsuitable excavation with a scale and a location reference, and the inspector initials the field record. That small habit prevents most of the disputes that earthwork payment can cause.

Borrow pits have their own measurement too. When the approach needs the 232 yd³ (about 230) of borrow shown by the mass haul diagram, the material will come from a pit the contractor opens nearby or from a commercial source. If it comes from a pit, the crew surveys the pit before and after, and the volume removed, adjusted by the shrinkage factor, should agree with the shortfall the diagram predicts. A large difference in either direction means that something in the quantities or the factors needs to be looked at again.

Common mistakes

  • MistakeAveraging end areas to get the middle area for the prismoidal formula.

    InsteadCompute the middle area from the dimensions at the middle section.

  • MistakeBalancing bank cut directly against compacted fill.

    InsteadApply the shrinkage (or swell) factor so both are in the same terms.

  • MistakeMeasuring final quantities from the design rather than the ground.

    InsteadSurvey the ground before and after each stage of work.

  • MistakeUsing sections too far apart over rough ground.

    InsteadAdd sections at breaks in the ground and at the ends of each cut and fill.

Summary and key terms

  • Cross-sections give end areas of cut and fill at each station.
  • Average end area volume is d(A1 + A2)/2; the prismoidal formula adds a middle area and is exact for smooth solids.
  • Bank, loose and compacted volumes differ; shrinkage and swell factors convert between them.
  • The mass haul diagram's ordinate is the running total of adjusted cut minus fill; its end value shows surplus or shortage.
  • Surface-to-surface methods compute volumes between terrain models and suit irregular shapes.
  • Payment quantities come from documented surveys of the ground before and after each stage.
End area
The area of cut or fill on a cross-section.
Average end area method
Volume between two sections as the mean of their areas times the distance between them.
Prismoidal formula
Volume as d/6 times the sum of the end areas and four times the middle area.
Shrinkage factor
The ratio of compacted fill volume to the bank volume it came from.
Mass haul diagram
A graph of cumulative adjusted cut minus fill along the alignment.
Borrow
Material brought in from outside the job to make up a shortage of fill.
Free haul
The haul distance included in the excavation price, beyond which overhaul is paid.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. Sections 100 ft apart have cut areas 160 and 230 ft². What is the average end area volume in cubic yards?

    Show answer

    100 × 390/2/27 = 722.2 yd³.

  2. A cut of 5,000 yd³ bank with a shrinkage factor of 0.85 is placed in a fill of 4,500 yd³. Is there a surplus or a shortage?

    Show answer

    5,000 × 0.85 = 4,250 yd³ compacted, a shortage of 250 yd³.

  3. What does a peak in the mass haul diagram mean?

    Show answer

    A point where cut changes to fill.

  4. Why must the middle area in the prismoidal formula be measured rather than averaged?

    Show answer

    Averaging the end areas would give the same result as the average end area method.

  5. When are surface-to-surface volumes better than sections?

    Show answer

    For irregular shapes such as stockpiles and pits, given good surfaces with breaklines.

Lesson quiz · 5 questions

Score 60% or more to complete this lesson.