PWR-320 · Lesson 12 of 12 · 26 min
A turbine startup walkthrough
▶ Video coming soon A video version of this lesson is on the way.
Keswold's outage schedule ended with the steam turbine back on load and Marrowby Foods back on Keswold's steam by the morning of Thursday, October 22, 2026. Okonkwo had arranged his days off to be there for the last part, and Anselm put him beside Liesl Brannagan in the control room for the steam turbine's first roll on Wednesday, October 21. "You've read the procedure, you've seen the parts, you watched the trip tests," Anselm said. "Now watch it all happen in order, and keep asking why."
This lesson follows that startup from the gas turbine's light-off to full load with the extraction in service. Each step draws on an earlier lesson: the turning gear and warming of lesson 5, the protection proven in lesson 6, the condenser vacuum of lesson 7, the gas turbine start of lesson 8, the HRSG and bypass of lesson 9, the synchronizing of lesson 10 and the vibration records of lesson 11. It closes with the debrief and a set of mixed questions in the style of the Third Class examinations.
The plan
The startup plan, issued by Anselm the week before and reviewed with each shift, fitted the turbine's cold start curve to the plant's commitments:
- Tuesday, October 20: condenser and auxiliaries in service overnight; gas turbine purge and light-off at dawn; HRSG warmed with its steam through the bypass to the condenser.
- Wednesday, October 21: steam turbine rolled off turning gear in the morning, run up with the cold start holds, and put through its overspeed tests after its first time at rated speed; then shut down onto turning gear overnight, because the grid operator had approved its return to the market from six the next morning.
- Thursday, October 22: hot restart before dawn, synchronize, load, and put the extraction in service so that Marrowby could shut down the rented package boiler it had used during the outage.
The plan listed the hold points, the steps at which the shift supervisor had to sign before the next began, and the abort criteria: limits on vibration, eccentricity, differential expansion, thrust and steam-to-metal mismatch at which the turbine would be tripped and the cause investigated before another attempt.
Tuesday: auxiliaries, vacuum and the gas turbine
The night shift on Monday and Tuesday brought the auxiliaries into service in the order the procedure gave. Cooling tower and circulating water pumps came first, then the condensate pumps on recirculation and the HRSG feed pumps, with the deaerator heated by auxiliary steam from the plant's small auxiliary boiler. With the rotor turning on turning gear since October 14 and eccentricity steady at 8 µm above its baseline, gland sealing steam was applied at about 03:00 on Tuesday, and the hogging ejector began pulling vacuum. By 04:15 the condenser was at about 20 kPa absolute, and the holding ejector was put in service and the hogging ejector shut off.
The gas turbine start began at 05:00. The static frequency converter cranked the rotor to purge speed and held it while the required volumes of air swept through the combustors, the exhaust duct and the HRSG. At light-off the flame detectors proved flame in both monitored cans within a few seconds, the crossfire tubes carried it round the other eight, and the exhaust temperature spread settled within its normal band as the unit accelerated. The converter dropped out at self-sustaining speed, the unit reached full speed no load, and it was synchronized at 05:42 and held at a low load with its inlet guide vanes partly closed to keep its exhaust temperature up.
Over the day the HRSG drum pressure rose at the rate its drum's thermal stress limits allowed. All of its steam went through the HP bypass valve and desuperheater to the condenser; the steam turbine's stop valves stayed shut, and the drains on the main steam line and turbine valve chest stayed open. By evening the steam at the turbine stop valves was at 3,000 kPa absolute and 350 °C, with about 116 K of superheat, comfortably above the start's minimum.
Wednesday morning: the roll
At 07:30 on Wednesday Liesl worked through the pre-roll checklist with Okonkwo reading the items aloud:
| Check | Reading | Requirement |
|---|---|---|
| Turning gear time | Seven days continuous | At least 4 h |
| Eccentricity | 8 µm above baseline, steady | No more than 25 µm above baseline |
| Bearing header oil pressure and temperature | Normal; oil 42 °C | Within range; oil at least 35 °C |
| Jacking oil and control fluid pressure | Normal | Within range |
| Condenser pressure | 9.5 kPa absolute | Below 20 kPa absolute |
| Main steam at stop valves | 3,000 kPa, 350 °C | Superheat at least 55 K |
| First stage metal temperature | 95 °C | Cold start curve applies below 150 °C |
| Differential expansion, thrust, casing growth | At cold values | Within limits |
| Drains | Open | Open |
| Trips armed, bypasses removed | Confirmed, permit log checked | No active bypasses |
Anselm signed the hold point at 08:05. Liesl latched the trip system, opened the stop valves, and selected the turbine controller's run-up program with a target of 500 r/min. At 08:10 the governor valves cracked open; the first stage shell temperature began to rise, and the turning gear disengaged automatically as the rotor accelerated past its speed.
At 500 r/min the controller held. Anselm and a mechanic went to the turbine with a listening rod while Liesl read out vibration, bearing metal temperatures, thrust and differential expansion. Nothing was out of the ordinary. As the procedure required for a first roll after a major inspection, Liesl then tripped the turbine from the control room and the team listened along the casing as it coasted down. A rub is easiest to hear with no steam flowing, and a rotor that slows unusually fast is dragging on something. The coast-down was quiet, its time normal, and at 08:35 the turbine was reset and rolled again.
Through the critical speeds
From the rub check the controller accelerated the turbine at 200 r/min per minute towards the heat soak speed. Okonkwo watched the vibration display as the speed crossed the generator's critical: bearing 3 and 4 vibration rose to a peak at about 1,160 r/min and fell away again, the phase swinging through about 180°. At about 1,840 r/min the turbine bearings did the same as the turbine rotor passed its own first critical. Liesl recorded the peak amplitudes and speeds on the startup log: each within a few r/min and a few micrometres of the previous start's record. A rotor whose critical speed peak has grown, or moved, has changed.
Worked problem
How long the run-up takes
Keswold's turbine accelerates from the 500 r/min rub check to 3,600 r/min at 200 r/min per minute, with one heat soak hold of 98 minutes at 2,000 r/min. How long is the acceleration time, and how long the whole run-up from the second roll?
Show solution
- Acceleration time:
- \[t = \frac{3{,}600 - 500}{200} = 15.5 \text{ min}\]
- Total, adding the hold:
- \[15.5 + 98 = 113.5 \text{ min}\]
Answer: Less than a quarter of an hour is spent accelerating; most of a cold run-up is spent waiting for the metal to heat. That is why the heat soak hold, not the acceleration rate, decides when a cold turbine reaches speed, and why a hot start, needing little heat soak, is so much faster.
Heat soak
The turbine reached 2,000 r/min at 08:52 and held there. The heat soak's purpose was to warm the rotor right through before load: the procedure's release conditions were a first stage metal temperature of at least 250 °C with its rate of rise inside the curve, differential expansion settled and casing growth tracking the expected value. Liesl raised the main steam temperature slowly as the metal followed it, keeping the first stage steam-to-metal mismatch inside its limit. The casing growth indicator at the front standard crept forward steadily; on Okonkwo's question, Anselm walked him down to watch the sliding base move against its scale.
At 10:30 the conditions were met, Anselm signed the second hold point, and the controller took the turbine to 3,600 r/min, arriving at 10:38. Liesl checked that the governor held the speed steady, that the exhaust hood temperature was low and its sprays not needed, and that the gland seals, condenser vacuum and air removal were stable.
The overspeed tests
Because the mechanical overspeed bolt had been removed and reset during the outage, and the electronic overspeed system's probes had been disturbed, both had to be proven by real overspeed tests before the unit returned to service. The test procedure, carried out under a permit, began at 13:00 after the turbine had run for more than two hours at speed, as the manufacturer requires, so that the rotor was thoroughly warm and its material at its tougher, warmer condition.
- Electronic channels: in the controller's overspeed test mode, Liesl raised the speed reference above rated speed in small steps while the technician watched each channel's trip output. The voted trip acted at 3,960 r/min, its set point; the turbine tripped, the stop and governor valves closed, and it coasted down to about 3,000 r/min before being reset and returned to 3,600.
- Mechanical bolt: with the electronic trip temporarily raised above the mechanical setting under the permit, and an operator standing at the hand trip, the speed was raised again. The bolt flew out and tripped the turbine at 3,958 r/min. The manufacturer's procedure requires two consecutive trips within the tolerance band; the second, after reset, came at 3,962 r/min.
Both mechanical trips were within about 0.1 in 100 of the 3,960 r/min setting: 3,958 ÷ 3,600 = 1.0994, and 3,962 ÷ 3,600 = 1.1006, or 109.9 and 110.1 in 100 of rated speed. The electronic trip setting was restored and verified, the permit was closed, and the test results were entered in the turbine's records, where the insurer would review them.
After the last trip the turbine was allowed to coast down all the way, so that a complete coast-down curve with its critical speed peaks could be recorded for comparison with the next start, and was then put back on turning gear. The steam was returned to the bypass. Overnight the turning gear kept the rotor straight while it stayed hot.
Thursday: the hot restart
At 05:00 on Thursday the first stage metal was still at about 330 °C, so the turbine's hot start curve applied. The HRSG had been brought to full pressure and its steam temperature raised to 465 °C overnight, because cold steam on a hot turbine was the one thing the hot start curve forbade. The pre-roll checks were repeated, the turbine rolled at 05:30, and with no heat soak needed it accelerated straight through its critical speeds to 3,600 r/min, a run-up of about twenty minutes in all.
Synchronizing was done with the automatic synchronizer, which Liesl supervised. The synchroscope pointer crept round in the fast direction as the synchronizer trimmed the speed; the generator voltage was matched within a fraction of the system's; and at 06:12 the breaker closed just before twelve o'clock. The controller immediately took a block load of 1.5 MW, so that the turbine would not run unloaded on the grid with its last stages churning, and the drains closed as the steam flow rose.
Worked problem
The loading time
The hot start curve allows loading at 0.6 MW per minute from the 1.5 MW block load to 18 MW, with a 15 minute hold at 9 MW. How long does loading take?
Show solution
- Ramp time:
- \[t = \frac{18 - 1.5}{0.6} = 27.5 \text{ min}\]
- Total, with the hold:
- \[27.5 + 15 = 42.5 \text{ min}\]
Answer: About three quarters of an hour from synchronizing to full load, which on a cold turbine could take several hours.
The extraction could not be put in service until the low-pressure section was carrying enough steam to stay cool with the extraction valve throttling, which the extraction performance diagram set at about 8 MW. At the 9 MW hold, Liesl put the extraction pressure controller in service and slowly opened the extraction isolating valve, and Keswold's operators called Marrowby's boiler room to begin their changeover. Over the next half hour Marrowby's steam demand moved from their rented package boiler to Keswold, the extraction flow rose to its full 6.0 kg/s (48,000 lb/h), and the decoupled controls held the megawatts steady while it did. By 07:20 the unit was at 18 MW with the extraction in service, and Marrowby shut their package boiler down.
The first day's checks
The outage procedure required a set of checks in the first day at load, each recorded and compared with the pre-outage baseline:
- Vibration at all four bearings, at several loads. All were normal except bearing 3, which had settled at 52 µm, higher than before; lesson 11 followed what Ingeborg made of it.
- Air in-leakage at the ejector vent, measured in the afternoon. It was slightly higher than before the outage, and a tracer gas survey on the following day found a leaking flange gasket on a low-pressure heater drain line, retightened the same week.
- Condenser performance: the UA value had recovered after the October 3 cleaning.
- Bearing temperatures, thrust position and oil analysis, with an oil sample sent to the laboratory to confirm that no flushing debris remained.
- Heat balance and section efficiency, giving the new baseline Ingeborg used on November 13.
The debrief
Anselm held the outage debrief the following week and invited Okonkwo to listen. The startup had met its schedule. The extraction non-return valve's slow solenoid, found on October 19, had been the one equipment problem that could have mattered; it went into the debrief as the reason the valve timing test stays in the procedure. Two items were added to the startup procedure: a reminder to confirm the rented package boiler's changeover plan with Marrowby the day before, and a column in the startup log for the gland steam temperature, which Liesl had found herself tracking by hand.
Okonkwo had one question left, and asked it at the end: what Anselm would do differently if the overspeed test had tripped outside its tolerance. "Stop," Anselm said. "Shut down, put it on turning gear, get the manufacturer on the phone, and find out why before we spin it again. A trip that's high is a rotor that's been closer to failure than we meant. Schedules can wait." Okonkwo wrote that on the last page of the notebook he had started on September 18.
Mixed problem practice
These questions draw on the whole course, in the style of the Third Class examinations.
Practice problems
Work each problem on paper first, then reveal the answer to check.
An impulse stage has blade speed 200 m/s and a change of whirl velocity of 370 m/s. Its jet speed is 420 m/s. Find the work and diagram efficiency.
Show answer
w = 74.0 kJ/kg; η = 2 × 74,000 ÷ 420² = 0.839.
A 30 MW unit with 4 in 100 droop sees a frequency rise of 0.12 Hz. Find its change in output with no deadband.
Show answer
−(0.12 ÷ 60) ÷ 0.04 × 30 = −1.5 MW.
A condenser at 7.5 kPa absolute receives 14 kg/s at 2,330 kJ/kg; h_f = 168.8 kJ/kg. Find the duty and the cooling water flow for a 9 K rise.
Show answer
Q = 14 × 2,161.2 = 30,260 kW; 30,260 ÷ (4.19 × 9) = 802 kg/s.
Find the ideal Brayton efficiency for r_p = 14.
Show answer
14^0.2857 = 2.126; 1 − 1 ÷ 2.126 = 0.530.
A 40 MVA, 13.8 kV generator carries 32 MW at 0.85 power factor. Find its current.
Show answer
S = 32 ÷ 0.85 = 37.6 MVA; I = 37.6 × 10⁶ ÷ (√3 × 13,800) = 1,575 A.
A turbine's mechanical overspeed bolt trips at 3,970 r/min on a 3,600 r/min machine. What is that as a fraction of rated speed?
Show answer
3,970 ÷ 3,600 = 1.103.
Common mistakes
MistakeStarting the steam turbine as soon as the HRSG makes steam.
InsteadSend the steam through the bypass until its pressure, temperature and superheat suit the turbine metal.
MistakeHolding the turbine at a speed inside a critical band to watch the vibration peak.
InsteadAccelerate through critical bands and record the peak; hold only at the listed speeds.
MistakeRunning an overspeed test on a turbine that has only just reached speed.
InsteadRun at speed long enough for the rotor to be thoroughly warm first, as the manufacturer specifies.
MistakeLetting the turbine run unloaded on the grid after synchronizing.
InsteadTake a block load at once so the last stages do not churn and overheat.
MistakePutting the extraction in service at very low load.
InsteadWait until the low-pressure section carries enough steam to stay cool, as the extraction performance diagram shows.
Summary and key terms
- Auxiliaries, vacuum and gland sealing come before steam; the HRSG's steam goes through the bypass until it suits the turbine.
- A cold start rolls to a rub check, accelerates through critical speeds, heat soaks, and reaches rated speed under hold point signatures.
- Overspeed tests prove the electronic and mechanical trips after they have been disturbed, with the rotor warm.
- A hot start needs hot steam, little heat soak and a fast run-up.
- After synchronizing, a block load is taken at once; loading follows the curve and the extraction goes in above its minimum load.
- First-day checks and a debrief set new baselines and improve the procedure.
- Hold point
- A step in a procedure at which a responsible person must sign before the next step begins.
- Abort criteria
- Limits at which a startup is stopped and the cause investigated before another attempt.
- HP bypass
- A valve and desuperheater that send HRSG or boiler steam around the turbine to the condenser.
- Block load
- An initial step of load taken immediately after synchronizing.
- Overspeed test
- A test in which a turbine is run above rated speed to prove that its overspeed trips act at their settings.
- Coast-down curve
- A record of speed and vibration against time as a tripped turbine slows to rest.
- Debrief
- A review after an outage or event to record what went well and what to change.
Lesson quiz · 5 questions