HSE-251 · Lesson 12 of 12 · 27 min

Capstone: a spill prevention and response plan for a fleet maintenance yard

This capstone brings the course together by building a spill prevention and response plan for an invented workplace: Northwind Fleet Services, a company that maintains and fuels about 60 delivery trucks and a few loaders at a single yard. The company, the site and the numbers are invented for teaching, but the problems are real ones found at many yards. Work through each step, then compare your thinking with the worked answers.

The site

Northwind's yard covers about two hectares on the edge of a small Ontario town. It has a maintenance shop with four service bays, a parts room and a small chemical storage room; a fuel island with a 25,000 L aboveground diesel tank and a 5,000 L gasoline tank in a shared concrete dike; a used oil tank of 2,000 L beside the shop; a drum storage pad; a vehicle wash bay with an oil-water separator; and a paved parking area. Storm drains in the parking area lead to a ditch along the rear fence, which flows to Cedar Creek, a small stream with brook trout, about 150 m away. The shop floor drains connect to the wash bay separator and then to the municipal sanitary sewer. There is a domestic well on a neighbouring property 120 m from the fuel island, and the soil is sandy.

A site plan of the Northwind Fleet yard showing the maintenance shop with chemical room, the fuel island with two tanks in a dike, the used oil tank, the drum pad, the wash bay and oil-water separator, parking with storm drains, the rear ditch leading to Cedar Creek 150 m away, a neighbouring well 120 m from the fuel island, and spill kit locations marked at the fuel island, shop, drum pad, wash bay and gate.
The invented Northwind Fleet yard, with spill kit locations.

Step 1: inventory and risk assessment

The first step is to list every substance and every place it could escape, then rate the risks. The inventory includes diesel, gasoline, used oil, new engine and hydraulic oils in drums, antifreeze, windshield washer fluid, brake cleaner, parts washer solvent, battery acid in stored batteries, diesel exhaust fluid, and wash bay detergents. The table summarizes the main sources and pathways, and the code ranks them.

Main spill sources at the Northwind yard.
SourceLargest credible spillPathwayReceptor
Fuel delivery overfillSeveral hundred litresFuel pad to storm drain; sandy soilCedar Creek; neighbour's well
Diesel tank failure25,000 L (into dike)Dike if intact; soil and ditch if notCreek, well
Drum puncture on pad205 LPad edge to gravel and storm drainCreek
Truck fuel tank leak in parking100 to 300 LPavement to catch basinsCreek
Shop spillsSmall to moderateFloor drains to separator and sewerSewer treatment plant
Wash bay separator bypassChronic oil dischargeSanitary sewerTreatment plant
# Ranking Northwind's spill risks: likelihood (1-5) x consequence (1-5). Scores are a matter of opinion.
risks = [
    ("Fuel delivery overfill",          3, 5),
    ("Truck fuel tank leak in parking", 4, 4),
    ("Drum puncture on drum pad",       3, 4),
    ("Hydraulic hose burst in yard",    4, 3),
    ("Wash bay separator bypass",       3, 3),
    ("Diesel tank failure (in dike)",   1, 5),
    ("Shop chemical spill",             3, 2),
]
for name, l, c in sorted(risks, key=lambda r: r[1] * r[2], reverse=True):
    s = l * c
    print(f"{name:<34} {s:>2}  {'HIGH' if s >= 15 else 'medium' if s >= 8 else 'low'}")
Output
Truck fuel tank leak in parking    16  HIGH
Fuel delivery overfill             15  HIGH
Drum puncture on drum pad          12  medium
Hydraulic hose burst in yard       12  medium
Wash bay separator bypass           9  medium
Shop chemical spill                 6  low
Diesel tank failure (in dike)       5  low

The ranking points to three priorities: fuel deliveries, leaks from trucks parked over storm drains, and the drum pad. A tank failure has a severe consequence but is unlikely, and the dike is the control, so its integrity and rainwater management matter. The wash bay separator is a chronic source that needs maintenance rather than emergency response.

Step 2: prevention

Prevention measures follow from the risks. For the fuel island: check the dike capacity, keep its drain valve locked and inspect rainwater before release; fit and test high-level alarms on both tanks; require an independent level check and an attended delivery with the supplier; label fill pipes; put a spill kit and a drain cover at the island; and fit an insert or valve on the nearest catch basin. For the parking area: inspect trucks for leaks during each service, use drip pans under leaking vehicles until repaired, and mark storm drains with a no-dumping message. For the drum pad: add spill pallets, a roof and bollards; keep only working stock outside; and move the pad away from the catch basin if possible. For the wash bay: pump out and inspect the separator on a schedule and keep records.

Worked problem

Checking the shared dike

The diesel tank holds 25,000 L and the gasoline tank 5,000 L. The dike is 9 m by 6 m with walls 0.6 m high. Is it big enough under the common Canadian rule (the larger of 110 % of the largest tank, or the largest tank plus 10 % of the others)?

Show solution
  1. 110 % of 25,000 L = 27,500 L. Largest plus 10 % of others = 25,000 + 500 = 25,500 L. The requirement is 27,500 L.
  2. Gross dike volume = 9 × 6 × 0.6 = 32.4 m³ = 32,400 L.
  3. Subtract the volume taken up by the gasoline tank and tank footings below the wall height, roughly 3,000 L: about 29,400 L available.
  4. 29,400 L is above 27,500 L, so it passes, but with little margin for rainwater. Rain must be removed promptly.

Answer: It passes, with limited margin. Locked drain valve, prompt removal of inspected rainwater and a roof or more frequent checks are needed.

# Northwind dike check (metric, Canadian rule). Tank displacement is an estimate.
diesel, gasoline = 25000, 5000
required = max(1.10 * diesel, diesel + 0.10 * gasoline)
gross = 9 * 6 * 0.6 * 1000
displacement = 3000                     # gasoline tank and footings below wall height (estimate)
available = gross - displacement
print(f"Required {required:,.0f} L; available about {available:,.0f} L; margin {available - required:,.0f} L")
rain_mm = 50
print(f"A {rain_mm} mm storm adds {9*6*rain_mm:,} L of water, leaving a margin of {available - required - 9*6*rain_mm:,.0f} L")
Output
Required 27,500 L; available about 29,400 L; margin 1,900 L
A 50 mm storm adds 2,700 L of water, leaving a margin of -800 L

Step 3: equipment

Spill kits go where the risks are: a wheeled kit of at least 250 L capacity with drain covers at the fuel island; a 150 L kit in the shop; a kit on the drum pad; a kit at the wash bay; and small kits in every service truck. Because the yard drains to a trout stream, the plan adds a cache of oil-only booms and materials for an underflow dam at the rear ditch, near where the storm outfall enters it. Kits are inspected monthly with tamper seals and restocked after any use. Protective equipment in each kit matches the safety data sheets for fuels, oils and the shop chemicals.

Step 4: response levels and roles

The plan defines three levels. Level 1: small spills of known substances on pavement or the shop floor, with no pathway to drains or water, cleaned up by trained staff. Level 2: larger spills, any spill reaching a catch basin, the ditch or soil, or any uncertainty; the shift lead becomes spill coordinator, the site response team responds and regulatory reporting is assessed. Level 3: fire, strong vapour, injuries, a tank or dike failure, or oil reaching Cedar Creek; evacuate the area, call 911 and the spill contractor, and notify regulators. Each shift has a named spill coordinator and backup, a person to make calls and a person to meet responders at the gate.

Step 5: notification

The notification card at each kit lists: 911 for fire, injury or immediate danger; the shift spill coordinator; the operations manager; the Ontario Spills Action Centre at 1-800-268-6060 and the town for any spill reaching soil, a storm drain, the ditch or the creek, or any spill to the sanitary sewer; the spill contractor; and CANUTEC for advice on dangerous goods. Because the creek has fish, the coordinator also confirms that federal Fisheries Act reporting is covered. The neighbour with the well is on the list, to be contacted if a spill reaches soil near the fuel island, after discussion with the regulator.

Step 6: waste, training, drills and review

The plan names a licensed waste contractor, confirms that Northwind is registered as a hazardous waste generator for its used solvent and spill waste, and sets up a lined, covered storage area for spill waste with labels. All shop and yard staff receive training on the plan when hired and every year, with hands-on practice placing drain covers and booms. The coordinator team runs two drills a year, one tabletop and one functional, and the plan is reviewed after each drill, each level 2 or 3 spill, and at least yearly.

Testing the plan with a scenario

Worked problem

Scenario: a truck leaks fuel over a catch basin overnight

At 06:30, a technician finds diesel pooled around a catch basin under a parked truck. The truck's tank has a crack and is still dripping. A rainbow sheen is visible in the rear ditch. About 180 L is missing from the truck tank. Walk through the response.

Show solution
  1. Assess: diesel, no fire, no strong vapour in open air, no injuries. Remove ignition sources; do not start the truck.
  2. Stop the source: place a drain pan under the crack and transfer the remaining fuel, or plug the crack with leak-sealing putty.
  3. Contain: cover the catch basin, ring the pool with socks and soak up the pool with pillows.
  4. Downstream: the sheen means oil reached the ditch. Deploy booms and an underflow dam in the ditch before Cedar Creek.
  5. Notify: the coordinator calls the Spills Action Centre and the town, confirms Fisheries Act reporting, and calls the spill contractor to clean the storm line and ditch.
  6. Document: log times, take photos, estimate volume recovered, keep waste separate and labelled.
  7. Close out and investigate: why did the crack go unnoticed in the last service, and why was the truck parked over a drain?

Answer: A level 2 spill with reporting required because oil reached the ditch. Stop, contain at the drain and in the ditch, report, document, then fix the inspection and parking practices.

Summary of the Northwind spill plan.
Plan elementNorthwind decision
Priority risksFuel deliveries, truck leaks over drains, drum pad
Key preventionAlarms and attended deliveries, drip pans, drum pad roof and pallets, drain inserts
Containment checkDike passes with limited margin; manage rainwater
EquipmentKits at five locations and in trucks; booms and underflow dam materials at the ditch
LevelsThree levels, with a named coordinator and backup each shift
Notification911, Spills Action Centre, town, contractor, CANUTEC
WasteRegistered generator, licensed contractor, covered storage
Training and reviewYearly training, two drills a year, review after drills and spills

Common mistakes

  • MistakeWriting a generic plan that does not mention the creek or the well.

    InsteadBuild the plan around the site's actual pathways and receptors.

  • MistakeAssuming the dike is big enough without checking.

    InsteadCalculate capacity, allow for tank displacement and rain, and manage rainwater.

  • MistakePutting all spill kits in the shop.

    InsteadPlace kits at each risk point, plus booms where the yard drains to water.

  • MistakeListing only internal phone numbers.

    InsteadInclude emergency services, regulators, the sewer authority, contractors and affected neighbours.

  • MistakeFinishing the plan and never drilling it.

    InsteadDrill twice a year and review the plan after drills and spills.

Summary and key terms

  • Start with an inventory and a risk assessment based on sources, pathways and receptors.
  • Use the ranking to focus prevention on the highest risks.
  • Check containment capacity, including tank displacement and rainwater.
  • Place equipment at risk points, with extra capacity where the site drains to sensitive water.
  • Define response levels and name roles and backups for every shift.
  • Build a notification list that fits the jurisdiction and the site's receptors.
  • Plan waste handling, training, drills and review so the plan stays current and works.
Fleet maintenance yard
A site where vehicles are serviced and fuelled, with fuels, oils and chemicals on site.
Inventory (spill planning)
A list of every substance on site with quantities and locations.
Largest credible spill
The biggest release that could realistically happen from a source.
Tank displacement
The volume inside a dike taken up by tanks and footings, which reduces containment capacity.
Catch basin insert
A device fitted in a storm drain that can trap oil or be closed during a spill.
Drip pan
A tray placed under a leaking vehicle or machine to catch drips.
Notification card
A posted card listing the first calls to make after a spill.
Scenario test
Walking through a realistic spill to check that the plan works.
Plan review
A scheduled or triggered check that the plan still matches the site.
Close-out investigation
Finding and fixing the cause of a spill after the response.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. What were Northwind's three highest spill risks?

    Show answer

    Fuel delivery overfills, truck leaks over storm drains and drum punctures on the drum pad.

  2. Why is the sandy soil important?

    Show answer

    Spills can soak in fast and travel toward the neighbour's well.

  3. What volume must the shared dike hold under the common Canadian rule?

    Show answer

    27,500 L (110 % of the 25,000 L tank).

  4. Why must tank displacement be subtracted?

    Show answer

    Tanks and footings inside the dike take up space that cannot hold spilled liquid.

  5. Why does Northwind keep booms near the rear ditch?

    Show answer

    The yard drains to a trout stream, so oil must be intercepted before it reaches the creek.

  6. What makes a spill level 2 at Northwind?

    Show answer

    Larger spills, any spill reaching a catch basin, ditch or soil, or any uncertainty.

  7. Whom does the coordinator call when oil reaches the ditch?

    Show answer

    The Spills Action Centre and the town, plus confirming Fisheries Act reporting, and the spill contractor.

  8. What should be done first when the truck is found leaking?

    Show answer

    Assess safely, then stop the source by catching or transferring fuel or plugging the crack.

  9. How often should Northwind drill its plan?

    Show answer

    Twice a year: one tabletop and one functional drill.

  10. What two practices did the scenario investigation question?

    Show answer

    Why the crack was missed at the last service and why the truck was parked over a drain.