HSE-217 · Lesson 3 of 12 · 27 min

Buried facilities, one-call centres and locates

Almost every piece of ground in a town or city, and much of the ground in rural and industrial areas, carries buried facilities: natural gas mains and services, electrical cables, oil and gas pipelines, water mains, sanitary and storm sewers, telephone, cable and fibre optic lines, traffic signal cables, street lighting and district heating. Striking one can kill, as with a gas line that ignites or a high-voltage cable that arcs through an excavator bucket, or can cause enormous cost and disruption. This lesson covers how buried facilities are found and marked before digging. Lesson 4 covers how to dig safely once the marks are on the ground.

The one-call system

Every province has a one-call centre, a single point of contact that notifies the owners of buried facilities in the area of a planned excavation. The excavator submits one request, and the centre sends it to every member owner whose facilities may be affected. Each owner then either marks its facilities on the ground or issues a clearance saying it has nothing in the area. Examples include the Ontario Dig Authority (renamed from Ontario One Call in October 2026), BC 1 Call, Utility Safety Partners in Alberta, Sask 1st Call, ClickBeforeYouDig in Manitoba and Info-Excavation in Quebec. The national damage prevention standard, CSA Z247, sets out good practice for owners, locators and excavators across the country.

In Ontario, the Ontario Underground Infrastructure Notification System Act, 2012 makes membership in the one-call system mandatory for infrastructure owners and sets the rules for locate requests. Following amendments that took effect in 2024, excavators should request locates only when work is expected to start within 30 days. Members must complete a standard locate within 5 business days and a large or multi-property request within 10 business days, may not charge for the locate, and must provide locates valid for at least 60 days. Markings that can no longer be seen are treated as expired. The authority can impose administrative penalties for breaches.

A flow chart of the locate process: plan the work and mark the area in white, submit a request to the one-call centre, the centre notifies member owners, each owner marks or clears, the excavator checks every response and the marks on site, then digs carefully and keeps marks visible, renewing when needed.
The locate process from planning to digging. Digging may not start until every owner has responded and the marks are valid.

What a locate request needs

A good locate request is specific. The person requesting it should give:

  • The exact address or legal description, the nearest intersection and, for rural work, GPS coordinates or a land location.
  • A clear description of the work area: which side of the road, how far from the building, the length and width of the trench.
  • The type of work, such as a water service, fence posts, a sewer replacement or directional drilling.
  • The method of excavation, the expected depth and the start date.
  • Contact details for someone on site who can answer the locator's questions.

White lining, marking the proposed excavation area on the ground with white paint, flags or stakes, removes most of the guesswork. It tells the locator exactly where the digging will be, so the marks cover the right area and the locator does not waste time marking the whole property.

Worked problem

Planning around the locate timeline

A contractor in Ontario plans to dig a water service at a single address on Monday 16 November. Locates take up to 5 business days. What is the latest day the request should be submitted, and what is the earliest it should be submitted?

Show solution
  1. Counting back 5 business days from Monday 16 November: Friday 13, Thursday 12, Wednesday 11, Tuesday 10 and Monday 9 November.
  2. To allow the full 5 business days before digging on the 16th, the request should be submitted no later than Monday 9 November, and earlier is wiser in busy seasons.
  3. Requests should only be made when excavation is expected within 30 days, so the earliest sensible submission is around 17 October.
  4. Once received, the locates must be valid for at least 60 days, so the marks will cover the work if it proceeds on schedule.

Answer: Submit between about 17 October and 9 November; do not dig until every owner has responded.

How locators find buried facilities

A locator is a trained technician who works for the facility owner or a contract locating company. Locators combine records with detection equipment:

  • Records: maps and as-built drawings show where a facility was intended to be installed, but are often inaccurate by a metre or more, especially for older installations.
  • Electromagnetic locating: a transmitter puts a signal on a conductive line, either by direct connection or by induction, and a receiver traces the signal along the ground. It works well on metallic pipes and cables, and on plastic pipes only when a tracer wire was installed with them.
  • Passive locating: a receiver picks up signals already present on some lines, such as power cables carrying current.
  • Ground-penetrating radar: radar pulses reflect off buried objects. It can find non-metallic pipes but struggles in wet clay and gives results that require skilled interpretation.
  • Acoustic and other methods: used for specific problems such as plastic water mains.

No method is perfect. Signals can bleed onto adjacent lines, tracer wires break, records are wrong, and depth readings are estimates at best. That is why the marks show the approximate location of a facility and why lesson 4 insists on careful exposure within the tolerance zone.

The marking codes

Locators use a standard set of colours so that anyone on site can read the marks. Canada follows the codes in CSA Z247, which match the American Public Works Association codes used in the United States. The colour identifies the type of facility, and symbols or letters next to the marks can show the owner, the size, the number of ducts and the direction of the line.

Standard marking colours for buried facilities, as used in CSA Z247 and the APWA code.
ColourFacility type
RedElectric power lines, cables, conduit and lighting cables
YellowGas, oil, steam, petroleum or other gaseous or flammable material
OrangeCommunications, alarm or signal lines, cables or conduit, including fibre
BluePotable water
PurpleReclaimed water, irrigation and slurry lines
GreenSewers and drain lines
PinkTemporary survey markings
WhiteProposed excavation limits or route
Plan view of a residential lot with a proposed trench outlined by white dashes. A yellow line of paint marks and flags shows a gas service, an orange line shows a communications cable, a red line shows an electrical service and a blue line shows the water service, each labelled with a letter code.
Marks on the ground show the approximate horizontal location of each facility. They do not show depth, and they do not cover private lines.

Reading the locate package

The locate is not just paint on the ground. Each owner provides a locate sheet or electronic response describing what was marked, the area covered, any facilities that could not be marked and the expiry date. The excavator must collect a response from every owner on the notification list and check that:

  • The locate covers the whole work area, including spoil and equipment areas if those will be disturbed.
  • Every listed owner has marked or cleared. A missing response means the excavator cannot dig.
  • The marks on the ground match the sheets. If a sheet shows a gas service and there is no yellow paint, stop and call.
  • The locates are still valid and the marks still visible. Rain, traffic, snow clearing and earlier digging erase paint and flags.
  • Any notes, such as a requirement for the owner to be present when its line is exposed, are understood by the crew.

Private facilities

One-call members mark the facilities they own. They do not usually mark private facilities, which can include a homeowner's buried electrical cable to a garage, site lighting in a parking lot, irrigation lines, private water and sewer services, gas lines beyond the meter, and the extensive buried networks inside industrial plants, campuses, hospitals and airports. On many sites these private lines outnumber the public ones.

Private facilities must be located by a private locating company hired by the property owner or contractor, or by the facility owner's own records and staff. A one-call clearance that says no conflicts does not mean nothing is buried there. It means none of the member owners has anything there.

Worked problem

Checking a locate package before digging

A crew arrives to dig a 25 m trench for a new electrical service to a detached garage. The locate package includes gas (marked), the electricity distributor (marked to the meter), telephone (cleared) and cable (marked). The garage feed will run from the house panel. What is missing?

Show solution
  1. The public owners have all responded, so the one-call portion is complete.
  2. The existing private lines on the property, such as an old feed to the garage, a sprinkler system, a private gas line to a barbecue or a buried pool cable, are not covered.
  3. A private locate is needed for the route between the house and the garage.
  4. The crew should also confirm the marks are still visible and the locates have not expired.

Answer: A private locate. The one-call members only marked their own facilities up to the meter or property line.

Abandoned, unknown and unlocatable facilities

Old facilities that are no longer in service are often left in the ground. Some are truly dead; others are still live under a different owner, or have been reconnected. Unless the owner has confirmed in writing that a line is abandoned and safe, treat every uncovered pipe or cable as live. If an excavation uncovers a facility that was not marked, stop work near it, protect it, and contact the one-call centre and the likely owners before continuing.

Some facilities cannot be located by electronic means, such as plastic pipes without tracer wire. The owner may mark them from records with a note that the location is approximate, or may require that the excavator expose them by hand or vacuum excavation before mechanical digging. Treat these as higher risk.

Keeping marks alive on a long job

Locate marks are fragile. Paint fades under traffic and sun, flags are pulled up by curious passers-by and lawn mowers, and the excavation itself removes the ground the marks were painted on. On a job that lasts more than a few days, the crew should protect the marks from the start. Useful practices include offsetting marks, where stakes are set a measured distance to one side of each line so its position can be re-established after the original paint is dug away; photographing the marks with a tape measure in the frame before digging begins; recording the positions on the site drawing; and requesting a re-mark as soon as marks become unclear rather than relying on memory.

When the locates are close to expiry, or the work moves outside the area originally described, a new request is needed. In Ontario, markings that can no longer be seen are treated as expired, even if the 60-day validity period has not run out. A crew that keeps digging after the marks have vanished has, in effect, no locate at all.

Directional drilling and boring add a special challenge, because the drill head travels underground where nobody can see it cross other facilities. Every crossing along a bore path should be exposed by vacuum excavation so the crew can watch the drill head pass, and the bore path should be planned with clearances agreed with the facility owners.

Common mistakes

  • MistakeDigging as soon as the waiting period has passed, even though one owner has not responded.

    InsteadDo not dig until every listed owner has marked or cleared the area.

  • MistakeTreating a one-call clearance as proof that nothing is buried.

    InsteadPrivate facilities are not marked by one-call members; arrange a private locate.

  • MistakeUsing one locate for a different part of the site or a later job.

    InsteadA locate covers only the described area and remains valid only for the stated period.

  • MistakeAssuming the marks show depth.

    InsteadMarks show approximate horizontal location only; depth must be found by careful exposure.

  • MistakeContinuing to dig after marks have faded or been destroyed.

    InsteadRequest a re-mark or a new locate before digging further.

Summary and key terms

  • Every province has a one-call centre; Ontario's is now called the Ontario Dig Authority.
  • In Ontario, standard locates are due within 5 business days and are valid for at least 60 days.
  • Accurate requests and white lining help locators mark the right area.
  • Locators use records, electromagnetic tracing and radar, none of which is perfect.
  • Standard marking codes identify the type of facility.
  • Check every response and every mark before digging.
  • Private facilities need a private locate; unknown facilities must be treated as live.
One-call centre
The service that notifies all member facility owners of a planned excavation.
Locate
The marking of buried facilities on the ground, together with the owner's written response.
Clearance
A response from an owner saying it has no facilities in the requested area.
White lining
Marking the proposed excavation area in white so locators know where digging will occur.
Tracer wire
A conductive wire installed with a non-metallic pipe so it can be located electronically.
Ground-penetrating radar
A detection method using radar pulses to find buried objects.
Private facility
A buried line owned by the property owner or a non-member, not marked by the one-call system.
Locate validity
The period during which a locate may be relied upon before it must be renewed.
As-built drawing
A drawing showing where a facility was actually installed, which may still be inaccurate.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. What does a yellow mark indicate?

    Show answer

    Gas, oil, steam or other flammable products.

  2. What does an orange mark indicate?

    Show answer

    Communications lines, including fibre.

  3. What is white lining?

    Show answer

    Marking the proposed excavation area in white paint or flags.

  4. How long must Ontario locates be valid?

    Show answer

    At least 60 days.

  5. Why can a one-call clearance be misleading?

    Show answer

    It does not cover private facilities.

  6. Why is electromagnetic locating unreliable on some plastic pipes?

    Show answer

    Plastic does not carry a signal unless a tracer wire was installed and is intact.

  7. What should you do if an unmarked pipe is uncovered?

    Show answer

    Stop, protect it, treat it as live and contact the one-call centre and likely owners.

  8. Do locate marks show the depth of a facility?

    Show answer

    No; they show approximate horizontal location only.

  9. Name three pieces of information a locate request should include.

    Show answer

    Exact location, work description, method, depth, start date and site contact.

  10. What should happen if a locate sheet lists a facility that has no marks on the ground?

    Show answer

    Stop and contact the owner before digging.

Lesson quiz · 5 questions

Score 60% or more to complete this lesson.