CON-240 · Lesson 11 of 12 · 30 min

Temporary works II: bracing, cranes and construction loads

The previous lesson covered the temporary works that hold up concrete. This lesson covers the other loads and temporary structures that constructors put on and around a building while it is going up: temporary bracing and hoarding exposed to wind, excavation support, cranes and their foundations and outrigger pads, hoists and scaffolds tied to the structure, fall protection anchors, and the stockpiles and equipment placed on partly finished floors. These are often treated as routine site logistics, but each of them is a structural load or a structure in its own right, and each has caused serious failures when nobody checked it.

Construction loads are design loads too

A permanent building is designed for occupancy loads that are usually much smaller than the loads that occur during construction. An office floor is designed for a live load of about 2.4 kPa (50 psf), yet during construction it may carry pallets of drywall, rebar bundles, a scissor lift, a concrete buggy, or a mobile crane outrigger. Concentrated construction loads can be many times the design load over a small area, and they are often placed on young concrete, on steel deck that has not been filled, or on slabs that are still reshored.

Canadian practice relies on the engineer of record or a temporary works engineer to check construction loads, using CSA S269.1 for formwork and falsework and the general requirements of the National Building Code and provincial regulations, which require that no part of a structure be loaded beyond what it can safely support.

Common construction loads and controls.
Construction loadTypical issueControl
Material stockpiles (drywall, rebar, block)Concentrated loads far above floor design loadLoading plan with permitted zones near columns, engineer approval
Mobile elevating work platforms (MEWPs)Heavy wheel loads, especially on slabs and over openingsCheck wheel loads against slab capacity; avoid PT slabs without approval
Concrete buggies and pumpsImpact and concentrated loads on formwork and young slabsRunways and formwork designed for them
Mobile cranes on slabs or near wallsOutrigger loads of hundreds of kilonewtons (tens of kips)Engineered crane pad and slab check
Hoists and scaffold tiesLateral and vertical loads into the structureTie and support design checked by the engineer
Fall protection anchorsLarge impact loads in a fallAnchors rated or engineered for arrest forces

Worked problem

A boom lift on a suspended slab

A boom lift weighs 7,000 kg and occupies a footprint of 2.5 m × 7.0 m. What is its average pressure on an office slab designed for a 2.4 kPa live load? What else should be checked?

Show solution
  1. Weight = 7,000 × 9.81 ≈ 68.7 kN.
  2. Average pressure = 68.7 ÷ (2.5 × 7.0) ≈ 3.9 kPa, already above the 2.4 kPa design live load.
  3. Wheel loads are much more concentrated: one wheel may carry 40 per cent of the weight when the boom is extended, about 27 kN on a small contact patch, so punching and local bending must be checked.
  4. Get the manufacturer's maximum wheel loads and the engineer's approval before driving it on the slab.

Answer: About 3.9 kPa average, over the design live load, with much higher wheel loads: get approval.

Wind on temporary structures

Temporary structures catch wind just as permanent ones do, and often more, because they are light, tall, and covered with sheeting or panels. Hoarding, site fencing with privacy screens, scaffolds wrapped in debris netting or shrink-wrap, temporary walls, formwork panels, and stacked materials can all be blown over or lifted. The wind load is:

\[F = q\, C_f\, A\]

where q is the design wind pressure, Cf is a force or shape coefficient and A is the exposed area. Codes allow reduced design wind pressures for short construction periods, but only within limits, and the temporary works designer chooses the value.

In Canada, the NBC wind provisions and CSA S269.1 give the basis for temporary structure wind loads, and the scaffold standard CSA Z797 covers scaffold ties and access scaffolds.

Worked problem

Wind on site hoarding

A 2.4 m high solid plywood hoarding is exposed to a design wind pressure of 0.6 kPa with Cf = 1.3. What force acts on each metre of hoarding, and what overturning moment must the posts and footings resist?

Show solution
  1. Force = 0.6 × 1.3 × 2.4 ≈ 1.87 kN per metre.
  2. It acts at mid-height, 1.2 m, so overturning moment = 1.87 × 1.2 ≈ 2.2 kN·m per metre.
  3. With posts every 2.4 m, each post base must resist about 5.4 kN·m, which needs an engineered embedment, brace or ballast.

Answer: About 1.9 kN/m and 2.2 kN·m/m of overturning.

Adding wrap or netting to a scaffold greatly increases its wind load. A scaffold designed and tied for an open frame may need many more ties once it is sheeted. Any change in enclosure, such as winter hoarding, must go back to the scaffold designer.

Excavation support

CON-130 covered excavation and trench safety. From a structural point of view, excavation support systems such as soldier piles and lagging, sheet piles, secant or contiguous pile walls, and trench boxes are retaining structures that carry earth pressure, groundwater pressure and surcharges, the same loads described in Lesson 9. They are temporary works, usually designed by the contractor's engineer, and they often support neighbouring buildings, streets and utilities.

In Canada, provincial regulations govern excavations. Ontario's construction regulation, for example, requires support or sloping for most excavations deeper than 1.2 m and engineered support systems for deeper or special cases; other provinces have similar rules. Check the current regulation for your province.

Key structural controls include keeping surcharges such as spoil piles, equipment and cranes back from the edge or including them in the design, monitoring walls and neighbouring structures for movement, installing tiebacks or struts in the designed sequence without over-excavating, and managing groundwater.

Cranes and their foundations

Cranes are among the largest temporary loads on a site. Mobile cranes transfer their weight plus the load and its moment to the ground through outriggers or crawler tracks. Under the outrigger nearest the load, the reaction can approach the total weight of the crane and load combined. Tower cranes rest on engineered foundations, sit on the building structure, or climb within it, and impose large vertical, horizontal and overturning forces.

In Canada, crane operations are governed by provincial regulations and CSA Z150 (mobile cranes) and CSA Z248 (tower cranes), with tower crane foundations designed by a professional engineer.

Elevation of a mobile crane with an extended outrigger resting on a timber crane mat over soil, showing the outrigger load arrow, the mat spreading the load, and the resulting bearing pressure on the soil compared with the allowable value.
A crane mat spreads the outrigger load so that the bearing pressure stays within the ground's capacity.

Worked problem

Outrigger pad sizing

A mobile crane's maximum outrigger load for a planned lift is 300 kN. The ground has an allowable bearing pressure of 150 kPa. What mat area is needed, and is a 1.2 m × 1.2 m mat enough?

Show solution
  1. Required area = 300 ÷ 150 = 2.0 m².
  2. A 1.2 m × 1.2 m mat gives 1.44 m², so pressure = 300 ÷ 1.44 ≈ 208 kPa, which is too high.
  3. A 1.5 m × 1.5 m mat (2.25 m²) gives about 133 kPa, which is acceptable if the mat is stiff enough to spread the load evenly.
  4. Check for buried utilities, voids, recent backfill and excavations near the outriggers.

Answer: At least 2.0 m²; the 1.2 m mat is too small, a 1.5 m mat works.

Cranes on suspended slabs, podium decks or near basement walls need an engineer's check of the structure below, and often temporary shoring through several floors. Tower crane foundations are engineered for the specific crane, height and site; the foundation concrete must reach its specified strength before the crane is erected, and climbing cranes impose loads on the building that the engineer of record must accept.

Worked problem

Crane outrigger near a basement wall

A crane outrigger with a 300 kN load is planned 1.5 m behind a 3 m high basement wall that was designed for a 12 kPa surcharge. Spread over a 1.5 m × 1.5 m mat, what surface pressure does the outrigger apply, and what should happen?

Show solution
  1. Pressure under the mat = 300 ÷ 2.25 ≈ 133 kPa.
  2. That is about 11 times the 12 kPa surcharge the wall was designed for.
  3. Move the crane back, or have the engineer check the wall and design temporary bracing.

Answer: The outrigger load far exceeds the design surcharge; relocate or engineer a solution.

Hoists, scaffolds and anchors attached to the structure

Material and personnel hoists, mast climbing work platforms and tall scaffolds are tied to the building at intervals. The ties push and pull on the structure, often on slab edges or columns that were never designed for them. Tie locations and forces should be given by the hoist or scaffold designer and accepted by the engineer of record. Ties must not be removed by other trades, for example to install windows or cladding, without a planned replacement.

Fall protection anchors must withstand the forces generated in a fall, which are large: a person falling a short distance onto a lanyard can generate several kilonewtons even with an energy absorber.

In Canada, provincial regulations and CSA Z259.16 and Z259.15 set anchor requirements; many provinces require fall-arrest anchors to have a capacity of about 22 kN unless designed by an engineer for a lower value with a safety factor. Check the current provincial rule.

Typical problems include anchoring to guardrails, conduit, roof drains, ductwork or light framing; anchors drilled into young concrete; and post-installed anchors not installed to the manufacturer's instructions. Use engineered or rated anchors only.

Construction loading plans

A construction loading plan brings these issues together. For a building, it shows each floor's allowable construction loads by zone, where materials may be stored (usually near columns and beams, never at mid-span or over openings), where equipment may travel, crane and hoist locations, scaffold and hoist ties, and any temporary shoring needed under heavy loads. It is prepared by the contractor with the temporary works engineer and reviewed by the engineer of record, then posted and enforced on site.

Site supervisors make loading decisions every day, often under pressure from deliveries. A posted plan, signage on each floor and a simple rule, 'no stockpiles without approval', prevent most overloads.

Loading decisions also depend on timing. A slab that can carry a pallet of block at 28 days may not carry it at 7 days, and a slab still supported by reshores may already be carrying load from the floors above. When in doubt, the question to ask is not only how heavy the load is, but what the slab is already carrying and how strong it is today.

Common mistakes

  • MistakeLanding heavy material deliveries wherever the crane can reach.

    InsteadUse the loading plan's permitted zones near columns, and get approval for anything heavier.

  • MistakeAdding wrap or netting to scaffolds without a design check.

    InsteadEnclosing a scaffold multiplies its wind load; have the designer review ties and bracing.

  • MistakeSetting crane outriggers on unchecked ground or near excavations.

    InsteadCheck ground capacity, use engineered mats and keep back from excavations and walls.

  • MistakeAnchoring fall arrest to anything handy.

    InsteadUse rated or engineered anchors that meet the regulation.

  • MistakeRemoving scaffold or hoist ties to install cladding.

    InsteadPlan replacement ties first; never remove ties without approval.

Summary and key terms

  • Construction loads often exceed the floor design load and act on young or incomplete structures.
  • Wind load on temporary structures equals pressure times shape coefficient times area; enclosures add a lot.
  • Excavation support systems are temporary retaining structures that must be designed and monitored.
  • Crane outrigger loads are huge; mats spread them to keep bearing pressure within limits.
  • Hoist and scaffold ties and fall protection anchors load the structure and need design.
  • A construction loading plan defines where materials and equipment may go.
Construction load
A load from materials, workers or equipment during construction.
ASCE 37
A US standard for design loads on structures during construction.
Hoarding
A temporary solid fence or enclosure around a site.
Force coefficient (Cf)
A factor relating wind pressure to force on a shape.
Crane mat
A timber, steel or composite pad that spreads an outrigger load.
Outrigger
An extendable leg that stabilizes a mobile crane.
Scaffold tie
A connection that holds a scaffold to the structure.
Anchorage
A secure point of attachment for fall protection.
Loading plan
A plan showing allowable construction loads and storage zones.
Soldier pile and lagging
An excavation support system of vertical steel piles with horizontal lagging boards.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. A 400 kN outrigger load on 200 kPa ground needs what mat area?

    Show answer

    2.0 m².

  2. Wind of 0.5 kPa, Cf 1.2, on a 2 m high hoarding: force per metre?

    Show answer

    1.2 kN/m.

  3. Why does wrapping a scaffold matter structurally?

    Show answer

    It greatly increases wind load on the scaffold and its ties.

  4. Where should materials usually be stored on a slab?

    Show answer

    Near columns and beams, not at mid-span or near openings.

  5. What anchor capacity do many provinces require for fall arrest?

    Show answer

    About 22 kN unless engineered.

  6. Who is responsible for ground conditions under a crane?

    Show answer

    The constructor in control of the site, as set by provincial rules.

  7. Why must a crane near a basement wall be checked?

    Show answer

    Its outrigger load adds a large surcharge to the wall.

  8. What should happen before a boom lift drives onto a suspended slab?

    Show answer

    Check wheel loads against slab capacity and get the engineer's approval.

  9. At what depth does Ontario generally require support or sloping?

    Show answer

    Deeper than 1.2 m, with exceptions.

  10. Name three things a construction loading plan shows.

    Show answer

    Allowable loads by zone, storage areas, travel routes, crane and hoist locations, shoring.