RCDD-113 · Lesson 7 of 12 · 20 min

Primary and secondary protectors

▶ Video coming soon A video version of this lesson is on the way.

The service provider's engineer, a patient man named Gord Lindahl who had been installing building entrances for thirty years, met Daniel at the Harbourview site in October, when the foundations were in and the entrance conduits had been placed. Gord wanted to know where his protector would go. Daniel had a drawing ready: the protector field on the east wall of the entrance facility, 5 feet from where the entrance conduits came through the foundation wall, and 6 feet from the PBB. Gord looked at it, nodded and said, 'You'd be amazed how often I'm told to put it at the far end of the room because that's where the backboard is.'

This lesson covers the devices that stand between outside cables and the equipment inside: the primary protectors required at the building entrance for exposed metallic circuits, the secondary protectors that add protection closer to equipment, and the special cases of coaxial cables and fiber cables with metal in them.

What a primary protector does

A primary protector connects each conductor of an incoming metallic cable, such as each pair of a copper telephone cable, to the building's bonding network through a device that is normally an open circuit. When the voltage between a conductor and the bonding network rises above the device's breakdown level, the device conducts and diverts current from the conductor to the bonding network. The conductor is then clamped close to the local reference, so the equipment connected to it sees only a small difference.

The primary protector's job is to protect people and the building first, and equipment second. It deals with large energies from lightning and power faults on the outside plant and keeps them out of the building wiring. It is not designed to bring the voltage down to a level that sensitive electronics can survive; that is the job of secondary protection and of the protection built into equipment.

A schematic of one copper pair entering a building. Each conductor passes through a fuse link section in the outside cable, then to a primary protector unit with a gas tube from each conductor to a ground terminal. The ground terminal connects by a short straight conductor to the PBB. The pair continues to a secondary protector and then to equipment.
One pair through primary and secondary protection. The primary protector diverts to the PBB; the secondary protector limits what reaches the equipment.

Protector technologies

Three main technologies have been used in primary protectors. Carbon blocks, the oldest, use two carbon electrodes separated by a small air gap; when the voltage is high enough, the gap arcs over. They are cheap but wear with each operation and can become noisy or short permanently, and they are now largely replaced. Gas discharge tubes, the most common today, enclose electrodes in a sealed tube filled with an inert gas; they break down at a predictable voltage, can carry large surge currents and recover afterwards. Solid-state protectors use semiconductor devices, typically thyristor-based, that respond faster and clamp at lower, more precise voltages than gas tubes, at a higher cost and with lower current capacity for very large surges.

Many protector units combine technologies, for example a gas tube for large currents with a solid-state element for speed. Most also include a fail-safe mechanism: if a sustained power fault overheats the unit, a spring-loaded contact or a melting element shorts the conductors permanently to ground. This keeps a power fault from causing a fire inside the building at the cost of putting the line out of service until the unit is replaced, which is the right trade-off.

Primary protector technologies
TechnologyHow it worksStrengthsLimitations
Carbon blockAir gap between carbon electrodes arcs overLow costWears, can become noisy or permanently shorted; largely obsolete
Gas discharge tubeSealed gas breaks down and conductsLarge surge capacity, recovers after operationSlower response; breakdown voltage varies with rate of rise
Solid-state (thyristor)Semiconductor switches on at a set voltageFast, precise, low clamping voltageHigher cost; lower capacity for the largest surges
HybridGas tube with a solid-state elementCombines capacity and speedMore complex; cost

Where the primary protector goes

Codes require a listed or certified primary protector on each metallic communications circuit that is exposed, as lesson 6 defined. The protector is to be located as close as practical to the point where the cable enters the building, inside or outside, so that the length of unprotected conductor inside the building is as short as possible. Chapter 8 of the NEC, in the article on communications circuits, sets out the requirements, including the conditions under which a protector without fuses may be used and how the protector is to be bonded.

The protector's grounding terminal must be connected to the building's grounding system with a bonding conductor that is as short and straight as practical. The code sets a minimum conductor size, limits on its length in many cases, and a list of acceptable connection points in order of preference, starting with the building's intersystem bonding connection point at the service or the grounding electrode system. In a building with a telecommunications bonding network, the PBB placed close to the protector and to the service provides that point, provided it is bonded to the service as lesson 3 described and the AHJ accepts it.

Daniel had three goals in placing the protector field: a short run of unprotected cable from the conduit entry, a short straight bond to the PBB, and enough working space in front of the protector panel for the provider's technicians. Gord confirmed the protector would be a building entrance terminal with plug-in gas tube units, fused at the cable by fine-gauge sections in the outside plant, and that the provider's equipment would be bonded to the PBB with the conductor size the provider's standard required.

Under a power contact, a protector that conducts to ground can carry a large current for a long time. If nothing limits that current, the cable conductors between the outside plant and the protector can overheat. Two arrangements deal with this. A fused protector includes a fuse in each conductor ahead of the protective element. A fuseless protector relies on a fuse link in the outside cable: a short section of finer-gauge conductor, upstream of the building, that melts under sustained overcurrent and opens the circuit before the conductors inside the building can overheat. The code allows fuseless protectors only when the conditions it lists are met, which usually include the presence of such a fuse link or a cable that is otherwise protected.

The fuse link is normally part of the service provider's outside plant design, which is a good example of why coordination with the provider matters. Daniel asked Gord to confirm in writing that the incoming cable included fuse links appropriate for the fuseless protectors he planned to install, and noted the confirmation in the design records.

Secondary protection

A primary protector leaves a residual voltage on the line: the voltage at which it conducts plus the voltage along its bonding conductor. That residual can still be several hundred volts for a short time, more than many electronic ports can withstand. Secondary protectors, installed closer to the equipment, reduce it further. They typically use solid-state elements with a lower clamping voltage and include current-limiting elements, such as positive temperature coefficient resistors or small fuses, that protect against sneak currents: small sustained currents, below the level that would operate a primary protector, that can still overheat wiring or equipment over time.

Secondary protectors are not a substitute for primary protection. They are designed for the smaller energy left after the primary protector has acted, and they need to be coordinated with it. If a secondary protector clamps too hard and too early, it may try to carry energy that should have been diverted at the primary, and fail. Protector makers publish guidance for coordination, and listing standards for secondary protectors include tests for that purpose.

At Harbourview, the copper pairs from the provider's entrance terminal served the building's emergency elevator phones, fire alarm communicator lines and a small number of legacy analog lines for the clinic's fax machines and alarm panels. Daniel specified secondary protection at the point where those lines were cross-connected to the building cabling in the main equipment room, with protectors listed for the circuits they served, and bonded the secondary protector panel to the PBB.

A graph of voltage against time for a surge on a copper pair. The unprotected surge rises to several thousand volts. After the primary protector, a lower residual pulse remains. After the secondary protector, the residual is lower again and below the equipment withstand line.
Coordinated protection: the primary protector removes most of the energy, and the secondary protector brings the residual below what the equipment can withstand.

Coaxial cables and antennas

Coaxial cables from rooftop antennas and from cable television or broadband providers have a metallic shield that must be bonded where the cable enters the building. For antenna feeds, good practice is to bond the shield at the top of the mast near the antenna, at the bottom of the mast or where the cable leaves the mast, and at the building entry, using grounding kits made for the cable type. A coaxial surge protector at the entry, bonded to the nearest busbar, protects the center conductor.

At Harbourview, the cellular distributed antenna system donor antennas and the two-way radio antenna on the roof fed coaxial cables down the east shaft to the level 4 telecommunications room. Daniel bonded each cable shield at the mast, bonded the mast to the lightning protection system and roof steel, and placed a coaxial protector on each cable at the rooftop antenna enclosure, bonded to the rooftop SBB. The DAS and radio equipment makers' installation guides set the details, and the electrical engineer confirmed the mast bonding matched the lightning protection design.

Fiber cables with metallic members

Optical fibers do not conduct electricity, but many fiber cables contain metal: steel or aluminum armor for rodent and crush protection, metallic strength members, or copper pairs combined with fiber in hybrid cables. A conductive fiber cable entering a building can carry surge and fault current on its metallic members just as a copper cable can. Codes require those members to be bonded to the building's grounding system as close as practical to the point of entrance, or, in some cases, to be interrupted by an insulating joint near the entrance so that no metal path continues into the building.

The service provider's fiber entrance cable at Harbourview was armored. Gord's crew would bond the armor at the splice enclosure in the entrance facility with a kit made for the cable, using a conductor to the PBB. The campus link, by contrast, was specified as an all-dielectric cable with no metal at all, so it needed no bonding and no protection, which was one of the reasons Roz had pushed for it.

Protection and bonding for incoming cables at Harbourview
Incoming cableWhat needs bonding or protectionWhere
Copper service cableEach pair through a primary protector; cable shield bondedEntrance facility, close to entry, bonded to the PBB
Copper pairs to sensitive equipmentSecondary protection after the primaryAt the cross-connect or near equipment
Coaxial antenna feedShield bonded at the mast and at entry; coaxial protectorMast, rooftop enclosure, bonded to the nearest busbar
Armored or conductive fiber cableMetallic members bonded, or interrupted by an insulating jointAs close as practical to the entrance
All-dielectric fiber cableNothingNot applicable

Worked problem

Checking the protector bond

The provider proposes placing the protector panel on the west wall of the entrance facility, about 7 meters from the PBB, because that wall has more free space. The cable enters on the east wall. Explain what Daniel should say and propose an alternative.

Show solution
  1. A west-wall location puts about 7 meters of unprotected cable inside the building between the entry and the protector, which the code is trying to minimize.
  2. It also lengthens the bond from the protector to the PBB to roughly 7 meters plus routing, and the inductance of that bond would raise the residual voltage on every protected pair during a surge, as lesson 6 showed.
  3. The alternative is to keep the protector on the east wall near the conduit entry and to rearrange the backboard layout there, or to add a second PBB-bonded busbar extension near the protector field if the room layout truly requires it.
  4. Daniel should note the requirement in the specification and on the drawing so that the location is fixed before installation.

Answer: Keep the protector close to the cable entry and close to the PBB; rearrange the wall rather than lengthen the bond.

Common mistakes

  • MistakeMounting the protector wherever there is free backboard.

    InsteadPlace it as close as practical to the cable entry, with a short straight bond to the PBB.

  • MistakeRelying on secondary protectors alone.

    InsteadInstall listed primary protection on exposed circuits and coordinate secondary protection with it.

  • MistakeForgetting the armor on a fiber cable.

    InsteadBond the metallic members of conductive fiber cables near the entrance, or use all-dielectric cable.

  • MistakeBonding a coaxial shield only inside the building.

    InsteadBond antenna feed shields at the mast and at the building entry, and protect the center conductor.

Summary and key terms

  • A primary protector diverts surge and fault energy from incoming conductors to the bonding network, protecting people and the building first.
  • Gas tubes, solid-state and hybrid protectors have replaced carbon blocks; fail-safe features short the line under sustained faults.
  • Locate primary protectors as close as practical to the cable entry, with a short, straight bond to the PBB.
  • Fused protectors or fuse links in the outside plant prevent overheating under power contact.
  • Secondary protectors reduce the residual voltage and guard against sneak currents; they must be coordinated with the primary.
  • Bond coaxial shields at the mast and entry, and bond or interrupt metallic members of fiber cables at the entrance.
Primary protector
A device at the building entrance that diverts surge and fault energy on incoming conductors to ground.
Secondary protector
A device closer to equipment that limits residual voltage and sneak currents after primary protection.
Gas discharge tube
A sealed tube of inert gas that conducts when the voltage across it exceeds its breakdown level.
Fuse link
A short, finer-gauge section of outside plant cable that melts under sustained overcurrent.
Sneak current
A small sustained current, below primary protector operation, that can overheat wiring or equipment.
Conductive optical fiber cable
A fiber cable that contains metallic members such as armor or strength members.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. What is the main job of a primary protector?

    Show answer

    To divert surge and fault energy on incoming conductors to the bonding network, protecting people and the building first.

  2. Why must the protector be close to the cable entry?

    Show answer

    To minimize the length of unprotected conductor inside the building.

  3. What is a sneak current?

    Show answer

    A small sustained current below primary protector operation that can overheat wiring or equipment.

  4. What must be done with the armor of a fiber cable entering a building?

    Show answer

    Bond it as close as practical to the entrance, or interrupt it with an insulating joint where the code allows.

Lesson quiz · 5 questions

Score 60% or more to complete this lesson.

Take the quiz