IRW-230 · Lesson 1 of 12 · 24 min
Steel joists and joist girders
▶ Video coming soon A video version of this lesson is on the way.
On Tuesday evening, October 13, 2026, Ilona Benedek set up two sawhorses in the Crossbeam yard and laid a short length of steel joist across them. It was an offcut from the Airpark Building B warehouse roof that the deck crew had finished in August, about 8 ft of a joist's top and bottom chords with three web members still welded between them. Ilona had run Crossbeam's decking crew for sixteen years, and this was the first of five Tuesday-evening deck nights she had agreed to run for the apprentices before winter. Shay Donnelly, Jules Ostrowski and two other first- and second-year apprentices pulled up chairs. "Raising gangs set beams," Ilona said, "but a lot of what we cover in this trade is lighter steel: joists, joist girders and deck. It is light, it is fast, and it bites you if you forget how flimsy it is before it is braced."
This course covers the light framing and floor and roof systems that follow the main frame: open-web steel joists and joist girders, the bridging that holds them up, metal deck and how it is landed, spread and fastened, shear studs and composite floors, fall protection on deck, and precast concrete members and their connections. This first lesson explains what joists and joist girders are, how they are made and designated, how they bear and are attached, and the special rules for joists at columns.
What a steel joist is
An open-web steel joist is a light, shop-made truss used to support floors and roofs. It has a top chord and a bottom chord, usually made of a pair of angles back to back, joined by web members of round bar or angles welded between them in a zigzag pattern. At each end, the top chord extends into a bearing seat, a short pair of angles or a bent plate that sits on the supporting beam, joist girder or wall. Because so much of the joist is empty space, it is very light for its depth and span: a joist that spans a warehouse bay weighs a fraction of a rolled beam of the same capacity, and ducts and pipes can run through its open webs.
Joists are not designed by the building's structural engineer piece by piece. The engineer shows the joist spacing, depth and the loads each joist must carry on the drawings, and the joist manufacturer designs and builds each joist to suit. The manufacturer then issues joist erection drawings, which show every joist's mark, its location, the bridging rows and the attachment at each end. The erector works from those drawings, not from the structural plans alone.
How joists are designated
In the United States, joists are designed to the Steel Joist Institute's standard specification (SJI 100), which covers three series of standard joists, and to SJI's specification for joist girders. Each standard joist has a designation that tells its depth and series. A 24K8 is a K-series joist 24 in deep with a chord size of 8; a 32LH10 is a long-span joist 32 in deep; and DLH means deep long-span. K-series joists are the light, common joists used for spans up to about 60 ft; LH and DLH joists are used for longer spans and heavier loads. The structural drawings may give the designation directly, or give a depth and loads and leave the design to the manufacturer. The joist erection drawings then give each joist a mark and show its bridging and attachments.
| Series | Typical use | Seat depth (typical) |
|---|---|---|
| K-series | Roofs and floors of offices, schools and stores; depths 8–30 in; spans to about 60 ft | 2-1/2 in |
| LH and DLH series | Large roofs and floors, longer spans and heavier loads; depths to about 120 in | 5 in (DLH may be deeper) |
| Joist girders | Primary members carrying joists at panel points, spanning between columns | 7-1/2 in |
Joist girders
A joist girder is a heavier truss, built the same way as a joist, that replaces a beam as the primary member in a joist roof or floor. Joist girders span between columns and carry the joists at evenly spaced panel points along their top chord. Because the load comes in at the panel points, where the web members meet, the joist girder works as a true truss, and its design depends on the joists landing at those points and nowhere else.
Joist girders have their own designation. A 48G8N10K is a joist girder 48 in deep with 8 panels (N) and a load of 10 kips at each panel point (K). The joist manufacturer designs the girder to that designation, and the erection drawings show the panel points where the joists bear.
Worked problem
Joists and panel points on a girder
On the Airpark Building B roof, joist girders span 40 ft between columns and joists are spaced at 5 ft. Each joist spans 50 ft and has a reaction of 5 kips at each end under the design load. How many joists bear on the top chord of an interior girder between its columns, and what load does each panel point carry if joists bear from both sides?
Show solution
- Spaces along the girder = 40 ÷ 5 = 8.
- Interior panel points = 8 − 1 = 7; the joists at the ends of the girder land on the columns' joist lines, which the drawings detail separately.
- Load at a panel point = 5 kips from the joist on one side + 5 kips from the joist on the other = 10 kips.
- Total from joists on one girder = 7 × 10 = 70 kips.
Answer: Seven panel points at 10 kips each, which is what the 8N and 10K in a designation such as 40G8N10K describe: an 8-panel girder with 10 kips at each panel point. A joist landed between panel points would bend the top chord, so joists go only where the erection drawing shows them.
How light joists really are
Joist weights are small compared with beams, which is part of why they are dangerous before they are braced. A joist lifted by its ends sags and twists; an unbridged joist standing on its seats is like a tall, thin fence panel with nothing holding it upright. A worker who steps onto an unbridged joist can roll it off its seats.
Worked problem
The weight of one joist
An Airpark joist is 50 ft long, and the joist manufacturer's list gives a weight of about 9.5 lb/ft for that mark. What does it weigh, and how does that compare with the W12x26 beam B2-14 at Ashcroft?
Show solution
- Weight = 50 × 9.5 = 475 lb.
- Beam B2-14 = 30 ft × 26 lb/ft = 780 lb, for a span of only 30 ft.
Answer: About 475 lb for a 50 ft span. The joist is lighter than a beam little more than half as long, which is why joists are often lifted several at a time and why they must be stabilized quickly.
Bearing and attaching joists
Each joist seat must bear on its support by at least the length the joist manufacturer specifies, and it must be attached before the hoisting line is released. Short bearing is one of the most common joist problems: when a beam is out of position, or a wall ledger is low, a seat can end up with only a sliver of steel under it. The joist erection drawings give the minimum bearing, and any seat that does not meet it is reported before the joist is loaded.
OSHA 1926.757 sets the minimum attachment of joists while they are being erected. Each end of a K-series joist must be attached with at least two 1/8 in fillet welds 1 in long, two 1/2 in bolts, or the equivalent. Each end of an LH or DLH joist or joist girder must be attached with at least two 1/4 in fillet welds 2 in long, two 3/4 in bolts, or the equivalent. Except for panelized joists, at least one end on both sides of the seat must be attached immediately after the joist is placed and before more joists are set. The final attachment on the joist erection drawings may be larger, and welds are made by welders qualified to AWS D1.1 or the procedure the drawings call for.
Joist seats are never welded or bolted where they do not bear, and the chords are never cut, notched or burned to fit around a pipe or a duct. A joist is a truss, and a cut chord or web member can make it fail suddenly. If a joist does not fit, the foreperson stops and calls the joist manufacturer through the general contractor.
Joists at columns
A joist that lands at a column, on the column's own joist line, is a special case. Because the column is not yet framed in by beams in every direction, a joist there is the first member to tie the column back to the rest of the structure, and if it rolls or slides the column can lose its stability. These joists are therefore bolted at the column rather than welded, and their bottom chord is held by a stabilizer plate on the column.
OSHA 1926.757(a) has special rules for joists at or near columns. Where a column is not framed in at least two directions with solid web members, the joist at the column must be field-bolted to provide lateral stability during erection. The column must have a vertical stabilizer plate at least 6 in by 6 in, extending at least 3 in below the bottom chord, with a 13/16 in hole to tie off the bottom chord. The hoisting cables stay on until the seat at each end is field-bolted and the bottom chord is restrained by the stabilizer plate. In bays 40 ft or longer, joists must be fabricated for field-bolting and be field-bolted at first unless constructability prevents it. Joists also may not be used as an anchorage for fall arrest unless a qualified person approves it in writing.
Delivery, shakeout and storage
Joists arrive on flatbed trailers in bundles, with their marks painted or tagged on the ends. The shakeout crew checks the bundles against the shipping list and lays them out near where they will be lifted, on level dunnage, upright or flat as the manufacturer allows, and away from traffic. Joists are long and floppy, and lifting a bundle with a single choker in the middle can bend chords and break web welds. The manufacturer's handling instructions show where to lift, and bundles are usually lifted with a spreader or two chokers well apart.
- Check every joist for bent chords, cracked or broken web welds and damaged seats before it is lifted, and set aside any damaged joist for the manufacturer to assess.
- Keep the bridging, bolts and bridging clips with their bay, because they are needed the moment the joists are set.
- Store joists so that water drains off them and they are not standing in mud; rust and dirt on seats and chords interfere with welding.
On the Airpark roof, Ilona said, the joists for each bay came on the trailer in the order they would be set, which saved a day of sorting in the yard. Not every job is so lucky, and a good shakeout is the difference between a gang that sets steel and a gang that hunts for it.
Setting joists
Joists are usually lifted from the ground or the trailer by the crane, either one at a time with a spreader or several at a time in a bundle landed on the girders or beams and then spread by hand. A joist set by the crane is guided by tag lines from the ground, landed on its seats, and held by the crane while the connectors attach at least one end, both sides of the seat. Joists at columns are bolted before the line comes off. As soon as a joist is attached, the next one is set beside it, and the bridging is installed as the joists go in, as lesson 2 describes.
Ilona finished the first night by passing round the Airpark joist erection drawing. Every joist had a mark, an end, a seat detail and a row of small symbols for the bridging. "Read the bridging before you read anything else," she said. "It tells you when it is safe to step on the steel."
Joists in floors and roofs
Joists are used for both roofs and floors, but they behave differently in each. Roof joists carry the deck, insulation, roofing and snow, and their design load is often governed by snow drift against parapets and higher roofs. Floor joists carry a concrete slab on form deck and the floor's live load, and they are usually deeper and closer together. Floor joists are often designed for vibration as well as strength, so that the floor does not feel lively when people walk on it. In both cases, the joist manufacturer's design assumes the bridging, the deck and the attachments are installed as shown; until they are, the joist has only a fraction of its design strength sideways.
Joists also carry things the drawings may not show in detail: rooftop units on frames, hung mechanical equipment, sprinkler mains and ceiling grids. Concentrated loads like these must be placed only where the joist manufacturer has designed for them, usually at panel points or on extra members called load-bearing web reinforcement. An erector who is asked to hang a load from a joist chord between panel points sends the question to the general contractor and the joist manufacturer before anything is welded on.
Common mistakes
MistakeTreating the structural plans as enough to set joists.
InsteadWork from the joist manufacturer's erection drawings, which show marks, bridging and attachments.
MistakeLanding a joist on a joist girder between panel points.
InsteadLand joists only at the panel points shown.
MistakeReleasing the hoisting line before both sides of one seat are attached.
InsteadAttach at least one end on both sides of the seat before the line comes off.
MistakeCutting a chord or web to clear a pipe.
InsteadNever cut a joist; stop and refer the conflict to the manufacturer.
MistakeWelding a joist at a column instead of bolting it.
InsteadField-bolt joists at columns and restrain the bottom chord at the stabilizer plate.
Summary and key terms
- Open-web steel joists are light shop-made trusses with top and bottom chords, web members and bearing seats.
- In the US, joists are designed to SJI 100; designations such as 24K8, 32LH10 and DLH give depth and series.
- Joist girders carry joists at panel points and span between columns.
- Joists bear by at least the manufacturer's minimum and are attached as shown before the line is released.
- OSHA 1926.757 sets minimum erection attachments and special rules for joists at columns, including the 6 in by 6 in stabilizer plate.
- Joists are never cut or notched, and damaged joists are set aside for the manufacturer.
- Open-web steel joist
- A light shop-made truss used to support floors and roofs.
- Chord
- The top or bottom longitudinal member of a joist or truss.
- Web member
- A diagonal or vertical member joining a truss's chords.
- Bearing seat
- The end of a joist that sits on its support.
- Joist girder
- A primary truss that carries joists at its panel points.
- Panel point
- A point on a truss chord where web members meet and loads are applied.
- Stabilizer plate
- A plate on a column that restrains the bottom chord of a joist or joist girder.
- Joist erection drawing
- The manufacturer's drawing showing joist marks, bridging and attachments.
Practice problems
Work each problem on paper first, then reveal the answer to check.
A joist girder spans 30 ft with joists at 5 ft. How many interior panel points carry joists?
Show answer
30 ÷ 5 = 6 spaces, so 5 interior panel points.
A 40 ft joist weighs about 7.5 lb/ft. What does it weigh?
Show answer
40 × 7.5 = 300 lb.
What does the designation 28LH09 mean?
Show answer
A long-span joist 28 in deep with a chord size of 9.
What is the minimum erection attachment at each end of a K-series joist under OSHA 1926.757?
Show answer
Two 1/8 in fillet welds 1 in long, two 1/2 in bolts, or the equivalent.
How big must a column stabilizer plate be under OSHA?
Show answer
At least 6 in by 6 in, extending at least 3 in below the bottom chord, with a 13/16 in hole.