On the Thursday after Devon's stop at Kellerton, the abatement contractor's crew arrived at 7:00 to remove the tee cover. Devon was working in the engine room, but at lunch he walked past the roped-off area and saw what he had only heard about: a plastic glove bag sealed around the tee, a worker in disposable coveralls and a full-face respirator working through the bag's built-in gloves, another keeping the material wet, a HEPA vacuum and a pile of labeled waste bags. "They made it look easy," he told Mei later. "Like it was routine." "It is routine," she said, "for them. That's the point. It's their trade, not yours."
This lesson explains how OSHA's rules classify asbestos work, who is allowed to do each class, what training and licensing are required in Ohio, and how to recognize an abatement work area when you see one. It is not a course in doing that work. The goal is that you know what is going on around you, what you may and may not do, and why Coldstream's crews leave all asbestos removal to the specialists.
Classes of asbestos work under OSHA
OSHA's construction standard divides asbestos work into four classes. The class depends on the kind of material and what is being done to it, because those decide how many fibers the work is likely to release. In general terms:
- Class I is the most hazardous: removal of thermal system insulation and surfacing ACM or PACM. Thermal system insulation means asbestos on pipes, fittings, boilers, breeching, tanks, ducts and other parts of mechanical systems, which is exactly the material insulators meet.
- Class II is the removal of ACM that is not thermal system insulation or surfacing material, such as floor tile, roofing, siding, mastics and many gaskets.
- Class III is repair and maintenance work in which ACM, including thermal system insulation or surfacing material, is likely to be disturbed, limited to small amounts, such as the material that fits in a single glove bag or waste bag.
- Class IV is maintenance and custodial work in which workers contact but do not disturb ACM or PACM, and cleanup of waste and debris from Class I, II and III work.
The higher the class, the more extensive the requirements: from basic awareness and care for Class IV, to small-scale controls such as glove bags and HEPA vacuums for Class III, to regulated areas, critical barriers, negative pressure enclosures, decontamination units, competent supervisors and accredited workers for Class I. A competent person must supervise every class of work.
Who may do the work
Training under OSHA is tied to the class of work. Class I work requires training equivalent to EPA's Model Accreditation Plan course for abatement workers, normally a four-day course with hands-on practice, and supervisors need the longer supervisor course. Class II work requires training specific to the material and method, or the full course. Class III work requires training equivalent to EPA's 16-hour operations and maintenance course. Class IV work requires awareness training of at least two hours. Training must be repeated each year with refresher courses.
In Ohio, abatement of more than 50 linear feet or 50 square feet of friable ACM must be done by a contractor licensed by Ohio EPA, with certified abatement workers and an on-site certified abatement specialist supervising. Ohio EPA also certifies the specialists who inspect buildings and design projects, and the people who monitor the air. EPA's NESHAP rules require a trained supervisor on site for regulated removal.
Coldstream's policy is stricter than the law requires: its crews do not do Class I, II or III work on any material known or suspected to contain asbestos. All Coldstream field workers receive at least Class IV awareness training, so that they can recognize suspect material, stop, and work safely near regulated areas, but removal is always left to the owner's licensed abatement contractor. "We insulate," Walt Lowery says. "We don't abate. If somebody wants to hire us to abate, they've got the wrong company."
Other insulation contractors make different choices. Some have trained crews that do limited asbestos work within the rules, especially on plant maintenance. If you work for such a company in the future, you will receive the training and certification the work requires before you do it. Until you have that training, the rule is simple: you do not disturb asbestos-containing material.
Recognizing an abatement work area
You will often work near abatement, because insulation work usually follows it. Knowing what you are looking at helps you stay out of the way and notice when something is wrong.
- Signs and barriers. Every entrance has warning signs, caution tape or rigid barriers, and often a sign-in log. Do not enter unless you are part of the work.
- Polyethylene sheeting. Walls, floors and openings covered and sealed with heavy plastic sheeting, often in two layers, to make an enclosure and to seal off vents and doorways.
- Negative air units. Boxy fan units with large filters, exhausting air from the enclosure through high-efficiency filters, so that air leaks into the work area rather than out of it. The plastic walls often bow slightly inward.
- Decontamination facility. A series of small rooms at the entrance to a large enclosure, where workers change, shower and leave contaminated clothing behind.
- Glove bags. For small removals from pipe, clear bags sealed around the pipe with built-in gloves, used without a full enclosure.
- Wet methods and HEPA vacuums. Sprayers keeping the material wet, and vacuums with high-efficiency filters, never brooms or compressed air.
- Air sampling pumps. Small pumps with filter cassettes, on stands around the area or clipped to workers' collars, collecting air samples for analysis.
- Labeled waste. Sealed, labeled bags or containers moved out through a waste route, never thrown down chutes or into ordinary bins.
If you notice a problem at an abatement area near your work, such as torn plastic, a negative air unit that has stopped, dust outside the barrier, a door left open or workers leaving in contaminated clothing, tell your supervisor at once. Your supervisor will tell the abatement contractor's supervisor and the owner's consultant.
After abatement: clearance
Before an abatement area is released, it is cleaned and inspected, and air samples are taken. OSHA's standard does not set a single clearance number, but most specifications and Ohio practice use a clearance level of 0.01 fibers per cubic centimeter by phase contrast microscopy for typical projects, and AHERA requires transmission electron microscopy clearance for larger school projects. As an insulator, ask to see the clearance before you start work in a former abatement area.
Clearance applies to the area that was abated, not to the whole building. If your work will extend beyond that area, the survey and the rules still apply there.
Worked problem
Checking classes and licensing
The Mountview abandoned line (lesson 12) had about 59 ft of aircell-covered pipe with an outside diameter of about 5.5 in. (a) What is the surface area of aircell on the whole line? (b) Which OSHA class is its removal? (c) Does Ohio require a licensed contractor? (d) Does the NESHAP renovation notification threshold apply?
Show solution
- Surface area = π × D × L = π × (5.5 ÷ 12) × 59 = 85 sq ft.
- (b) Aircell on pipe is thermal system insulation, so removing it is Class I work.
- (c) Ohio requires a licensed contractor above 50 linear feet or 50 square feet of friable ACM; 59 linear feet and 85 square feet both exceed that.
- (d) The NESHAP renovation threshold for pipe is 260 linear feet; 59 ft is below it, so EPA notification is not triggered by this pipe alone, although the state and the hospital's own procedures still apply.
- Debris on the ceiling tiles also had to be cleaned up; that cleanup is part of the Class I project.
Answer: About 85 sq ft; Class I; yes, a licensed Ohio contractor is required; the NESHAP pipe notification threshold is not reached by 59 ft.
Removal is not the only option
Owners do not always remove asbestos-containing material. Depending on its condition and on the work planned, an owner may choose to:
- Leave it in place and manage it, if it is in good condition and will not be disturbed.
- Repair it, by patching small areas of damage with suitable materials.
- Encapsulate it, by coating it with a sealant that binds the surface and the fibers.
- Enclose it, by building an airtight barrier or a new jacket around it so that it cannot be disturbed or release fibers.
- Remove it, when it is badly damaged or in the way of work.
Repair, encapsulation and enclosure are themselves regulated asbestos work, because they can disturb the material; repair and maintenance that disturbs thermal system insulation is at least Class III work, and larger jobs are Class I. An insulator might be asked to put a new metal jacket over old asbestos pipe covering as a way of enclosing it. That is asbestos work, not ordinary jacketing, and Coldstream does not do it. If you are ever asked to jacket over old insulation of unknown content, stop and ask for the survey and the owner's abatement plan.
Working alongside an abatement contractor
On renovation and plant shutdown work, insulators often follow an abatement contractor area by area: the abatement crew removes the old insulation from one section, the area is cleared, and the insulators reinsulate it while the abatement crew moves to the next section. That sequence works well when the trades coordinate closely.
- Know the abatement schedule and which areas are active, cleared or not yet started.
- Respect the abatement contractor's barriers, decontamination units and waste routes; do not use them as shortcuts or storage areas.
- Ask to see the clearance for each area before you enter it, and check that it covers the whole of your work area.
- Keep your materials and tools out of active abatement areas, so they do not become contaminated waste.
- Report anything you find in a cleared area that looks like missed material or debris; abatement crews can miss pieces behind supports or inside chases, just as earlier insulators did.
At Kellerton, the abatement contractor removed the asbestos from two valves and a flange pair the Friday before the November outage, and the clearance report was in Mei's file before the Coldstream crew started work on Monday. When Devon found the unlisted tee, the same contractor came back the next day. That kind of working relationship, built over years, makes stops quick and painless.
Asbestos work and the insulator's trade
Some insulators move into abatement work during their careers, because the skills of working on pipe and equipment carry over and because abatement contractors value people who understand insulation systems. Doing so means taking the full training and certification for that work, and accepting the discipline of enclosures, decontamination and air monitoring. It is a legitimate and important trade in its own right. It is simply not part of an insulator's job without that training.
In Ohio, abatement workers and specialists must carry their Ohio EPA certification cards on the job, and inspectors can check them. Accredited training under EPA's Model Accreditation Plan must be renewed by annual refresher courses, and a worker whose accreditation has lapsed cannot do the work until it is renewed. Some building owners and specifications also require additional site-specific training, for example for work in hospitals or in plants with special hazards. If you are ever asked to help an abatement crew, even by carrying materials into the regulated area, the answer is no: entry is for trained, protected workers only.
Common mistakes
MistakeThinking a small amount of asbestos is fine for anyone to remove.
InsteadEven Class III and IV work requires training, and Coldstream does no Class I to III work.
MistakeEntering an abatement area to check measurements or fetch a tool.
InsteadNever enter a signed abatement area unless you are part of that work.
MistakeAssuming a glove bag is something you can pick up and use.
InsteadGlove bag removal is asbestos work that requires training and authorization.
MistakeStarting work in a former abatement area without seeing the clearance.
InsteadAsk for the clearance result first, and check that it covers your area.
MistakeIgnoring torn plastic or a stopped negative air unit next door.
InsteadReport it at once; the barrier protects you too.
Summary and key terms
- OSHA classifies asbestos construction work as Class I to IV; removing thermal system insulation is Class I.
- Training rises with the class, from two-hour awareness for Class IV to accredited courses for Class I; Ohio EPA licenses abatement contractors above 50 linear or square feet.
- A competent person must supervise every class of asbestos work.
- Coldstream crews do no asbestos removal; all removal is left to the owner's abatement contractor.
- Abatement areas have signs, plastic sheeting, negative air units, decontamination facilities, glove bags, wet methods, HEPA vacuums, air sampling and labeled waste.
- Ask for the clearance result before starting work in a former abatement area, and report problems at abatement areas near your work.
- Class I asbestos work
- Removal of thermal system insulation and surfacing ACM or PACM.
- Class IV asbestos work
- Maintenance and custodial work that contacts but does not disturb ACM, and cleanup of asbestos waste.
- Competent person
- A person able to identify asbestos hazards and with the authority to correct them, required for all asbestos work.
- Glove bag
- A sealed plastic bag with built-in gloves used to remove asbestos insulation from pipe.
- Enclosure
- A sealed work area of plastic sheeting under negative pressure, used for high-risk removal.
- Negative air unit
- A fan unit with high-efficiency filters that exhausts air from an enclosure so air leaks inward.
- Decontamination facility
- The rooms at an enclosure entrance where workers change, shower and leave contaminated clothing.
Practice problems
Work each problem on paper first, then reveal the answer to check.
Which OSHA class is removal of asbestos pipe insulation?
Show answer
Class I.
What training does Class IV work require?
Show answer
Awareness training of at least two hours.
Above what amount of friable ACM does Ohio require a licensed abatement contractor?
Show answer
More than 50 linear feet or 50 square feet.
Aircell with a 4.3 in outside diameter covers 13 ft of pipe. What is its surface area?
Show answer
π × (4.3 ÷ 12) × 13 = 14.6 sq ft.
What should you do if you see torn plastic at an abatement enclosure next to your work?
Show answer
Tell your supervisor at once so the abatement supervisor and consultant can deal with it.
Lesson quiz · 5 questions
Score 60% or more to complete this lesson.
Create a free account to save your progress, take quizzes and earn a certificate.