DCE-320 · Lesson 11 of 12 · 34 min

Outside plant, diverse routes and carrier entrances

A data center is only as reliable as its connections to the outside world. The fibers that join it to carriers, internet exchanges, other data centers on the campus and the operator's other regions run through the outside plant (OSP): duct banks, maintenance holes, poles, bridges and road crossings that the operator often does not own and cannot fully see. Most serious connectivity outages are caused not by equipment but by cable cuts, typically by excavation, and the defense against them is physical diversity: more than one route, entering the building at more than one point, with nothing shared between them.

This lesson covers OSP construction, high-count fiber cables and splicing, long-link loss budgets, how to design and verify diverse routes, building entrance facilities and the code rules that apply to them, and the commercial arrangements for carrier connectivity.

Outside plant construction

Fiber between buildings and to carriers is placed in one of three ways:

  • Underground in duct banks: groups of conduits, typically 100 mm (4 in) in diameter, laid in a trench and often encased in concrete, with maintenance holes (manholes) or handholes at intervals for pulling, splicing and storing slack. This is the standard for campuses and for the routes immediately around a data center.
  • Directly buried: armored cable placed in a trench or plowed in without conduit. Cheaper, but the cable cannot be replaced or added to without digging again.
  • Aerial: cable lashed to a steel strand on utility poles. Quick and cheap where poles exist, but exposed to storms, vehicle strikes, ice and fire.

Inside each conduit, innerduct (smaller plastic ducts, often three per 100 mm conduit) or fabric innerduct (flexible textile sleeves that pack more cables into a conduit) subdivides the space, so that each new cable can be pulled without disturbing the others. Microduct bundles allow fiber cables to be blown in with compressed air, a method called air-blown fiber or jetting, which places cable over long distances with little pulling tension and allows capacity to be added later.

Trenchless methods avoid open excavation where it is impractical. Horizontal directional drilling (HDD) bores under roads, railways and rivers by steering a drill head along a planned path and pulling conduit back through the hole. Micro-trenching cuts a narrow slot in the road surface for microduct, which is fast but shallow and therefore easier to damage later.

Cross-section of an underground duct bank in a trench. Six 100 millimeter conduits in two rows of three are encased in concrete. One conduit is shown with three innerducts, another with a fabric innerduct holding several cables. A warning tape lies in the backfill above the concrete, and the depth to the top of the concrete is marked below the finished grade.
A concrete-encased duct bank with innerduct. Warning tape above the bank alerts excavators before they reach it.

Maintenance holes are placed at changes of direction, at splice points and at intervals set by the cable's allowable pulling tension and by the number of bends; for fiber pulled in conduit, spacing is commonly a few hundred meters, and longer where cable is blown in. At each maintenance hole, a slack loop (commonly 15 to 30 m) is stored on racks so that the cable can be pulled out for splicing or repairs without adding a new splice.

OSP depth and routing are set by the owner's standards and by the authority granting the right of way. Telecommunications ducts are commonly buried with about 30 to 42 in of cover. Before any excavation, the contractor must call or submit a request to 811, the national call-before-you-dig number, which routes it to the state one-call center so that owners of buried facilities can mark them.

High fiber-count cables and splicing

Campus and inter-building cables have grown enormously with AI clusters and multi-building campuses. Cables of 864, 1728 and 3456 fibers are common, and 6912-fiber cables are used between large buildings. These cables use ribbon fiber: 12 fibers bonded side by side, so that a whole ribbon can be spliced in one operation with a mass fusion splicer. Rollable ribbon, in which the fibers are joined only at intermittent points, can be rolled into a compact bundle, putting many more fibers into a given duct than flat ribbons.

Worked problem

Splicing time for a high-count cable

A 3456-fiber cable must be spliced to two 1728-fiber cables at a maintenance hole. Mass fusion splicing takes about 3 minutes per 12-fiber ribbon including preparation and protection, and single-fiber splicing about 2 minutes per fiber. Compare the splicing time.

Show solution
  1. Ribbons: \(3456 / 12 = 288\). Mass fusion time: \(288 \times 3 = 864\) min = 14.4 h.
  2. Single fiber: \(3456 \times 2 = 6912\) min = 115 h.

Answer: About 14 hours with mass fusion splicing against about 115 hours one fiber at a time. Ribbon cable is what makes very high fiber counts practical to install and repair, which matters greatly when a cut cable must be restored.

Splices are housed in sealed splice closures in maintenance holes or vaults, organized in trays with each fiber identified by its color code. Standard fiber colors repeat in a 12-color sequence: blue, orange, green, brown, slate, white, red, black, yellow, violet, rose and aqua, with tubes or ribbons identified by the same sequence.

Loss budgets for OSP links follow the same method as in Lesson 6, but the fiber attenuation and splices become significant, and an allowance is added for future repairs: each time a cable is cut and repaired, at least one or two splices are added.

Worked problem

Campus link between buildings

Two buildings on a campus are 6.5 km apart along the duct route. A 100GBASE-LR4 link (6.3 dB channel budget, 1310 nm) will use the OSP cable. The cable is installed in three reel lengths, so there are two OSP splices, plus a splice at each building entrance between the OSP cable and indoor pigtails. There are four mated LC pairs at 0.5 dB. Use 0.4 dB/km and 0.1 dB per splice.

Show solution
  1. Fiber: \(0.4 \times 6.5 = 2.60\) dB.
  2. Splices: 4 × 0.1 = 0.40 dB.
  3. Connectors: 4 × 0.5 = 2.00 dB.
  4. Total: 5.00 dB. Margin: 6.3 − 5.0 = 1.3 dB.

Answer: The link fits with 1.3 dB of margin, enough for a few repair splices (0.1 to 0.2 dB each) but not for another cross-connect. If the campus will grow beyond about 8 km of route, or the design adds patching points, a longer-reach optic would be needed.

Worked problem

Metro link to a carrier hotel

A 40 km route at 1550 nm uses fiber at 0.25 dB/km, has splices every 4 km (including both ends, 11 splices) at 0.1 dB, four connector pairs at 0.5 dB, and a 3 dB allowance for repairs and aging. Will an optic with an 18 dB loss budget work?

Show solution
  1. Fiber: \(0.25 \times 40 = 10.0\) dB.
  2. Splices: \(11 \times 0.1 = 1.1\) dB. Connectors: \(4 \times 0.5 = 2.0\) dB.
  3. Calculated loss: 13.1 dB. With the repair allowance: 16.1 dB.

Answer: Yes, with 1.9 dB to spare after the allowance. Over these distances fiber attenuation dominates. Longer data center interconnect links, beyond about 80 km, use coherent optics and optical amplifiers, which are planned with optical signal-to-noise ratio as well as loss (DCE-210).

Waterfall chart of the 40 km link budget. Starting from 18 decibels of available budget, bars step down by 10.0 dB for fiber, 1.1 dB for splices, 2.0 dB for connectors and 3.0 dB for the repair allowance, leaving 1.9 dB of remaining margin.
The 40 km link budget as a waterfall: fiber attenuation uses most of the budget.

Route diversity

Two routes are diverse only if no single event can cut both. Shared risks are often hidden:

  • Two carriers may lease fiber in the same duct bank, or in the same conduit of a third party, for part of their routes.
  • Different routes often converge at bridges, railway and highway corridors, river crossings and the last few hundred meters before a building.
  • Two "diverse" entrances may join inside the building in the same entrance room or the same tray.
  • Two carriers may both rely on the same upstream exchange, central office or power supply.

Network engineers call each such shared element a shared risk link group (SRLG). The designer verifies diversity by obtaining route maps (usually as geographic files) from each carrier, overlaying them, and identifying every point where the routes come within a set distance of each other, often a few tens of meters. The contracts should then commit the carriers to maintaining the separation and to notifying the operator before any re-route. Diversity is not permanent: carriers re-route fiber during road works and network changes, so it must be re-checked periodically.

TIA-942 calls for diverse entrance pathways for higher rating levels, with maintenance holes on separate sides of the building and recommends that they be separated by at least 20 m. Within the building, each entrance should lead to its own entrance room or to a separate area, and backbone cabling from each to the MDAs should follow separate pathways.

Map-style diagram of a data center with two entrance points on opposite sides, each with a maintenance hole. Route A, in blue, leaves the north side and runs to carrier point of presence 1. Route B, in orange, leaves the south side and runs to point of presence 2. Both routes cross a river on the same bridge, which is circled in red and labeled shared risk. A third route, in green, crosses the river by directional drilling at a separate point.
Two routes that appear diverse can share a bridge or corridor. A third crossing removes the shared risk.

Worked problem

Availability of diverse routes

Records show that a metro fiber route of this length suffers about 2 cuts per year, each taking 8 hours to repair. Estimate the annual hours of outage with one route and with two fully diverse routes. Then estimate it if the two routes share a bridge section that is cut 0.1 times per year with a 12 hour repair.

Show solution
  1. One route: \(2 \times 8 = 16\) h per year. Unavailability \(U = 16/8760 = 0.00183\).
  2. Two fully independent routes: both are down only if they fail at the same time. \(U^2 = 0.00183^2 = 3.3 \times 10^{-6}\), or about 0.03 h (2 minutes) per year.
  3. Shared bridge: adds \(0.1 \times 12 = 1.2\) h per year in which both routes are down together.
  4. Total with the shared section: about 1.2 h per year.

Answer: Diversity reduces expected outage from 16 hours a year to about 2 minutes, but a single shared section rare enough to be overlooked raises it to about 1.2 hours, 40 times worse. Removing shared risks matters more than adding more routes.

Building entrance facilities

Where the OSP cables enter the building, the design must keep out water and gas, protect the cables and the people working on them, and meet code rules for outside plant cable inside a building:

  • Entrance conduits slope down away from the building so water drains outward, and every conduit, including spares, is sealed with duct plugs or an expanding sealant.
  • OSP cables are designed for water resistance and strength, not for fire performance, and are usually not listed for indoor use. They are therefore spliced to listed indoor cable, or enclosed in a suitable raceway, close to the entrance point.
  • Metallic members in OSP cables (armor, strength members) must be bonded to the building's telecommunications bonding system at the entrance, and copper circuits from outside need primary protectors that limit lightning and power-cross voltages.

In the US, the NEC covers these entrance requirements: unlisted outside plant optical fiber cable may extend into the building no more than 15 m (50 ft) from the point of entrance before terminating in an enclosure, unless it is in a suitable raceway (770.48); conductive members must be bonded or interrupted at the entrance (770.93 and 770.100); and communications circuits that may be exposed to lightning or power contact need listed primary protectors (800.90).

The entrance room then holds the splice enclosures or OSP termination panels, carrier equipment and the patch panels that connect to the building backbone. In multi-tenant and colocation buildings, carriers often have their own locked cages or cabinets in the entrance room, and the operator's staff make the cross-connects between them.

Diagram of a building entrance. Outside plant cable comes up from a maintenance hole through a sealed conduit that slopes down away from the building. Inside the building wall, the cable reaches a splice enclosure in the entrance room within a short distance of the entrance point, where it is spliced to indoor-rated cable. The armor is bonded to the telecommunications bonding busbar. Indoor cable continues to an OSP termination panel and to carrier equipment, then to the backbone toward the main distribution area.
At the entrance, OSP cable is sealed, bonded and spliced to listed indoor cable close to the point of entrance.

Carrier connectivity

A data center connects to the outside world through several kinds of service and arrangement:

  • Lit services: a carrier provides bandwidth, such as an Ethernet circuit or a wavelength at a given speed, over its own equipment. The carrier manages the optics and the network.
  • Dark fiber: the operator leases fibers with no equipment and lights them with its own optics, gaining capacity limited only by its equipment. Long-term dark fiber is often acquired as an indefeasible right of use (IRU), a prepaid lease of typically 15 to 25 years.
  • Internet exchange points and peering: the operator connects to networks at an exchange or in a carrier hotel (a building where many carriers interconnect) to exchange traffic directly (DCE-210).
  • Cross-connects in colocation: in a colocation facility, the customer pays the operator a monthly fee for each cross-connect from its cage to a carrier in the meet-me room. A carrier-neutral facility, with many competing carriers present, is valuable to tenants.

Building routes in public rights of way requires permits or franchise agreements from the city, county or state transportation department that controls the road, and railway crossings need agreements with the railroad. Attachments to utility poles are governed by agreements with the pole owner and by FCC pole attachment rules (47 U.S.C. § 224), or by the state in states that regulate attachments themselves. Data center developers who are not carriers usually contract with a carrier or a fiber builder to construct and own the off-site routes.

The schedule for OSP is often longer than for the building cabling: permits, road crossings and a single uncooperative landowner can add months. As noted in DCE-200, diverse fiber routes into a site must be planned with the site selection, not after the building is designed.

Lesson 12 draws the course together in a complete project, including the diverse entrances and routes covered here.

Common mistakes

  • MistakeAccepting two carriers as diverse because they are different companies.

    InsteadOverlay their route maps; carriers often share ducts, bridges and corridors.

  • MistakeBringing two entrance conduits into the building side by side.

    InsteadEnter on separate sides with separate maintenance holes, ideally at least 20 m apart, and keep the routes separate inside.

  • MistakeRunning unlisted OSP cable through the building to the MDA.

    InsteadTransition to listed indoor cable (or a suitable raceway) close to the entrance point, as the electrical code requires.

  • MistakeDesigning long links with no allowance for repairs.

    InsteadAdd margin for repair splices and aging; each cable cut adds at least one splice.

  • MistakeLeaving entrance conduits unsealed.

    InsteadSeal every conduit, including spares, against water and gas, and slope conduits away from the building.

  • MistakeExcavating near fiber routes without locates.

    InsteadContact 811 for locates before any digging.

Summary and key terms

  • Most connectivity outages are cable cuts; diversity of routes and entrances is the main defense.
  • OSP is built as concrete-encased duct banks with innerduct and maintenance holes, direct-buried cable, or aerial cable; HDD and micro-trenching avoid open trenches.
  • High-count ribbon cables (up to 6912 fibers) are mass-fusion spliced 12 fibers at a time; rollable ribbon packs more fiber per duct.
  • Long-link budgets include fiber attenuation, splices, connectors and a repair allowance; fiber loss dominates at tens of kilometers.
  • Diverse routes must share no duct, bridge, corridor or entrance; verify by overlaying route maps and re-check periodically.
  • Two independent routes reduce outage roughly from U to U²; a single shared section can dominate the result.
  • Entrances: slope and seal conduits, bond metallic members, protect copper circuits, and transition OSP cable to listed indoor cable close to the entrance.
  • Connectivity: lit services, dark fiber (often IRUs), peering at exchanges, and cross-connects in carrier-neutral meet-me rooms.
Outside plant (OSP)
Cabling and pathways outside buildings, including duct banks, maintenance holes, poles and buried cable.
Duct bank
A group of underground conduits, often encased in concrete.
Innerduct
Smaller ducts installed inside a conduit to subdivide it for separate cables.
Maintenance hole
An underground vault used for pulling, splicing and storing slack cable.
Horizontal directional drilling (HDD)
A steerable trenchless method of installing conduit under obstacles.
Air-blown fiber
Fiber cable installed in microducts by compressed air.
Ribbon fiber
Fibers bonded side by side in groups (usually 12) for mass fusion splicing.
Mass fusion splicing
Splicing all fibers of a ribbon in one operation.
Shared risk link group (SRLG)
A set of links that share a physical element and can fail together.
Dark fiber
Leased fiber with no carrier equipment, lit by the customer.
Indefeasible right of use (IRU)
A long-term, prepaid right to use specific fibers.
Carrier-neutral
A facility open to any carrier, giving tenants a choice of connectivity.
Primary protector
A device at the building entrance that limits lightning and power-cross voltages on copper circuits.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. Why is direct-buried cable cheaper than duct bank construction, and what is its main drawback?

    Show answer

    It needs no conduit or concrete; but adding or replacing cable requires digging again.

  2. How many 12-fiber ribbons are in a 1728-fiber cable?

    Show answer

    1728 / 12 = 144 ribbons.

  3. Calculate the loss of a 12 km link at 1310 nm with 0.35 dB/km, five splices at 0.1 dB and two connector pairs at 0.5 dB.

    Show answer

    4.2 + 0.5 + 1.0 = 5.7 dB.

  4. Will the previous link meet a 6.3 dB budget with a 1 dB repair allowance?

    Show answer

    5.7 + 1.0 = 6.7 dB, which exceeds 6.3 dB; a longer-reach optic or fewer connections is needed.

  5. A route has an unavailability of 0.002. Estimate the unavailability of two independent such routes.

    Show answer

    0.002² = 4 × 10⁻⁶, about 2 minutes per year.

  6. Name three places where two apparently diverse routes often share risk.

    Show answer

    Bridges and river crossings; road or rail corridors; the same third-party duct bank; the building entrance or entrance room; a shared central office.

  7. Why are entrance conduits sloped away from the building?

    Show answer

    So that water entering the duct system drains outward rather than into the building.

  8. What must be done with the armor of an OSP cable at the building entrance?

    Show answer

    Bond it to the telecommunications bonding system (or interrupt it as the code permits), so that lightning and fault currents are safely conducted.

  9. What is the difference between a lit service and dark fiber?

    Show answer

    A lit service is bandwidth provided over the carrier's equipment; dark fiber is bare fiber that the customer lights with its own optics.

  10. Why is a carrier-neutral meet-me room valuable to colocation tenants?

    Show answer

    Tenants can choose among competing carriers, connect to several for diversity, and switch carriers with a cross-connect rather than new construction.

Lesson quiz · 5 questions

Score 60% or more to complete this lesson.

Take the quiz