MSBA-150 · Lesson 12 of 12 · 20 min

Case study: moving a business off spreadsheets

▶ Video coming soon A video version of this lesson is on the way.

This capstone brings the course together. You will work through the decisions Corbel & Finch made in November 2026 as they prepared to switch from an old desktop accounting package and a family of spreadsheets to Business Central on January 1, 2027. Each part sets a task, shows the facts the team had, and then gives the answer they reached, with the reasoning. Try each task before reading the answer.

The situation in November 2026

Corbel & Finch at the start of the case.
FactDetail
BusinessCoffee roaster with wholesale, a web shop and two cafés; about 40 staff; one legal entity
Old systemsDesktop accounting package, spreadsheets for inventory, pricing and green-coffee contracts
Users9 people need full access, 3 café managers need read access and approvals, 2 shared warehouse scanners
VolumesAbout 600 sales invoices and 120 supplier invoices a month; 228 active customers; 180 vendors; 260 items
ProductionGreen coffee is roasted in batches and bagged; one input, one roast, one bagging step per product
Go-live targetJanuary 1, 2027, the start of the fiscal year; first transactions dated January 2
TeamBettina (owner, sponsor), Callum (in-house lead), Noor (partner consultant and developer), Imogen (purchasing)

Task 1: choose licences

Decide which licences Corbel & Finch needs and whether full users should have Essentials or Premium. Use the United States list prices from November 2025 (80 dollars for Essentials, 110 for Premium, per user per month) as a reference, and consider whether the roasting process needs manufacturing features.

Worked problem

Licence decision

Nine full users, three café managers who look up data and approve requests, and two shared scanners. Is Premium worth it for roasting?

Show solution
  1. Full users: 9. The café managers fit the Team Member licence (read, approve, light edits). The scanners each take a Device licence.
  2. Premium adds manufacturing (production orders, routings, capacity) and service management. Corbel & Finch's process has one input, one roast and one bagging step, which assembly orders in Essentials can represent: an assembly bill of materials consumes green coffee and packaging and outputs bagged coffee at a calculated cost.
  3. Cost difference at list price: 9 users × (110 − 80) = 270 dollars a month, or 3,240 dollars a year, for features the company would not use.
  4. Decision: Essentials for full users, revisit Premium if the company later needs routings, capacity planning or service contracts.

Answer: 9 Essentials, 3 Team Member and 2 Device licences. Assembly orders cover roasting; Premium would cost about 3,240 dollars a year more at list prices without a matching need.

Because Essentials and Premium cannot be mixed freely for full users in one tenant, the team noted that a later move to Premium would apply to all nine full users, and recorded that in the decision log.

Task 2: environments and companies

Lay out the environments and companies the project needs from now until a month after go-live.

The answer: one production and three sandbox environments, all included in the subscription.
EnvironmentTypeCompaniesUse
PRODProductionCorbel & Finch Coffee Roasters Ltd.Live company from go-live
CONFIGSandboxThe configured company, plus CRONUSConfiguration, test migrations, user testing
TRAININGSandboxA copy of the configured company with test dataStaff training in December
UPDATE-TESTSandboxA copy of production made each release waveTesting major updates and extensions before they reach production

One company is enough because there is one legal entity; the cafés and wholesale are separated with the BUSINESS LINE dimension and locations. The sandboxes use the three included with the subscription, so no extra environments need to be bought.

Task 3: the setup checklist

List, in order, the setup that must be complete in the CONFIG sandbox before the final test migration. Then say how it reaches production.

The configuration checklist.
OrderSetupLesson
1Company Information, accounting periods for 2026 and 2027, posting date windows3
2Number series and links on Sales & Receivables, Purchases & Payables and Inventory Setup3
3Chart of accounts with account categories, 168 accounts6, 11
4Posting groups: specific and general, general posting setup, inventory posting setup by location7
5Tax setup: tax areas, jurisdictions and groups7
6Dimensions: BUSINESS LINE and DEPARTMENT global, CAMPAIGN, SALESPERSON, ORIGIN shortcut; defaults and blocked combinations8
7Templates for customers, vendors and items4
8Approval user setup, workflows, notifications and email9
9Report layouts and report selections for invoices and statements3
10Security groups, permission sets and profiles, customized pages for each role2, 5
11Copilot capabilities reviewed and set10
12Financial reports, the analysis view and Power BI apps11

Setup reaches production as a configuration package exported from CONFIG and applied to the production company, followed by a check that each setup table matches. Security groups, profiles and Copilot settings are applied in production by hand, because some of them are environment-wide rather than company data.

Task 4: migration and opening balances

Describe what will be migrated, how, and how the team will prove it is right.

Worked problem

Migration plan

The old system holds nine years of history. The cutover date is December 31, 2026. What moves, by which method, in what order?

Show solution
  1. Master data (December 18 to 20, after a freeze on new customers and vendors in the old system): 228 customers, 180 vendors and 260 items, cleansed and mapped, imported through configuration packages with templates.
  2. Open transactions (January 1 to 2): 340 open sales invoices and about 90 open purchase invoices as individual documents through journals; open purchase orders for green coffee re-entered as purchase orders.
  3. Balances (January 1 to 2): inventory by item and location through item journals from the December 31 count; bank balances and remaining G/L balances through a general journal, excluding receivables and payables already posted through customers and vendors.
  4. History: 24 months of monthly G/L net change by account and BUSINESS LINE for comparatives; detailed history kept read-only in the old package.
  5. Proof: reconcile record counts, aged receivables and payables, inventory quantity and value, and the trial balance account by account; Bettina signs off.

Answer: Master data first, then open documents, then balances, then summarized history, with a signed reconciliation of counts, subledgers, inventory and the trial balance.

Task 5: the cutover timeline

Build a timeline from the start of December to the first month-end close.

A horizontal timeline from December 1, 2026 to February 5, 2027. Markers: December 1 to 12 user acceptance testing; December 7 to 16 training; December 15 dress-rehearsal migration; December 18 master data freeze and load; December 23 go or no-go decision; December 31 old system closed; January 1 and 2 opening balances and reconciliation; January 4 first full day of trading in Business Central; January 4 to 29 hypercare; February 1 to 5 first month-end close.
The Corbel & Finch cutover timeline.
Cutover milestones.
DateMilestoneOwner
Dec 1 to 12User acceptance testing with scripted scenarios for each roleCallum
Dec 7 to 16Training in the TRAINING sandbox, by roleNoor and Callum
Dec 15Dress-rehearsal migration, timed, into a copy of productionNoor
Dec 18 to 20Master data freeze in the old system; load master data into productionCallum
Dec 23Go or no-go decision against agreed criteriaBettina
Dec 31Final sales and purchases in the old system; physical inventory countCallum and roastery manager
Jan 1 to 2Open documents, opening balances, reconciliation and sign-offCallum, Noor, Bettina
Jan 4First full trading day in Business CentralEveryone
Jan 4 to 29Hypercare: daily check-ins, quick fixes, issue logNoor
Feb 1 to 5First month-end close in Business CentralCallum

Task 6: go or no-go criteria

Write the criteria Bettina will use on December 23. Good criteria are specific and measurable, not "we feel ready".

Go or no-go criteria.
CriterionMeasure
Testing completeAll critical test scenarios passed; no open critical or high-severity issues
Migration rehearsedDress rehearsal completed within the planned time with a clean reconciliation
People trainedEvery user has completed role training and one practice task in the TRAINING sandbox
Access readyAll users can sign in to production with the right role centre and permissions
Documents readyInvoice, statement and order confirmation layouts approved
Integrations readyWeb shop orders flow to Business Central in the sandbox test; bank file format tested
Fallback definedOld system can be used for one more week if needed, with a plan to re-run cutover

Task 7: risks

Name the top risks and a response for each.

The risk register.
RiskLikelihoodResponse
Inventory count on December 31 is wrongMediumCount by location with two people per area; recount differences above a threshold
Web shop integration fails in the first weekMediumTest in sandbox; manual order entry procedure ready for up to 30 orders a day
Users revert to spreadsheetsHighRemove old pricing workbook access; role centres show what users need; hypercare check-ins
Posting setup error discovered after go-liveMedium40 test postings checked with Find entries; daily trial balance review in January
Approvals slow purchasingLowLimits set at realistic levels; substitutes defined; notifications tested
A major update arrives during hypercareLowSchedule the update window after hypercare in the administration center

The update risk is specific to cloud ERP. Microsoft's 2026 release wave 2 began rolling out in October 2026, so production would already be on version 29 at go-live, but the next major update, 2027 release wave 1, would arrive from April 2027. Noor set the update window so that it would not land during the first close, and planned to test the update in the UPDATE-TEST sandbox first.

Task 8: the first month-end

Write the first month-end checklist in Business Central, linking each step to what the course covered.

The first month-end checklist.
StepHow in Business Central
Make sure all January documents are postedCues for unposted orders and invoices on the role centre
Reconcile bank accountsBank account reconciliation with Copilot assist, reviewing every proposed match
Adjust item costs and post inventory costJob queue entries for cost adjustment, checked for errors
Review receivables and payablesAged reports; apply unapplied payments
Check dimensionsTrial balance filtered by BUSINESS LINE; correct errors with Dimension Correction
Post accruals and adjustmentsGeneral journal, approved through the journal approval workflow if required
Lock JanuaryPosting date window on General Ledger Setup moved to February; Callum keeps January on User Setup until done
ReportFinancial reports, CAFE-GM and the Power BI dashboard

On the first Monday of February 2027, the plan says, Bettina will have her numbers. Whether she believes them will depend on the reconciliation work in Task 4 and the posting setup checks in Task 3, which is why so much of a Business Central project happens before anyone posts a real transaction.

Reflecting on the case

Projects like this one fail less often from software problems than from skipped preparation: data that was never cleaned, posting setup that was never tested, users who were never trained in their own role. The structure of Business Central, with master data, documents, posting groups, dimensions and permanent ledgers, rewards careful setup and punishes shortcuts. The next courses in the MB-800 program go deeper into finance, and the MB-820 program covers the developer side, including the extensions that Quarrystone builds for the web shop integration.

Task 9: training and hypercare

Plan training by role and the support arrangements for the first weeks.

Training plan by role.
GroupTrainingLengthProof of readiness
Order processorsSales orders, invoices, credit memos, customer lookups, Copilot sales line suggestionsTwo half daysEnter and post five practice orders in the TRAINING sandbox
PurchasingPurchase orders, receipts, invoices, approvalsOne half dayProcess one green-coffee order end to end
Warehouse and roasteryReceipts, assembly orders, transfers, counts on scannersOne half dayPost an assembly order and a transfer
Café managersItem lookups, approvals on phone and browserOne hourApprove a test request on a phone
CallumEverything above plus setup, close, reports and administrationThroughout the projectRuns the dress rehearsal

Hypercare ran for four weeks after go-live. Noor held a 15-minute check-in every morning in the first week and twice a week after that, and every issue went into a shared log with a severity, an owner and a date. Most issues in the first week were small: a field users wanted on a page (solved by customizing the profile), a printer setting, two permission gaps found by Effective Permissions. The log was closed when two weeks passed with no new high-severity issues, which became the formal end of the project.

Common mistakes

  • MistakeBuying Premium "just in case".

    InsteadMatch licences to processes; assembly orders in Essentials cover simple production.

  • MistakeGoing live without measurable go or no-go criteria.

    InsteadAgree specific criteria in advance and decide against them.

  • MistakeLetting a major update land during the first close.

    InsteadSchedule update windows and test updates in a sandbox.

  • MistakeEnding the project at go-live.

    InsteadPlan hypercare and the first month-end close as part of the project.

Summary and key terms

  • Licences follow processes: 9 Essentials, 3 Team Member and 2 Device licences fit Corbel & Finch.
  • One production and three sandbox environments cover configuration, training and update testing.
  • Setup is completed and tested in a sandbox and moved to production with configuration packages.
  • Migration moves master data, open documents, balances and summarized history, proven by reconciliation.
  • A cutover timeline, go or no-go criteria and a risk register make the switch predictable.
  • Hypercare and the first month-end close are part of the project.
Assembly order
A document that consumes components and outputs an assembled item, available in Essentials.
User acceptance testing
Testing by business users of the configured system against real scenarios.
Dress rehearsal
A full, timed practice run of the migration and cutover.
Go or no-go decision
The decision, against agreed criteria, whether to proceed with go-live.
Hypercare
A period of intensive support right after go-live.
Risk register
A list of project risks with likelihood and planned responses.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. Why did the team choose Essentials over Premium?

    Show answer

    Roasting fits assembly orders in Essentials, and Premium would cost about 3,240 dollars a year more at list prices for unused features.

  2. Which sandbox protects production from surprises in a release wave?

    Show answer

    UPDATE-TEST, a copy of production used to test each major update.

  3. Name three go or no-go criteria.

    Show answer

    For example: critical tests passed, migration rehearsed with a clean reconciliation, users trained, access ready, a fallback plan defined.

Lesson quiz · 5 questions

Score 60% or more to complete this lesson.

Take the quiz