PWR-510 · Lesson 1 of 12 · 21 min
The chief engineer's responsibilities
▶ Video coming soon A video version of this lesson is on the way.
Anselm Rasmusen had been a shift supervisor at Keswold Energy Centre since the plant was commissioned in 2020. Before that he had spent years at the pulp mill where he and Grazyna Wolanski had worked side by side. He held a Second Class certificate, which is what O. Reg. 219/01 asks of a shift engineer in a first-class plant, and Keswold's rating, set by its heat recovery steam generator and steam turbine, makes it a first-class plant. In the autumn of 2026 Morwenna Faulds, Keswold's chief engineer, told him she planned to retire in 2028 and that the owner wanted him to succeed her. That meant a First Class certificate, so Anselm enrolled in a part-time First Class Power Engineering course and Morwenna offered to meet him one evening a week in the training room.
"The certificate on the wall is the small part," Morwenna said at their first session. "The big part is that everything in this plant that can hurt someone, break, leak, cost money or break the law ends up on your desk. You don't do all of it yourself. You make sure it gets done, by the right people, and you can show that it was." She began with a blank sheet of paper and asked Anselm to list everything the chief engineer is answerable for. It took him most of an hour.
This lesson sets out the legal and practical responsibilities of a chief engineer: the duties the law places on the chief and on the owner, the difference between being responsible and doing the work, the chief's role in operations, maintenance, engineering, safety, the environment, people and money, and how the chief manages all of that through systems, delegation and records. It closes with the path to the highest certificate or license and what the examinations at that level expect.
A legal position, not only a job title
In Ontario, the Technical Standards and Safety Act and O. Reg. 219/01 make the chief operating engineer a defined legal position. The owner of a registered plant must appoint a chief operating engineer who holds a certificate of the class the plant's rating requires, and must notify TSSA of the appointment. The chief is responsible for the operation of the plant and for ensuring that a qualified operating engineer is on duty as shift engineer whenever any unit is operating. The regulation also sets limits that shape the job: in a first- or second-class plant, the chief operating engineer may not also serve as the day shift engineer, and every shift engineer must hold a certificate no more than one class lower than the chief's required class.
Alberta takes the same approach through ABSA and the Power Engineers Regulation, which set the class of chief power engineer by the size and type of plant and allow some plants to operate under an approved alternative such as a reduced attendance or remote monitoring program. Other provinces follow the same pattern with their own tables. The details differ, but the idea is common to all of them: the size and hazard of the plant set the class of the person in charge, and that person carries a duty that cannot be handed back to the owner.
The owner's duties remain. The owner must register equipment, keep it in a safe condition, pay for inspections and repairs, provide competent staff and the resources they need, and not direct anyone to operate unsafely. A chief engineer who is refused the resources to operate safely has a duty to say so in writing and, if necessary, to the regulator. Morwenna put it bluntly: "The owner can overrule my budget. The owner cannot overrule my judgment about whether a boiler is safe to run."
Responsible is not the same as doing
A chief engineer at a plant the size of Keswold cannot personally watch every shift, inspect every vessel or approve every work order. The job is to build and run the systems that make those things happen and to check that they work. That is the difference between accountability, which stays with the chief, and delegation, which hands the work and the authority for it to someone else. Delegation without a clear scope, the competence to do the work and a way of checking it is not delegation; it is abdication.
Morwenna showed Anselm Keswold's delegation of authority table. It lists, for each type of decision, who may make it and who must be told. Shift supervisors may take equipment out of service, approve lockouts and permits, and call in contractors for urgent work within a spending limit. The maintenance planner schedules the backlog. The reliability engineer, Ingeborg Haverlund, sets inspection plans and condition monitoring intervals. Some decisions stay with the chief: returning a pressure vessel to service after a repair, approving a change to a safety instrumented function, accepting a deviation from a code or a jurisdictional requirement, and signing anything that goes to a regulator.
- Written authority says what each role may decide, approve and spend.
- Competence is checked before authority is given, through qualification records, not assumed from seniority.
- Reporting brings back what was decided, so that the chief can see patterns and step in when something drifts.
- Audit samples the work, as Pilar's permit audit did at Cantwell (PWR-420), to confirm that the system works as written.
The chief engineer's areas of responsibility
Anselm's hour-long list, tidied up, fell into eight areas. Each is the subject of later lessons in this course or earlier courses in the program, and each needs a system, an owner and a record.
- Operations. Safe, reliable and efficient operation within the plant's limits: procedures, shift staffing, handover, logs, alarms, operating envelopes and the conduct of operations (PWR-420).
- Maintenance and reliability. A maintenance strategy based on failure modes and consequences, planned work, condition monitoring, spares, backlog and the decisions about repair, replacement and life extension (PWR-420, lessons 7 and 8 of this course).
- Engineering and projects. Design reviews, modifications, management of change, capital projects and outages, and the economic case for each (lessons 2 to 6).
- Pressure equipment integrity. Registration, inspection, repairs and alterations by qualified organizations, relief device servicing and records, increasingly managed through risk-based inspection (PWR-340, lesson 7).
- Health and safety. The employer's duties under occupational health and safety law, process safety management where it applies, permits, lockout, contractor safety and incident investigation (PWR-340, PWR-420).
- Environment. Air approvals or permits, water and wastewater, spills, emissions reporting and greenhouse gas programs (PWR-420, lesson 10).
- People and training. Staffing, recruitment, qualification, succession, discipline and the culture of the plant (lesson 11).
- Budgets and contracts. The operating and capital budgets, service contracts, long-term agreements and the plant's commercial obligations to customers such as Marrowby Foods (lesson 11, PWR-420).
Running through all eight is the chief's relationship with the owner, the regulators, the insurer and the customers. Lesson 9 deals with regulators and audits. The steam contract with Marrowby Foods is a reminder that a cogeneration plant's chief has a customer across the road whose production depends on the plant's reliability, and whose own auditors check Keswold as a supplier (PWR-340).
The chief engineer's working rhythm
Morwenna's week has a pattern that has hardly changed in twenty years. Each morning she reads the shift logs and the overnight alarm summary, walks part of the plant, and holds a fifteen-minute meeting with the day shift supervisor, the maintenance planner and Ingeborg. Each week she reviews the backlog, the permits issued, open management of change items and the week's operating data against its targets. Each month she reports to the owner on safety, reliability, efficiency, emissions, costs and the status of projects, and she meets Marrowby's plant engineer to review steam supply. Each year she prepares the budget and capital plan, reviews every major procedure, chairs the management review of the safety and environmental programs, and plans the outage.
| Interval | Typical chief engineer activities |
|---|---|
| Daily | Read logs and alarm summary, walk part of the plant, short coordination meeting |
| Weekly | Backlog and permits review, open MOCs, operating data against targets |
| Monthly | Owner report, customer meeting, KPI review, safety committee follow-up |
| Quarterly | Contract reviews, emergency plan contacts check, training progress |
| Annually | Budget and capital plan, procedure review, management review, outage plan |
The rhythm matters because problems rarely announce themselves. The boiler 3 pitting at Cantwell came from a routine test that quietly dropped off a task list months earlier (PWR-340). A chief who looks at the same indicators at the same intervals notices when a line on a report stops moving, a backlog grows, or the same alarm appears on every night shift.
Records that prove the work was done
A plant is judged by its records as much as by its equipment. Regulators, insurers, auditors and lawyers ask to see the operating log, the inspection and repair records, relief valve servicing records, permits and lockout records, training and qualification records, management of change files, incident reports and environmental data. Many of these have legal retention periods, and all of them are evidence of whether the plant's systems work. Morwenna's rule is that a record should be made at the time, by the person who did the work, in a form someone else can understand in ten years.
O. Reg. 219/01 requires a log book for every registered plant, kept by the operating engineers on duty and checked by the chief operating engineer, and TSSA inspectors routinely read it. The pressure equipment code adoption document sets its own record and notification requirements, such as keeping inspection records and notifying TSSA of certain events within set periods (PWR-340).
When the chief must say no
Most of a chief engineer's decisions are about how to do things. A few are about whether to do them at all: whether to return a boiler to service with an unresolved defect, whether to run a turbine with a vibration trend that is rising, whether to accept a contractor's crew whose permits are poorly filled in, whether to defer an inspection to suit production. In each case the chief has to weigh the commercial pressure against the risk and make a decision that can be defended later. Morwenna's advice was to write the reasons down before making the decision, not after.
The Keswold bearing 3 vibration trend from November 13 is a live example (PWR-320). The 1X amplitude rose from 38 to 52 micrometres, well below the alarm of 100, and the plan is a trim balance at the next short shutdown. Anselm asked when Morwenna would stop the unit instead. "If the trend steepens, if the phase moves, if the bearing metal temperature changes, or if anything at all happens that the trim balance theory does not explain," she said. "Marrowby would rather lose steam for a day than lose it for a month."
The path to the highest certificate or license
TSSA's First Class guideline, which took effect in June 2021, sets the experience at 4,800 hours as chief operating engineer of a second-class plant or as a second-class operating engineer in a second- or first-class plant, or 3,360 hours for a graduate of an approved full-time First Class program. At least a third of the experience must be in boiler operation in a registered plant, and no more than a third may be maintenance of regulated equipment. There are eight examinations, 1A-1 to 1A-4 and 1B-1 to 1B-4, all essay style: each runs 3.5 hours, the candidate answers any five of seven questions, the pass mark is 65 in 100, and a failed paper can be rewritten after 60 days. Examinations and experience can be completed in any order, and a candidate who passes must obtain the certificate within five years.
Worked problem
Checking the experience
Anselm's log extract for the last 30 months shows 5,460 hours as a second-class operating engineer at Keswold, of which 2,350 hours were spent with the heat recovery steam generator or the auxiliary boiler under his direct charge and 1,010 hours on maintenance of regulated equipment. Does this meet the TSSA First Class requirement on its own?
Show solution
- \[\frac{2{,}350}{5{,}460} = 0.43 \ge 0.33 \qquad \frac{1{,}010}{5{,}460} = 0.18 \le 0.33\]
- \[5{,}460 \text{ h} \ge 4{,}800 \text{ h}\]
Answer: Yes. The total exceeds 4,800 hours, the boiler operation share is 0.43, above the minimum of a third, and the maintenance share is 0.18, below the maximum of a third. The experience needs to be confirmed in a letter from the chief operating engineer on company letterhead, which Morwenna will write. Anselm can sit the examinations at his own pace while his record is assessed.
The First Class papers test the same subjects as the Second Class papers at greater depth and with a management emphasis: applied mechanics and thermodynamics, metallurgy and materials, codes and design calculations, boilers and their auxiliaries, prime movers and electrical machines, instrumentation and control, plant management, environment and law. Essay answers are marked for completeness and reasoning as much as for the final number. Morwenna's advice was the same as Grazyna's had been for Pilar: plan the papers like a project, write practice answers in full, and have someone mark them (PWR-420).
"You'll find that the First Class material is mostly about decisions," Morwenna said, "and the engineering is there so you can make them on evidence. Every lesson from here on, ask yourself who decides, on what information, and what record is left behind."
Common mistakes
MistakeThinking the chief engineer's duties transfer to the owner when the owner sets the budget.
InsteadThe owner sets resources; the chief's duty for safe operation stays with the chief and must be raised in writing if resources are inadequate.
MistakeDelegating work without written authority, checked competence and reporting.
InsteadDelegate with a written scope, qualified people and a way to check the work.
MistakeTreating records as paperwork to be done after the job.
InsteadMake records at the time, by the person who did the work, in a form others can understand later.
MistakeAssuming seniority proves competence.
InsteadCheck qualification records before giving authority.
MistakeDeciding first and writing the reasons later.
InsteadWrite down the reasons before a difficult decision, so the decision can be defended.
MistakeCounting total hours without checking how they divide between operation and maintenance.
InsteadBreak experience down the way the examining body asks, with dates and a signed confirmation.
Summary and key terms
- The chief engineer holds a defined legal position in many jurisdictions and an owner-defined one elsewhere; the class required follows the size and hazard of the plant.
- The owner provides registration, resources and competent staff; the chief is accountable for safe operation and must say so in writing when resources are inadequate.
- Accountability stays with the chief; work is delegated through written authority, checked competence, reporting and audit.
- The chief's responsibilities cover operations, maintenance and reliability, engineering and projects, pressure equipment integrity, health and safety, environment, people and budgets.
- A regular working rhythm and good records let the chief see when systems drift.
- The path to the highest certificate or license depends on documented experience and examinations at a management level.
- Chief operating engineer
- The person appointed by the owner to be responsible for the operation of a registered plant.
- Accountability
- Responsibility for an outcome that stays with a person even when the work is delegated.
- Delegation of authority
- A written statement of which roles may make which decisions, approvals and commitments.
- Shift engineer
- The qualified engineer in charge of the plant on a shift.
- Log book
- The plant's continuous record of operation, kept by the engineers on duty.
- Owner
- The person or organization that owns the plant and carries the duties of registration, maintenance and resourcing.
- Management review
- A periodic review by senior management of whether a management system is working and what must change.
Practice problems
Work each problem on paper first, then reveal the answer to check.
A candidate has 4,950 hours, 1,500 of them boiler operation and 1,700 maintenance. Does the TSSA split work?
Show answer
No: boiler operation is 0.30, below a third, and maintenance is 0.34, above a third.
In a first-class plant, may the chief operating engineer also be the day shift engineer?
Show answer
No.
What class must a shift engineer in a plant needing a First Class chief hold at minimum?
Show answer
Second Class.
How long after passing must a TSSA First Class candidate obtain the certificate?
Show answer
Within five years.
Lesson quiz · 5 questions
Score 60% or more to complete this lesson.