PRIN-160 · Lesson 9 of 12 · 25 min

Practising the processes I: starting up, directing and initiating

The seven processes describe the journey of a project from its first request to its closure, and the exams test them in two ways. Foundation asks about their purposes, objectives, triggers, activities and outputs. Practitioner asks which process is running in a scenario, who should be doing what, and what should happen next. This lesson covers the three processes that get a project off the ground: starting up a project, directing a project and initiating a project. Lesson 10 covers the four that run and end it. As always, check the exact activity names in your manual before the exam; this lesson uses descriptive wording.

How the processes fit together

A project begins when the business layer issues a project mandate. Starting up a project is a pre-project process that checks whether the project is viable and worthwhile and prepares for initiation. Directing a project runs from the end of starting up until closure and is where the project board makes its decisions. Initiating a project is the first management stage, which builds the foundation for the rest of the project: the project initiation documentation, the project plan and the detailed business case. Controlling a stage, managing product delivery and managing a stage boundary then repeat for each delivery stage, and closing a project ends it.

A horizontal timeline. Pre-project: starting up a project, triggered by a project mandate. Initiation stage: initiating a project. Subsequent stages: controlling a stage and managing product delivery, with managing a stage boundary at the end of each stage. Final stage: closing a project. A band above the whole timeline is labelled directing a project, with decision points marked at authorize initiation, authorize the project, authorize each stage and authorize closure.
The PRINCE2 processes across the life of a project.

Starting up a project: revision points

Starting up a project: points that exams test.
PointWhat to remember
TriggerThe project mandate from the business layer
PurposeEnsure the prerequisites for initiating are in place by answering whether the project is viable and worthwhile
Key activitiesAppoint the executive and project manager; capture previous lessons; prepare the outline business case; design and appoint the project management team; select the delivery approach and assemble the project brief; plan the initiation stage
Main outputsProject brief (including the outline business case and project product description); initiation stage plan; daily log; lessons log
Who does most of the workThe executive is appointed first; the project manager then prepares most products
Ends withA request to the board to initiate the project

Two points catch candidates. First, the executive is appointed before the project manager, because the executive is accountable and appoints the rest of the team. Second, starting up is deliberately short and light. Its purpose is to stop poorly conceived projects before money is committed to initiation, so a scenario where starting up takes months and produces a detailed plan has probably gone wrong.

Directing a project: revision points

Directing a project: points that exams test.
PointWhat to remember
TriggerThe request to initiate a project, from starting up
PurposeEnable the board to be accountable for success by making key decisions and exercising overall control while delegating day-to-day management
Key activitiesAuthorize initiation; authorize the project; authorize a stage or exception plan; give ad hoc direction; authorize project closure
How the board worksBy exception: it sets tolerances and responds to exceptions, rather than managing day to day
Ad hoc directionResponds to requests for advice, exception reports and external events; can be given at any time
Ends withClosure authorized and the business layer notified

The most frequent Practitioner question about directing asks whether the board is behaving as a board. Boards that approve individual work packages, hold weekly progress meetings to tell the project manager what to do next, or skip stage boundary decisions are not directing by exception. Equally, a board that never gives direction when the project manager asks for advice is failing in its role.

Initiating a project: revision points

Initiating a project: points that exams test.
PointWhat to remember
TriggerAuthority to initiate from the board
PurposeEstablish solid foundations so the organization understands the work needed before committing to a significant spend
Key activitiesAgree the tailoring requirements; prepare the management approaches; set up project controls; create the project plan; refine the business case; assemble the project initiation documentation
Management approachesIncluding risk, quality, change control, communication, commercial, sustainability, and digital and data management approaches
Main outputsProject initiation documentation; detailed business case; project plan; benefits management approach; next stage plan (prepared in managing a stage boundary near the end of initiation)
Ends withA request to the board to deliver the project

Initiation is a management stage with its own stage plan and its own boundary. Near its end, managing a stage boundary prepares the plan for the first delivery stage, so the board can authorize the project and the next stage at the same time. Questions sometimes test this overlap by asking which process produces the first delivery stage plan.

Foundation-style practice

Original Foundation-style questions on the first three processes.
QuestionOptionsAnswer and reasoning
Which process is triggered by the project mandate?A. Directing a project; B. Starting up a project; C. Initiating a project; D. Managing a stage boundaryB.
Which role is appointed first in starting up a project?A. Project manager; B. Executive; C. Senior user; D. Team managerB.
Which is NOT an activity in directing a project?A. Authorize the project; B. Give ad hoc direction; C. Authorize a work package; D. Authorize project closureC. Work packages are authorized by the project manager in controlling a stage.
Which product is assembled in initiating a project?A. Project brief; B. Project initiation documentation; C. End project report; D. Checkpoint reportB.
What is a purpose of starting up a project?A. Deliver specialist products; B. Ensure the prerequisites for initiating are in place; C. Authorize stages; D. Hand over productsB.

Practitioner-style practice: a new branch project

Scenario extract. Harbour City Libraries' board of trustees has asked the library to open a small branch in a leased storefront in a growing neighbourhood. The director of library services, who will be executive, appoints Dev Sharma as project manager. Dev starts by reviewing the lessons report from the makerspace refit and the accessibility upgrade. He drafts a project brief with an outline business case comparing a leased storefront with a mobile library van, and plans a three-week initiation stage. A trustee suggests skipping initiation because 'the lease is already signed and the design is simple'.

Practitioner-style questions on starting up, directing and initiating (invented scenario).
QuestionAnalysisAnswer
Which process is Dev carrying out?He is preparing the project brief and initiation plan before the board decides to initiate.Starting up a project.
Is it appropriate for Dev to review the earlier lessons reports?Capturing previous lessons is part of starting up and applies learn from experience.Yes, because lessons are sought at the start of the project.
Is skipping initiation appropriate because the lease is signed?Manage by stages requires at least two management stages, initiation being the first. Initiation can be short.No. Initiation can be brief and light, but it is still needed to agree the plan, controls and business case.
The executive wants to approve the project brief and the project plan at the same meeting next week. Is this appropriate?The project brief leads to authorizing initiation; the project plan is created during initiation, so it cannot be ready yet.No. The board authorizes initiation on the brief; it authorizes the project later, on the project initiation documentation.

The branch's lease must be approved under the library board's delegated authority policy and reported to the municipality, which funds most of the library's capital budget. In exam terms, the municipality and the library board are both parts of the business layer, which is why the executive checks the project mandate's constraints before starting up continues.

A matching question on outputs

An original matching question on process outputs (3 marks).
ItemOptions: A Starting up a project; B Directing a project; C Initiating a project; D Managing a stage boundary; E Controlling a stage; F Closing a projectAnswer
Produces the project briefPre-project preparationA
Produces the plan for the first delivery stage near the end of initiationPlanning the next stageD
Agrees the tailoring requirements for the branch projectBuilding the foundations of the projectC

Timing the decisions

Questions about directing often turn on when a decision is made. The program below lays out Dev's branch project as a sequence of process steps and board decisions, which is a useful study aid: drawing the sequence for each running case makes 'what happens next' questions much easier.

The decision sequence for a three-stage project (illustrative).
steps = [
    ("project mandate", "business layer", None),
    ("starting up a project", "executive and project manager", None),
    ("authorize initiation", "project board", "decision"),
    ("initiating a project", "project manager", None),
    ("managing a stage boundary (plan stage 2)", "project manager", None),
    ("authorize the project and stage 2", "project board", "decision"),
    ("controlling a stage / managing product delivery", "project manager / team managers", None),
    ("managing a stage boundary (plan stage 3)", "project manager", None),
    ("authorize stage 3", "project board", "decision"),
    ("closing a project", "project manager", None),
    ("authorize project closure", "project board", "decision"),
]
for n, (step, who, kind) in enumerate(steps, 1):
    mark = "  <- board decision" if kind else ""
    print(f"{n:>2}. {step:<50} {who}{mark}")
print(f"board decisions: {sum(1 for s in steps if s[2])}")
Output
 1. project mandate                                    business layer
 2. starting up a project                              executive and project manager
 3. authorize initiation                               project board  <- board decision
 4. initiating a project                               project manager
 5. managing a stage boundary (plan stage 2)           project manager
 6. authorize the project and stage 2                  project board  <- board decision
 7. controlling a stage / managing product delivery    project manager / team managers
 8. managing a stage boundary (plan stage 3)           project manager
 9. authorize stage 3                                  project board  <- board decision
10. closing a project                                  project manager
11. authorize project closure                          project board  <- board decision
board decisions: 4

The sequence shows four board decisions for a project with an initiation stage and two delivery stages. Look at which steps belong to the project manager: preparing the next stage plan in managing a stage boundary always comes before the board's authorization of that stage.

Worked problem

What happens next?

Question: 'The branch project's executive has just authorized initiation. What should happen next?' Options: (a) Dev authorizes work packages for the storefront fit-out; (b) Dev begins initiating a project, starting by agreeing the tailoring requirements; (c) the board authorizes the project; (d) Dev prepares the project brief.

Show solution
  1. Locate: directly after authorize initiation in directing a project.
  2. Classify: process sequence.
  3. Rule: authority to initiate triggers initiating a project; the project brief was already prepared in starting up.
  4. Eliminate (a): no delivery work before the project is authorized. Eliminate (c): the project initiation documentation is not ready. Eliminate (d): already done.
  5. Choose (b).

Answer: (b). Initiation follows the authority to initiate.

The project brief and the PID

Questions often test the difference between the project brief and the project initiation documentation. The brief is a starting point: it describes the project's background, objectives, outline business case, project product description, delivery approach and the project management team, in enough detail for the board to decide whether to invest in initiation. The PID is the full basis for managing the project: it adds the management approaches, project controls, the project plan, the detailed business case and the tailoring decisions. If a question asks which product the board uses to authorize the project, it is the PID; if it asks which product supports the decision to authorize initiation, it is the brief.

Common mistakes

  • MistakeThinking the request to initiate triggers initiating a project.

    InsteadIt triggers directing a project, where the board authorizes initiation.

  • MistakeAppointing the project manager before the executive.

    InsteadThe executive is appointed first.

  • MistakeSkipping initiation on simple projects.

    InsteadInitiation can be short but is always a management stage.

  • MistakeHaving the board authorize work packages.

    InsteadWork packages are authorized by the project manager.

  • MistakeExpecting the project plan in starting up.

    InsteadThe project plan is created during initiation.

Summary and key terms

  • Starting up is triggered by the project mandate and asks whether the project is viable and worthwhile.
  • The executive is appointed first; the project brief and initiation stage plan are the main outputs.
  • Directing a project runs from the request to initiate until closure, with the board deciding by exception.
  • Initiating a project is the first management stage and produces the project initiation documentation.
  • The plan for the first delivery stage is prepared in managing a stage boundary near the end of initiation.
  • Draw the decision sequence for each scenario to answer 'what happens next' questions.
Project mandate
The trigger for starting up a project, issued by the business layer.
Project brief
A statement describing the purpose, cost, time and performance requirements and constraints, used to start initiation.
Project initiation documentation
The collection of products that defines the project and forms the basis for its management.
Authority to initiate
The board's decision that starts initiating a project.
Ad hoc direction
Board guidance given at any time in response to requests or events.
Initiation stage
The first management stage, in which the project's foundations are built.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. What triggers starting up a project?

    Show answer

    The project mandate.

  2. Which role is appointed first?

    Show answer

    The executive.

  3. Name the five board activities in directing a project.

    Show answer

    Authorize initiation, authorize the project, authorize a stage or exception plan, give ad hoc direction, authorize project closure.

  4. Who authorizes work packages?

    Show answer

    The project manager, in controlling a stage.

  5. What does initiating a project assemble?

    Show answer

    The project initiation documentation.

  6. Which process prepares the first delivery stage plan?

    Show answer

    Managing a stage boundary, near the end of initiation.

  7. Can initiation be skipped on a simple project?

    Show answer

    No; it can be short, but it is always a management stage.

  8. Why can't the board approve the project plan with the project brief?

    Show answer

    The project plan is created later, during initiation.

  9. How many board decisions are in the three-stage example?

    Show answer

    Four.

  10. What happens straight after authority to initiate?

    Show answer

    Initiating a project begins.

Lesson quiz · 5 questions

Score 60% or more to complete this lesson.

Take the quiz