PMP-121 · Lesson 2 of 12 · 26 min

Identifying and analysing stakeholders

You cannot engage stakeholders you have not found, and you cannot engage them well if you do not understand what they want and how much they can influence the project. Identification and analysis are therefore the foundation of everything else in this course. They start before the project is formally approved, when the business case and charter are drafted, and they continue until closure. This lesson covers sources and techniques for identifying stakeholders, the stakeholder register, and the main analysis models: the power/interest grid and its variants, the salience model, the stakeholder cube and simple scoring.

Where to look for stakeholders

Stakeholder identification works best as a deliberate search rather than a list written from memory. Useful sources include the business case and charter, which name sponsors, customers and objectives; organization charts, which show who owns affected processes and staff; contracts and agreements, which name suppliers, partners and their obligations; lessons learned from similar projects, which often record stakeholders that earlier teams missed; regulatory requirements, which identify authorities and the evidence they expect; and the people already identified, who can be asked "Who else should we talk to?" That last question, sometimes called snowball identification, is one of the most productive techniques available.

Workshops and brainstorming with the core team and sponsor quickly produce a first list. Interviews with experienced staff add depth. For projects with public impact, a community or geographic scan, such as a map of who lives, works or operates near a site, catches groups that office-based teams overlook. Questionnaires can reach large groups, and document analysis catches formal obligations. A good starting prompt is to walk through the project life cycle and ask who is involved, consulted, affected or able to object at each stage.

Stakeholder identification techniques. Using several together reduces blind spots.
TechniqueBest forWatch out for
Document review (charter, contracts, regulations)Formal stakeholders and obligationsMisses informal influencers
Brainstorming with the teamA quick first listGroup blind spots; dominant voices
Expert interviewsHidden or informal stakeholdersTakes time; one expert's bias
Snowball ("who else?")Networks and indirect stakeholdersCan grow without limit; needs a stopping point
Life cycle walkthroughStakeholders who appear in later phasesRequires a reasonable view of the delivery approach
Geographic or community scanProjects with physical sites or public impactNeeds local knowledge
Lessons learnedRecurring stakeholders across similar projectsOld lists may be out of date

The stakeholder register

The main output of identification is the stakeholder register, a living document that records who the stakeholders are and what the project knows about them. A register typically includes identification information (name or group, organization, role, contact details, relationship owner), assessment information (interests, expectations, requirements, influence, attitude, phase of most interest) and classification (category, priority, current and desired engagement). On agile projects the same information may be held in a lighter form, such as a stakeholder board or personas, but the purpose is identical.

Some register content is sensitive. A note that a director is hostile to the project, or that a union is planning a campaign, could damage relationships if it circulated widely. Keep sensitive assessments where only those who need them can see them, describe behaviour factually rather than with labels, and remember that privacy law may apply to personal information about individuals.

Extract from a stakeholder register for a hospital scheduling project. Attitudes are recorded factually and the full register is access-controlled.
StakeholderRoleMain interestsPowerInterestAttitudeOwner
Chief nursing officerHead of nursing practicePatient safety, workload, staffing rulesHighMediumCautiousSponsor
Unit managers (12)Build and approve rostersTime to build schedules, fairnessMediumHighMixedProject manager
Nurses' unionRepresents nursing staffScheduling rules in the collective agreementHighHighConcernedLabour relations lead
IT securityApproves new systemsAccess controls, data protectionHighLowNeutralTech lead
Patients' councilPatient voiceContinuity of careLowMediumSupportiveProject manager

In Canada, personal information collected about individuals in a commercial context is governed by the Personal Information Protection and Electronic Documents Act (PIPEDA) or by substantially similar provincial laws in Quebec, Alberta and British Columbia. Public bodies follow federal or provincial public-sector privacy laws. A register that records opinions about named people is personal information, so collect only what the project needs, restrict access and retain it no longer than necessary.

The power/interest grid

The best-known analysis tool places stakeholders on a two-by-two grid by their power (ability to affect the project) and their interest (how much they care about it). Each quadrant suggests a default engagement strategy. Variants use influence instead of interest (power/influence grid), or impact (the stakeholder's ability to cause changes to planning or execution) in place of power.

A two-by-two grid with interest on the horizontal axis and power on the vertical axis. The top right quadrant reads manage closely, top left keep satisfied, bottom right keep informed and bottom left monitor. Dots representing stakeholders are scattered across the quadrants.
The power/interest grid and the default strategy for each quadrant.
Default strategies by quadrant. These are starting points; individual circumstances decide the final approach.
QuadrantDefault strategyTypical stakeholders
High power, high interestManage closely: involve in decisions, consult often, build partnershipSponsor, key customer, powerful regulator actively watching
High power, low interestKeep satisfied: meet their needs efficiently, avoid overloading them, watch for rising interestSenior executives outside the sponsor line, some regulators, legal
Low power, high interestKeep informed: regular, adequate information; use their knowledge and energyEnd users, community members, junior staff
Low power, low interestMonitor: light-touch information, check periodicallyPeripheral departments, the general public

The grid has limits. It is a snapshot, while power and interest change: a quiet executive becomes highly interested once the budget is threatened, and an individual end user with little power can gain a great deal by organizing colleagues or going to the media. The grid also ignores attitude: a high-power, high-interest stakeholder who is a champion needs very different handling from one who is opposed. Many teams therefore colour or label the dots by attitude, or add arrows to show where they want each stakeholder to move.

The salience model

The salience model, developed by Mitchell, Agle and Wood in 1997, classifies stakeholders by three attributes: power (the ability to impose their will), legitimacy (the appropriateness of their involvement, through contract, law, ownership or moral claim) and urgency (the time sensitivity and criticality of their claims). Stakeholders with all three attributes are definitive and demand immediate attention. Those with two attributes are expectant; those with one are latent.

Three overlapping circles labelled power, legitimacy and urgency. The region where all three overlap is labelled definitive. Regions with two overlapping circles are labelled dominant, dangerous and dependent, and regions of a single circle are labelled dormant, discretionary and demanding.
The salience model. Salience rises with the number of attributes a stakeholder holds.
The seven stakeholder classes of the salience model.
ClassAttributesExample
DormantPower onlyA senior executive with authority who has no current claim on the project
DiscretionaryLegitimacy onlyA charity the company supports, with no power or urgent claim
DemandingUrgency onlyA persistent complainant with no authority or legitimate claim
DominantPower and legitimacyThe board of directors
DangerousPower and urgencyA group threatening disruption without a legitimate claim
DependentLegitimacy and urgencyResidents affected by a spill who rely on regulators to act for them
DefinitiveAll threeA regulator issuing a stop-work order

The salience model is useful for large, complex stakeholder communities, especially where some groups have urgent but contested claims. It reminds project managers that legitimacy and urgency matter alongside power, and that stakeholders move between classes: a dependent group of residents becomes definitive if they win the support of a powerful authority.

The stakeholder cube and other variants

Some guidance describes a stakeholder cube, which adds a third dimension to the grid, typically attitude (supportive or resistant) or activity (active or passive), giving eight segments. Another variant, the directions of influence, classifies stakeholders as upward (senior management, the sponsor), downward (the team and specialists), outward (customers, suppliers, regulators, the public) and sideward (peers such as other project managers competing for shared resources). The directions model is a useful check that communication is planned in every direction, not just upward to the sponsor.

A cube divided into eight smaller blocks. Its three edges are labelled power, interest and attitude, each running from low to high or from resistant to supportive. One corner block is highlighted and labelled high power, high interest, resistant: top priority.
A stakeholder cube adds attitude to power and interest.

Simple scoring

When a project has dozens of stakeholders, a simple weighted score helps rank them. Each stakeholder is rated on a few criteria, such as power, interest and urgency, the ratings are weighted and summed, and the result is combined with attitude to highlight the stakeholders who are both important and not yet supportive. Scores are a conversation aid, not a precise measure: they help a team agree priorities and make assumptions visible.

# Prioritize stakeholders with a simple weighted score (illustrative weights)
stakeholders = {
    # name: (power, interest, urgency, attitude) each scored 1-5; attitude 1 = opposed, 5 = champion
    "Sponsor (VP Operations)": (5, 5, 3, 5),
    "Chief nursing officer":   (5, 3, 4, 2),
    "Unit managers":           (3, 5, 4, 3),
    "Nurses' union":           (4, 4, 5, 1),
    "IT security":             (4, 2, 2, 3),
    "Patients' council":       (2, 4, 2, 4),
}
w_power, w_interest, w_urgency = 0.5, 0.3, 0.2

rows = []
for name, (p, i, u, a) in stakeholders.items():
    score = w_power * p + w_interest * i + w_urgency * u
    risk = score * (6 - a)          # higher when important AND unsupportive
    rows.append((name, score, a, risk))

print(f"{'Stakeholder':26}{'Priority':>9}{'Attitude':>9}{'Risk':>7}")
for name, score, a, risk in sorted(rows, key=lambda r: -r[3]):
    print(f"{name:26}{score:9.1f}{a:9d}{risk:7.1f}")
Output
Stakeholder                Priority Attitude   Risk
Nurses' union                   4.2        1   21.0
Chief nursing officer           4.2        2   16.8
Unit managers                   3.8        3   11.4
IT security                     3.0        3    9.0
Patients' council               2.6        4    5.2
Sponsor (VP Operations)         4.6        5    4.6

In this illustrative output, the union and the chief nursing officer rise to the top of the risk ranking because they combine high priority with low support. The sponsor has the highest priority score but low risk, because she is already a champion. That combination tells the project manager where engagement effort is most needed now.

Worked problem

Placing stakeholders on the grid

A municipal transit project will close a downtown station for 18 months to rebuild it. Place these stakeholders on the power/interest grid and give a default strategy: (a) the transit authority board; (b) daily commuters who use the station; (c) the provincial or state transportation ministry that provides half the funding but is not involved day to day; (d) a business improvement association representing nearby shops; (e) the city's parks department, whose small park is used as a laydown area for two months.

Show solution
  1. (a) Board: high power, high interest. Manage closely.
  2. (b) Commuters: low individual power, high interest. Keep informed, using channels they already use; watch for collective influence.
  3. (c) Ministry: high power, low current interest. Keep satisfied with concise reports on funding milestones; watch for rising interest if costs grow.
  4. (d) Business association: medium-to-high power through political access, high interest. Treat as manage closely during planning and construction.
  5. (e) Parks department: medium power over its land, low interest beyond the laydown period. Keep satisfied through clear agreements and site restoration.

Answer: The board and business association need close management; the ministry needs to be kept satisfied; commuters need to be kept well informed; the parks department needs a clear agreement. Positions should be reviewed when construction begins.

Making analysis useful

Analysis is only worth doing if it changes what the team does. For each high-priority stakeholder, the analysis should lead to concrete answers: who owns the relationship, what the stakeholder needs to know or decide, how and how often they will be engaged, and what would move them toward greater support. Those answers feed the stakeholder engagement plan in the next lesson and the communications management plan in lesson 6.

Common mistakes

  • MistakeWriting the stakeholder list from memory in a single meeting.

    InsteadUse several techniques, including documents, interviews and asking stakeholders who else should be involved.

  • MistakeTreating the power/interest grid as permanent.

    InsteadRevisit positions at each phase and after significant events, and show attitude alongside power and interest.

  • MistakeWriting loaded labels such as "difficult" in a widely shared register.

    InsteadRecord behaviour and interests factually and restrict access to sensitive assessments.

  • MistakeIgnoring low-power stakeholders entirely.

    InsteadKeep them informed and monitor them; individuals can gain power by organizing or going public.

  • MistakeTreating scores as precise measurements.

    InsteadUse scores to start a discussion and make assumptions visible.

Summary and key terms

  • Identify stakeholders using several techniques: documents, workshops, interviews, snowballing, life cycle walkthroughs and community scans.
  • The stakeholder register records identification, assessment and classification information and is updated throughout the project.
  • The power/interest grid suggests four default strategies: manage closely, keep satisfied, keep informed and monitor.
  • The salience model classifies stakeholders by power, legitimacy and urgency; definitive stakeholders hold all three.
  • The stakeholder cube adds attitude or activity; the directions of influence check upward, downward, outward and sideward communication.
  • Simple weighted scores help rank many stakeholders, especially when combined with attitude.
  • Analysis must lead to concrete engagement decisions and owners.
Stakeholder register
A project document recording stakeholders' identification, assessment and classification information.
Power/interest grid
A two-by-two model that classifies stakeholders by their power and interest to suggest an engagement strategy.
Salience model
A model that classifies stakeholders by power, legitimacy and urgency.
Legitimacy
The appropriateness of a stakeholder's involvement, based on contract, law, ownership or moral claim.
Urgency
The time sensitivity and criticality of a stakeholder's claims.
Definitive stakeholder
In the salience model, a stakeholder with power, legitimacy and urgency.
Stakeholder cube
A three-dimensional extension of the grid, adding attitude or activity.
Directions of influence
A classification of stakeholders as upward, downward, outward or sideward.
Snowball identification
Asking identified stakeholders who else should be involved.
Attitude
A stakeholder's current stance toward the project, from opposed to champion.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. Name three documents that help identify stakeholders.

    Show answer

    For example, the business case, the project charter and contracts.

  2. What is the default strategy for high-power, low-interest stakeholders?

    Show answer

    Keep satisfied.

  3. What three attributes does the salience model use?

    Show answer

    Power, legitimacy and urgency.

  4. A group has an urgent and legitimate claim but no power. Which salience class?

    Show answer

    Dependent.

  5. What is one limitation of the power/interest grid?

    Show answer

    It is a snapshot and ignores attitude unless added.

  6. What does "sideward" mean in the directions of influence?

    Show answer

    Peers, such as other project managers competing for shared resources.

  7. Why should parts of the stakeholder register be access-controlled?

    Show answer

    It may contain sensitive assessments and personal information that could damage relationships or breach privacy rules.

  8. What question drives snowball identification?

    Show answer

    "Who else should we talk to?"

  9. In the scoring example, why did the sponsor have low risk despite high priority?

    Show answer

    She is already a champion, so the gap between current and desired support is small.

  10. What should analysis produce for each high-priority stakeholder?

    Show answer

    A relationship owner, information and decision needs, engagement method and frequency, and actions to build support.