MBA-511 · Lesson 6 of 12 · 19 min

Estimating project cash flows

When the cohort reconvenes, Dr. Varga puts the press-line figures from lesson 5 back on the screen and admits that he simplified them. A real proposal does not arrive with a tidy row of after-tax cash flows. It arrives with an engineering estimate of the equipment cost, a production manager's guess at the labor saved, a purchasing estimate of scrap reduction, and a spreadsheet from the accounting team showing the project's effect on reported earnings. Turning those into the cash flows that belong in an NPV calculation is where most of the judgment in capital budgeting lies, and where most of the errors are made.

The incremental principle

The cash flows that matter are incremental: the difference between the firm's cash flows with the project and without it. Everything follows from that principle. A cost that will be incurred whether or not the project goes ahead is irrelevant. A benefit that the firm would enjoy anyway is irrelevant. What counts is how the decision changes the firm's future cash.

Four kinds of item commonly trip up analysts. Sunk costs, money already spent, should be ignored; Northfield's 400,000 dollars of engineering studies for the press line are gone whatever the board decides. Opportunity costs, the value of resources the project uses that could be used elsewhere, should be included even when no cash changes hands; if the press line occupies floor space that could otherwise be leased to a neighboring firm for 250,000 dollars a year, that forgone rent is a cost of the project. Side effects on the firm's other products count: a new product that takes sales from an existing one, called cannibalization, reduces the incremental benefit, while one that helps sell other products adds to it. And allocated overhead counts only to the extent that it actually changes; if head office costs are spread across projects by a formula but would not rise, they are not incremental.

Which items belong in the incremental cash flows of the press line.
ItemInclude?Reason
Engineering study already paidNoSunk cost
Floor space that could be leased outYesOpportunity cost
Lost sales of the old bracket lineYes, as a reductionCannibalization
Share of head office costs, unchanged in totalNoNot incremental
Extra inventory of spare partsYesInvestment in working capital
Interest on the loan to buy the pressNoFinancing is reflected in the discount rate

Cash flow, not profit

The NPV calculation uses after-tax cash flows, not accounting profit. Three adjustments turn one into the other. First, depreciation is not a cash outflow; the cash was spent when the equipment was bought. But depreciation for tax purposes reduces the taxes the firm pays, and that tax saving, the depreciation tax shield, is a real cash benefit. Second, investment in working capital, such as inventory, receivables and spare parts, ties up cash at the start and releases it when the project ends. Third, interest is excluded from project cash flows, because the cost of financing is captured in the discount rate; including it would count the cost of debt twice.

\[CF_t = (R_t - C_t)(1-\tau) + \tau D_t - \text{CapEx}_t - \Delta NWC_t\]

In this formula, revenue minus cash operating costs is taxed at the tax rate, the depreciation deduction saves tax equal to the tax rate times the deduction, and capital spending and increases in working capital are subtracted. An equivalent form starts with operating profit after tax and adds back depreciation, the same structure as free cash flow to the firm in lesson 4. Project analysis and company valuation use the same building blocks.

Depreciation for tax

In the United States, tax depreciation uses the Modified Accelerated Cost Recovery System, MACRS. Each asset is assigned a recovery period, such as five years for computers and vehicles or seven years for most machinery, and the IRS publishes the percentage of the cost that may be deducted each year, using a half-year convention so that the first and last years get half a year's deduction. On top of MACRS, bonus depreciation lets firms deduct a large part of the cost of qualifying property immediately. The Tax Cuts and Jobs Act of 2017 allowed 100 percent bonus depreciation and scheduled it to phase down from 2023; the 2025 budget reconciliation law, the One Big Beautiful Bill Act, made 100 percent bonus depreciation permanent for qualifying property acquired after January 19, 2025. Firms can elect out and use ordinary MACRS, for example when they expect higher tax rates later or have losses that make deductions less valuable now.

The value of faster depreciation comes from timing. Over the life of an asset, total deductions equal its cost whether they are taken over seven years or in the first year. But a dollar of tax saved in the first year is worth more than a dollar saved in the eighth. Bonus depreciation therefore does not reduce the total tax a firm pays on a project so much as defer it, and the value of the deferral rises with the discount rate.

\[PV_{\text{tax shield}} = \sum_{t=1}^{T} \frac{\tau\,D_t}{(1+r)^t}\]
Bar chart of yearly tax depreciation on a 14 million dollar machine over eight years under 7-year MACRS and under 100 percent bonus depreciation; bonus depreciation puts the full cost in year 1
Tax depreciation on the press line under 7-year MACRS and under 100 percent bonus depreciation. Bonus depreciation moves all deductions to the first year.

Northfield's press line in full

The press line costs 14 million dollars. Engineering expects it to save enough in labor and scrap to add 3.4 million dollars a year after tax, which at a combined federal and state rate of 25 percent, the federal rate of 21 percent plus a typical state tax net of its federal deduction, is about 4.53 million before tax. It requires 0.8 million dollars of spare parts and tooling, recovered at the end of eight years, when the line can be sold for about 1.5 million. The line is seven-year MACRS property, and because it is acquired well after January 19, 2025, it qualifies for 100 percent bonus depreciation unless Northfield elects out.

# Northfield press line: incremental after-tax cash flows with MACRS (millions)
cost, life, salvage = 14.0, 8, 1.5
savings, tax, r = 3.4 / (1 - 0.25), 0.25, 0.09     # pre-tax savings giving 3.4 after tax
nwc = 0.8                                          # spare parts and tooling, recovered at the end
macrs7 = [0.1429, 0.2449, 0.1749, 0.1249, 0.0893, 0.0892, 0.0893, 0.0446]

def project(bonus):
    dep = [cost] + [0.0] * (life - 1) if bonus else [cost * p for p in macrs7]
    flows = [-cost - nwc]
    for t in range(1, life + 1):
        cf = savings * (1 - tax) + dep[t - 1] * tax
        if t == life:
            book = cost - sum(dep)
            cf += salvage + nwc - (salvage - book) * tax   # tax on gain over remaining basis
        flows.append(cf)
    return sum(f / (1 + r) ** t for t, f in enumerate(flows)), dep

for label, bonus in [("7-year MACRS", False), ("100% bonus", True)]:
    v, dep = project(bonus)
    print(f"{label:14s} first-year deduction {dep[0]:5.2f}  NPV {v:5.2f}")
Output
7-year MACRS   first-year deduction  2.00  NPV  7.59
100% bonus     first-year deduction 14.00  NPV  8.20

Two lessons emerge. First, once the tax shield, working capital and salvage value are included, the NPV rises to about 7.6 million dollars, well above the simple figure of 4.8 million in lesson 5, which treated 3.4 million a year as the whole after-tax cash flow and left out the tax value of depreciation. Second, bonus depreciation adds about 0.6 million dollars of value by moving all the deductions into the first year. For a capital-intensive firm making many such investments, that changes which projects clear the hurdle, which is exactly what the policy intends.

Working capital and terminal values

Working capital is easy to forget and can change a decision. A new store needs inventory before it makes its first sale; a new product line needs receivables because customers pay on credit. These investments are cash outflows at the start and, if the project ends, cash inflows when the inventory is sold off and receivables are collected. Grace's estimate for a new Fairway store includes 1.1 million dollars of inventory, partly offset by 0.7 million of supplier credit, so the net working capital investment is 0.4 million. Cedarline, the cohort's case company, shows what happens when working capital is ignored: its inventory grew from 58 to 128 million dollars over four years, absorbing cash that its reported profits never revealed.

At the end of the forecast, a project may have a salvage value, or it may continue indefinitely, in which case a terminal value is needed, usually a growing perpetuity of the final year's cash flow. When an asset is sold, the tax consequences depend on how its sale price compares with its remaining tax value: a sale above that value creates a taxable recapture or gain, a sale below it a deductible loss. These end-of-life effects are small for long projects at high discount rates but can matter for short ones.

Inflation, scenarios and forecasting bias

Forecasts should be consistent about inflation. If the discount rate is nominal, as rates observed in markets are, the cash flows should include expected inflation in prices, wages and materials. A common mistake is to hold revenues flat in today's dollars and discount at a nominal rate, which understates the NPV of every long project. Tax depreciation, by contrast, is fixed in nominal terms at the original cost, so its real value falls with inflation.

Forecasts are also systematically optimistic. Studies of large capital projects, notably by Bent Flyvbjerg, find that cost overruns and benefit shortfalls are the norm, not the exception, and that the cause is less often bad luck than a combination of optimism and strategic misrepresentation by project sponsors. Dr. Varga recommends three defenses. Reference-class forecasting compares a project's estimates with the actual outcomes of similar past projects. Scenario analysis builds a pessimistic, base and optimistic case with internally consistent assumptions, rather than flexing one variable at a time. And break-even analysis asks how far a key assumption, such as annual savings, could fall before the NPV reaches zero; for the press line, after-tax savings could fall by about two fifths before the project destroys value.

Worked problem

A new Fairway store

Grace estimates that a new store will cost 9 million dollars to fit out and will generate pre-tax operating cash flow of 1.6 million dollars a year for 15 years. Net working capital of 0.4 million is needed at the start and recovered at the end. Ignore depreciation for a moment and use a tax rate of 25 percent and a cost of capital of 8 percent. What is the NPV before the depreciation tax shield, and what does the answer tell Grace?

Show solution
  1. After-tax operating cash flow: 1.6 times 0.75 = 1.2 million dollars a year.
  2. PV of 15 years of 1.2 million at 8 percent: annuity factor 8.559, so 10.27 million.
  3. Initial outlay: 9.0 plus 0.4 = 9.4 million. PV of working capital recovered in year 15: 0.4 / 3.172 = 0.13 million.
  4. NPV before the tax shield = 10.27 + 0.13 minus 9.4 = about 1.0 million dollars.

Answer: The store has an NPV of about 1.0 million dollars before counting the tax value of depreciation on the fit-out, which would add more. It is a modest positive. Because store openings across the industry often fall short of their forecasts, Grace should test how far first-year sales could miss before the NPV turns negative.

Common mistakes

  • MistakeMoney already spent on a feasibility study is a cost of the project.

    InsteadIt is sunk; only future cash flows that change with the decision count.

  • MistakeDepreciation is a cash outflow.

    InsteadDepreciation is not cash, but its tax deduction saves cash.

  • MistakeInterest on the loan should be subtracted from project cash flows.

    InsteadFinancing costs are captured in the discount rate.

  • MistakeWorking capital can be ignored because it is recovered at the end.

    InsteadTying up cash for years has a real cost in present value terms.

Summary and key terms

  • Project cash flows are incremental: the difference between the firm's cash flows with and without the project.
  • Ignore sunk costs; include opportunity costs, cannibalization and side effects; exclude unchanged overhead and interest.
  • After-tax cash flow equals operating cash flow after tax plus the depreciation tax shield, minus capital spending and working capital investment.
  • Accelerated tax depreciation adds value by moving tax savings closer to the present.
  • Use nominal flows with nominal rates, build consistent scenarios and check forecasts against past projects.
Incremental cash flow
The change in a firm's cash flow that results from a decision.
Sunk cost
A cost already incurred that cannot be recovered and should not affect a decision.
Opportunity cost
The value of the best alternative use of a resource.
Cannibalization
The loss of sales of existing products caused by a new product.
Depreciation tax shield
The tax saved because depreciation is deductible, equal to the tax rate times the deduction.
Accelerated depreciation
Tax depreciation that allows larger deductions in an asset's early years than in its later years.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. A project uses a warehouse that the firm owns and could lease out for 300,000 dollars a year. Should that amount be in the project analysis?

    Show answer

    Yes. The forgone rent is an opportunity cost of using the warehouse for the project.

  2. A firm with a 25 percent tax rate claims 2 million dollars of tax depreciation in a year. What is the tax shield?

    Show answer

    0.25 times 2 million = 500,000 dollars of tax saved.

  3. A new product will sell 10 million dollars a year but will reduce sales of an existing product by 3 million. What revenue should go in the analysis?

    Show answer

    The incremental revenue of 7 million dollars, along with the incremental costs.

  4. Why does faster tax depreciation raise a project's NPV if total deductions are unchanged?

    Show answer

    The tax savings arrive sooner, so their present value is higher.

Lesson quiz · 5 questions

Score 60% or more to complete this lesson.

Take the quiz