Concrete takeoff: footings, walls, slabs, reinforcing and formwork

Cast-in-place concrete is the backbone of most buildings' substructure and often their structure too, and it is the trade general contractors most often self-perform. A concrete takeoff produces four related quantities for each element: the volume of concrete, the contact area of formwork, the mass or weight of reinforcing steel, and the area of finishing. Each is bought, built and priced differently, but all come from the same dimensions. This lesson takes off the common elements of a building foundation and slab and shows how the quantities connect.

Organizing a concrete takeoff

Concrete work is taken off element by element, following the structural drawings: footings, piers and pile caps, foundation walls, grade beams, columns, slabs on grade, suspended slabs, beams, stairs and miscellaneous items such as equipment pads, curbs and sumps. Each element is listed separately because each has its own formwork method, placing method and productivity, and therefore its own unit price. A wall poured from a pump in large lifts costs much less per cubic meter or cubic yard to place than a small equipment pad poured by hand.

  • Concrete volume: the net volume in place, measured from dimensions, with no deduction for reinforcing steel and usually none for small embedded items or openings below a stated size.
  • Formwork: the contact area of concrete surfaces that need forms, by element type, measured in square meters or square feet of contact area (SFCA in US practice).
  • Reinforcing: bar lengths by size, converted to mass or weight, with laps, hooks and supports, often taken off from the structural drawings or later from the rebar fabricator's shop drawings.
  • Finishing and curing: the area of exposed horizontal surfaces to be finished, such as slab tops and wall tops, and the area to be cured or protected.
  • Accessories: anchor bolts, embedded plates, waterstops, expansion joint filler, vapor retarder under slabs, form ties and chamfer strips.

Strip footings and walls

Strip footings and foundation walls are measured along their centerline, which avoids double-counting at corners. For a rectangular building with walls of uniform section, the centerline length is the perimeter measured to the middle of the wall. Exterior corners add a little and interior corners subtract a little relative to outside dimensions, and the centerline method balances them automatically. Footings under walls of a different width have their own centerline.

Formwork for footings is usually the two side faces, since the bottom is cast against soil; formwork for walls is both faces over the full height, plus bulkheads at pour joints and blockouts for openings. Corners, pilasters and steps in the wall add labor and are often counted separately, because they slow the forming crew far more than their area suggests.

A section through a strip footing and foundation wall. The footing is 24 in wide and 10 in deep; the wall above is 8 in thick and 8 ft high. Vertical #5 bars at 16 in and horizontal #4 bars at 12 in are shown in the wall, with dowels into the footing. Formwork faces are highlighted on both sides of the wall and the footing sides.
One section, four quantities: concrete volume, formwork contact area, reinforcing and finishing all come from the same dimensions.

Worked problem

Footing and wall concrete and formwork

A rectangular foundation has a centerline perimeter of 316 ft. Footings are 24 in wide and 10 in deep; walls are 8 in thick and 8 ft high. Calculate the concrete volumes in cubic yards with 3 % waste and the formwork contact areas.

Show solution
  1. Footing concrete: 316 × 2.0 × (10 ÷ 12) = 526.7 ft³ = 19.51 yd³; with 3 % waste, 20.09 yd³.
  2. Wall concrete: 316 × (8 ÷ 12) × 8 = 1,685.3 ft³ = 62.42 yd³; with 3 % waste, 64.29 yd³.
  3. Footing forms (two sides): 2 × (10 ÷ 12) × 316 = 526.7 SFCA.
  4. Wall forms (two faces): 2 × 8 × 316 = 5,056 SFCA, plus bulkheads and corners counted separately.

Answer: About 20.1 yd³ and 64.3 yd³ of concrete to order, 527 SFCA of footing forms and 5,056 SFCA of wall forms.

Reinforcing steel

Reinforcing steel is bought and priced by mass or weight, but taken off by counting bars and measuring their lengths. For each bar mark, the estimator calculates the number of bars from the spacing and the length of the element, the length of each bar including hooks and laps, and the total length, then multiplies by the mass or weight per unit length for the bar size.

\[\text{Number of bars} = \dfrac{\text{Length of element}}{\text{Spacing}} + 1\]
US inch-pound reinforcing bars to ASTM A615 and A706.
Bar sizeNominal diameterWeight per foot
#30.375 in0.376 lb/ft
#40.500 in0.668 lb/ft
#50.625 in1.043 lb/ft
#60.750 in1.502 lb/ft
#81.000 in2.670 lb/ft

Laps are needed where bars are spliced because they are longer than the stock lengths delivered, commonly 12 m or 18 m in Canada and 20, 40 or 60 ft in the United States. Lap lengths are shown on the drawings or in the general notes, often as a multiple of bar diameter. Dowels from footings into walls, corner bars and bars around openings are counted separately. Supports such as chairs and bolsters, tie wire and a small waste allowance are added in pricing.

Worked problem

Reinforcing a foundation wall

The 316 ft wall from the previous example has vertical #5 bars at 16 in, each 9.25 ft long including the lap with the footing dowel, plus 4 extra bars at corners. Horizontal #4 bars are at 12 in vertically, in 40 ft stock lengths with 2 ft laps. Calculate the reinforcing weight.

Show solution
  1. Vertical bars: 316 ÷ 1.333 = 237, plus 4 corner bars = 241 bars × 9.25 ft = 2,229 ft.
  2. Vertical weight: 2,229 × 1.043 = 2,325 lb.
  3. Horizontal lines: 8 ÷ 1 + 1 = 9 lines × 316 ft = 2,844 ft.
  4. Laps: each 316 ft line needs about 316 ÷ 40 = 8 laps × 2 ft = 16 ft; 9 lines × 16 = 144 ft. Total 2,988 ft.
  5. Horizontal weight: 2,988 × 0.668 = 1,996 lb. Total: 2,325 + 1,996 = 4,321 lb, about 2.16 tons before waste and supports.

Answer: About 4,320 lb, or 2.16 tons, of reinforcing in the wall.

A ratio check catches gross errors: divide the reinforcing mass by the concrete volume. Here 1,776 kg ÷ 46.08 m³ is about 39 kg/m³, or in imperial terms 4,321 lb ÷ 62.4 yd³ is about 69 lb/yd³, which is reasonable for a lightly reinforced foundation wall. Heavily reinforced columns, transfer beams and shear walls can exceed 150 kg/m³ or 250 lb/yd³. A ratio far outside the expected range suggests a missed bar mark or a units error.

Slabs on grade and suspended slabs

Slabs on grade are measured by area, with volume calculated from the specified thickness. Thickened edges, thickened slabs under walls, drop panels at columns and depressions for finishes or showers add concrete and must be taken off separately. The estimator also takes off the granular base and compaction, the vapor retarder with laps, insulation where specified, reinforcing mesh or bars, edge forms, construction and control joints, and finishing and curing by area.

Concrete placed on grade usually needs a larger waste allowance than concrete in forms, because the subgrade is never perfectly level: a slab specified at 125 mm or 5 in often averages several millimeters or a fraction of an inch thicker. Many estimators allow 4 to 7 % on slabs on grade against 2 to 3 % in formed elements.

Worked problem

Slab on grade quantities

A slab on grade is 80 ft × 120 ft and 5 in thick, with a 4 % allowance for subgrade variation and waste, ordered in 0.5 yd³ increments. Calculate the concrete to order, the finishing area and the vapor retarder area with 10 % added for laps and turn-ups.

Show solution
  1. Area: 80 × 120 = 9,600 ft².
  2. Net volume: 9,600 × (5 ÷ 12) = 4,000 ft³ = 148.1 yd³; with 4 %, 154.1 yd³, ordered as 154.5 yd³.
  3. Finishing area: 9,600 ft².
  4. Vapor retarder: 9,600 × 1.10 = 10,560 ft².

Answer: 154.5 yd³ of concrete, 9,600 ft² of finishing and about 10,560 ft² of vapor retarder.

Suspended slabs add formwork for the soffit, measured by area, and shoring and reshoring, which are usually priced per unit of slab area with allowances for the number of floors of reshores required. Beams and drop panels add soffit and side forms. Openings larger than the stated deduction size are deducted from concrete and soffit forms but add edge forms.

Columns, stairs and miscellaneous concrete

Columns are counted by type and height, with volume from the section and height and forms from the perimeter and height. Round columns are formed with fiber or steel tubes priced per unit length by diameter. Stairs are measured by volume for concrete but priced largely on labor, because forming treads and risers is slow; many estimators price them per riser or per flight. Equipment pads, housekeeping pads, curbs, sumps and trenches are small in volume but labor-intensive, and they are often omitted from takeoff because they appear only on mechanical or electrical drawings.

How common concrete elements are measured and priced.
ElementConcrete measured byFormwork measured byPricing notes
Strip footingsVolume from centerline length × sectionTwo side facesLow forming cost, often placed by chute
WallsVolume from centerline length × sectionBoth faces, plus bulkheads, corners, blockoutsPumped; tie spacing and height affect cost
ColumnsVolume by type × heightPerimeter × height, or tube length for round columnsLabor intensive per cubic unit
Slab on gradeArea × thickness, plus thickeningsEdge forms by lengthFinishing and curing by area
Suspended slabArea × thickness, plus beams and dropsSoffit area, edges, shoringReshoring by floor
StairsVolumeTreads, risers and soffitOften priced per riser or per flight

Pricing concrete work

Each concrete element's unit price combines several cost items, built up from the quantities above.

  • Concrete material: purchase quantity × delivered price, plus winter, short-load and admixture charges, from Lesson 6.
  • Placing: labor and placing equipment such as pump or crane, priced per cubic unit by element and pour size.
  • Formwork: labor per unit of contact area from Lesson 4, plus form materials or rental, with reuse factors for systems used several times.
  • Reinforcing: usually a subcontract or supply-and-place price per metric ton or ton, from the fabricator and placer.
  • Finishing, curing and protection: labor and materials per unit area, plus winter heating and hoarding where needed.
  • Testing and inspection: cylinders and field tests, if the contract assigns them to the contractor.

Formwork reuse deserves attention. Prefabricated wall forms or panels used ten times on a repetitive building cost far less per use than plywood forms built for a single pour. The estimator plans the number of form sets, the pour sequence and the number of uses, and spreads the form material cost over the total contact area formed.

Common mistakes

  • MistakeMeasuring walls and footings on outside dimensions and doubling corners.

    InsteadUse the centerline length so corners are counted once.

  • MistakeForgetting dowels, corner bars and laps in reinforcing.

    InsteadCount each bar mark, add laps at stock lengths, dowels and corner bars, then check kg/m³ or lb/yd³.

  • MistakeUsing the same waste allowance for slabs on grade and formed elements.

    InsteadAllow more on slabs on grade for subgrade variation.

  • MistakeMissing pads, curbs and sumps on mechanical and electrical drawings.

    InsteadReview all disciplines' drawings for miscellaneous concrete.

  • MistakePricing all concrete at one placing rate.

    InsteadPrice each element separately; small pours and stairs cost far more per cubic unit to place.

Summary and key terms

  • Each concrete element yields concrete volume, formwork contact area, reinforcing mass or weight and finishing area.
  • Footings and walls are measured on the centerline length.
  • Reinforcing is counted bar by bar, with laps at stock lengths, then converted to mass or weight.
  • A reinforcing ratio per cubic unit of concrete is a quick check for errors.
  • Slabs on grade need thickenings, base, vapor retarder, joints and finishing taken off, and a larger waste allowance.
  • Columns, stairs and miscellaneous items are labor intensive and easy to miss.
  • Unit prices combine material, placing, forming, reinforcing, finishing, curing and testing.
Centerline length
The length of a wall or footing measured along its middle, used for volume and forms.
Contact area
The area of concrete in contact with formwork.
SFCA
Square feet of contact area, the US unit for formwork.
Lap splice
An overlap of two reinforcing bars to transfer force between them.
Stock length
The standard length in which reinforcing bars are supplied.
Dowel
A short bar extending from one pour into the next, such as from footing to wall.
Slab on grade
A concrete slab supported directly on the ground.
Thickened edge
A deeper strip of slab at its perimeter or under walls.
Reshoring
Temporary supports placed under a slab after the original shores are removed.
Form reuse
Using the same form panels for several pours to reduce cost per use.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. Why are walls measured on the centerline?

    Show answer

    So corners are counted once and outside and inside corner errors cancel.

  2. A footing is 150 ft long, 2 ft wide and 1 ft deep. What is its volume in yd³?

    Show answer

    300 ft³ = 11.1 yd³.

  3. A 100 ft wall 10 ft high needs forms on both faces. What is the contact area?

    Show answer

    2,000 SFCA.

  4. How many bars at 12 in spacing are needed along 20 ft?

    Show answer

    20 ÷ 1 + 1 = 21.

  5. What is the weight of 100 ft of #5 bar?

    Show answer

    104.3 lb.

  6. Why add a larger waste allowance on slabs on grade?

    Show answer

    Subgrade variation makes the average thickness greater than specified.

  7. What does a reinforcing ratio check reveal?

    Show answer

    Missed bar marks or units errors when the ratio is outside the expected range.

  8. Name three accessories in a concrete takeoff.

    Show answer

    Any three of: anchor bolts, embedded plates, waterstops, joint filler, vapor retarder, form ties, chamfer.

  9. Why are stairs often priced per riser?

    Show answer

    Their cost is dominated by forming labor, not concrete volume.

  10. How does form reuse affect cost?

    Show answer

    Form material is spread over more uses, lowering cost per unit of contact area.

Lesson quiz · 5 questions