PET-370 · Lesson 12 of 12 · 19 min

Development plan and economics: capstone

Ethan's year in the thermal group ends with the assignment Mei Lin promised at the start: a development plan for the north block at Tamarisk Hill. The block holds heavy oil that the original flood never reached, and the board wants to know whether a 10,000 bbl/d expansion with new patterns and steam generators is worth building. 'Pull together everything you have learned,' Mei says. 'Reservoir, wells, steam, water, carbon, permitting and money. Paul, Lena and Tom will review it. Then the board decides.'

This capstone lesson walks through the structure of a thermal development plan: the resource and process choice, the development concept, the production and steam forecast, the facility and water plan, the environmental and regulatory case, the cost estimate and the economics. It ends with the questions reviewers ask and the ways a plan can be made more robust.

Step 1: the resource

Ethan starts with the geology from lesson 2. Grace Nakoochee's mapping shows a stacked set of Kern River Formation sands in the north block, with about 60 ft of net pay in the main sand at oil saturations of 0.55 to 0.65, separated from a shallower sand by a silty interval that should act as a baffle. The oil is about 13 °API with a viscosity of about 4,000 cP at reservoir temperature. The block is shallow, under 1,000 ft, so the operating pressure must stay well below the fracture pressure. Using the volumetric method from lesson 1, the block holds about 170 million barrels of oil in place.

Step 2: the process and concept

The choice of process follows from the reservoir. The oil is mobile when hot, the sand is thick enough for efficient steam and the field already has a proven steamflood next door, so a continuous steamflood with an initial cycle of steam on each producer is the base case. Ethan considers SAGD-style horizontal wells near the base of the sand as an option, and a solar or cogeneration supply for part of the steam to cut fuel and carbon costs. In situ combustion is ruled out by the shallow depth and nearby surface operations.

The development concept is about 120 inverted seven-spot patterns of about 2.5 acres, drilled in three phases from the south toward the north. New once-through steam generators and a produced water softening plant are added to the existing central plant, and the produced oil goes through the existing treating facilities. Sustaining wells and infill wells are drilled every year after start-up to keep production level.

Step 3: production and steam forecast

The Marx-Langenheim model from lesson 8, calibrated to the history of the existing flood, gives the growth of the heated zone and the oil rate per pattern. Combining it with the drilling schedule gives a field forecast: a ramp over three years, a plateau of 10,000 bbl/d for about twelve years and a decline at about 8 percent a year as the patterns mature. Over 25 years the plan recovers about 74 million barrels, about 44 percent of the oil in place, at an average SOR of 4.0.

A plot of oil rate in barrels per day against year over 25 years. The rate ramps from about 2,500 in year one to a plateau of 10,000 from year four to year fifteen, then declines to about 4,300 by year 25. A second line shows annual cash flow in millions, negative in the first year and positive from year three.
Production and cash flow profile for the development plan. Most of the value comes from the plateau years.

Step 4: facilities, water and emissions

The steam rate at plateau is about 40,000 bbl/d CWE. The water plan recycles produced water into the new steam generators after softening, and sends the surplus to existing disposal wells. The greenhouse gas intensity, using the method from lesson 11, is about 97 kg CO₂e per barrel at an SOR of 4, so the carbon cost under cap-and-trade is a real line item. Ethan includes a case in which a solar steam field supplies part of the daytime steam, and notes that all new wells must be permitted under the current state rules and sited outside the setback zones around homes and schools.

Step 5: costs and economics

The economic model brings the pieces together. Revenue is the production times the netback price, which is the market price less transport, blending and other deductions. Operating costs include steam, at a cost per unit of steam that depends mainly on gas price, fixed costs for the facility and staff, and carbon compliance costs. Capital costs include the initial facility and wells over three years and sustaining capital every year. The net present value, NPV, discounts each year's cash flow to today at the company's discount rate.

\[\mathrm{NPV}=\sum_{t}\frac{CF_{t}}{(1+r)^{t}}\]
A 25-year production profile, cash flow and NPV at 10 percent, and the sensitivity of NPV to SOR.
# Development economics for a thermal project: production, steam, carbon and NPV
SI = False  
years = 25
peak = 5000.0 if SI else 10000.0          # m3/d bitumen (ca SAGD expansion) or bbl/d (us steamflood expansion)
ramp = [0.25, 0.65, 0.95] + [1.0] * 12 + [0.92 ** n for n in range(1, years - 14)]
sor = 3.0 if SI else 4.0
price = 380.0 if SI else 62.0              # netback per m3 (CA dollars) or per bbl (US dollars) before steam and carbon costs
steam_cost = 22.0 if SI else 1.9           # gas and water cost per m3 or per bbl of steam (CWE)
carbon = 6.0 if SI else 1.2                # net carbon compliance cost per m3 or per bbl of oil
opex_fixed = 60e6 if SI else 45e6          # per year
capex = [450e6, 550e6, 150e6] if SI else [180e6, 140e6, 60e6]
sustaining = 40e6 if SI else 25e6          # new well pairs or patterns each year after start-up
r = 0.10
npv = 0.0; cum = 0.0
for y in range(years):
    oil = peak * ramp[y] * 365
    cash = oil * (price - sor * steam_cost - carbon) - opex_fixed - (sustaining if y >= 3 else 0)
    cash -= capex[y] if y < len(capex) else 0
    npv += cash / (1 + r) ** (y + 0.5)
    cum += oil
    if y in (0, 2, 5, 10, 15, 20, 24):
        print(f"year {y + 1:2d}: oil {peak * ramp[y]:7,.0f} {'m3/d' if SI else 'bbl/d'}  cash flow {cash / 1e6:7.0f} million")
print(f"cumulative oil {cum / 1e6:.0f} million {'m3' if SI else 'bbl'}; NPV at 10 % = {npv / 1e6:,.0f} million")
for d_sor in (-0.5, 0.5):
    npv2 = 0.0
    for y in range(years):
        oil = peak * ramp[y] * 365
        cash = oil * (price - (sor + d_sor) * steam_cost - carbon) - opex_fixed - (sustaining if y >= 3 else 0) - (capex[y] if y < len(capex) else 0)
        npv2 += cash / (1 + r) ** (y + 0.5)
    print(f"SOR {sor + d_sor:.1f}: NPV {npv2 / 1e6:,.0f} million")
Output
year  1: oil   2,500 bbl/d  cash flow    -176 million
year  3: oil   9,500 bbl/d  cash flow      79 million
year  6: oil  10,000 bbl/d  cash flow     124 million
year 11: oil  10,000 bbl/d  cash flow     124 million
year 16: oil   9,200 bbl/d  cash flow     109 million
year 21: oil   6,064 bbl/d  cash flow      48 million
year 25: oil   4,344 bbl/d  cash flow      14 million
cumulative oil 74 million bbl; NPV at 10 % = 610 million
SOR 3.5: NPV 637 million
SOR 4.5: NPV 582 million

The base case gives an NPV of about 610 million dollars at 10 percent. Mei Lin looks at the sensitivity first. 'Half a point of SOR moves the value by about 27 million dollars either way,' she says. 'What about price?' Ethan has run that too: a 20 percent drop in the oil price, which is well within the range of the last decade, cuts the NPV by about 60 percent. 'So the reservoir decides how good the project is,' Mei says, 'and the market and the permitting rules decide whether we can build it. Make sure the board sees all three.'

Step 6: risks and the review

Paul, Lena and Tom each review the plan from their own angle. Paul asks about the reservoir: are the pay and saturation maps supported by enough wells and core, and how much would the mud layer or the top water reduce the rate? Lena asks about the forecast: does the efficiency factor match the field's history, and what happens if the plateau is shorter? Tom asks about operations: can the steam generators and water plant reach the planned capacity, and how will start-up of new wells be managed alongside existing ones? Mei asks about the decision: which uncertainties matter most, what would it take to change the recommendation and what can be learned before the money is committed?

Ethan answers with a risk register that lists each uncertainty, its likely effect on value and the way it will be managed: more delineation wells where the pay map is weakest, a phased development so that the first phase informs the later ones, a solvent pilot before committing to solvent co-injection, and a range of price cases. The plan does not remove the uncertainties, but it shows the board what they are and how the company will respond.

Bringing the course together

The capstone draws on every lesson. The classification of heavy oil and bitumen and the volumetric estimate come from lesson 1, the geology and containment from lesson 2 and the viscosity and thermal properties from lesson 3. Steam generation, mining and extraction and wellbore heat losses come from lesson 4, the SAGD concept and Butler's equation from lesson 5 and operations and SOR from lesson 6. Cyclic steam, steamflooding and the alternatives to steam come from lessons 7 to 10, and the environmental and regulatory case from lesson 11. A good thermal engineer knows how each of these pieces connects to the others, and to the value of the project.

Worked problem

NPV of a simple cash flow

A small expansion costs 120 million dollars now and earns 25 million dollars a year for ten years, starting at the end of year 1. Calculate the NPV at 10 percent.

Show solution
  1. The present value factor for ten equal annual payments at 10 percent is (1 − 1.1⁻¹⁰) / 0.1 = 6.145.
  2. PV of the cash flows = 25 × 6.145 = 153.6 million dollars.
  3. NPV = 153.6 − 120 = 33.6 million dollars.

Answer: About 34 million dollars. The project creates value at a 10 percent discount rate, but a 22 percent drop in annual cash flow would make the NPV negative.

Presenting the plan

The final step is presenting the plan to the people who decide. A board does not need every calculation, but it does need a clear account of what is proposed, what it will cost, what it is expected to return and what could go wrong. Ethan organizes his presentation around a few key exhibits: a map showing where the development would go and why, a production and steam forecast with its range of uncertainty, a cash flow chart with the base case and the main sensitivities, a summary of the environmental case and the permits needed, and the risk register. Each exhibit has a one-line conclusion at the top so that the message is clear even to someone who reads only the headlines.

Mei Lin adds advice from her own experience. Show the downside honestly, because a board that is surprised later loses trust in the team. Explain what the company will learn from each phase and how that learning will change later decisions. And state the recommendation plainly: proceed, proceed with conditions, or stop. A plan that ends with a clear recommendation, supported by the analysis and honest about its uncertainties, is far more useful than one that hedges every statement.

After the decision

Approval starts a new phase of work. Regulatory applications are prepared from the plan, detailed engineering of the facilities begins, drilling programs are designed and contracts are let. The forecast becomes the baseline against which the project's performance will be tracked. As the first wells come on, engineers compare actual rates and SORs with the forecast and update the reservoir model, which informs the later phases. In this way a development plan is never really finished: it is revised with each new set of data, and the questions it answers, which process, how many wells, how much steam, at what cost and with what impact, are asked again at every stage of the project's life.

For Ethan, the year in the thermal group has been an introduction to all of these questions. He has learned how heavy oil and bitumen differ from conventional oil, why heat and solvents work and where they fall short, how to estimate rates and steam needs with simple models and when to trust those models, and how environmental and economic factors shape every decision. The skills apply far beyond a single asset, to any project in which energy, fluids and rock must be managed together.

Common mistakes

  • MistakeBuilding the plan around one process without checking the reservoir.

    InsteadLet thickness, viscosity, depth and cap rock decide the process.

  • MistakeUsing Butler or Marx-Langenheim rates unscaled.

    InsteadCalibrate analytical forecasts to field history or simulation.

  • MistakePresenting a single NPV.

    InsteadShow sensitivities to SOR, price and costs, and the main risks.

  • MistakeLeaving environmental and regulatory costs out of the economics.

    InsteadInclude carbon, water and reclamation costs and the permitting path.

Summary and key terms

  • A thermal development plan starts with the resource and lets the reservoir choose the process.
  • The concept sets wells, pads or patterns, facilities and phasing.
  • Analytical models calibrated to field history give production and steam forecasts.
  • Water, emissions and regulation are part of the plan and the economics.
  • NPV discounts cash flows; SOR and price sensitivities show what matters.
  • A risk register and phased development make the plan robust.
Development plan
A document setting out how a resource will be developed, produced and paid for.
Netback
Market price less transport, blending and other deductions.
NPV
Net present value, the sum of discounted cash flows.
Sustaining capital
Spending on new wells and equipment to maintain production.
Sensitivity
The change in value for a change in one input.
Risk register
A list of uncertainties, their effects and how each will be managed.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. What decides the choice of process?

    Show answer

    Reservoir thickness, viscosity, depth and cap rock.

  2. Why calibrate analytical rates?

    Show answer

    Ideal models overestimate field performance.

  3. What is a netback?

    Show answer

    The price received after transport and other deductions.

  4. How can phasing reduce risk?

    Show answer

    The first phase provides information before later spending.

Lesson quiz · 5 questions