DCT-340 · Lesson 6 of 12 · 20 min

Emergency operating procedures and alarm response procedures

Planned work at Stonebridge follows methods of procedure, written days or weeks ahead, reviewed and approved, as DCT-330 described. Emergencies do not wait for a review. When a chilled-water pipe starts leaking at 03:00 or a UPS drops to bypass in the middle of a storm, the people on shift must act within minutes, in the right order, without making things worse. They do it with procedures written in advance for exactly those situations: emergency operating procedures, known as EOPs, and the shorter alarm response procedures that sit behind each important alarm. This lesson is about how those procedures are written, kept and used, and why practising them matters as much as having them.

The family of procedures

Jamal has met several kinds of procedure in the program. It helps to see them side by side.

The procedures used in operations. MOPs are planned changes; ARPs and EOPs are prepared responses.
ProcedureUsed forWrittenExample
Standard operating procedure (SOP)Routine operation that repeatsOnce, reviewed periodicallyTaking the weekly generator readings; starting a CRAH after a filter change
Method of procedure (MOP)A specific planned change or maintenance jobFor each job, approved through change managementUPS-A2 annual internal inspection
Alarm response procedure (ARP)What to do when a particular alarm appearsOnce per alarm type, kept with the alarmCRAH high return temperature; battery string high temperature
Emergency operating procedure (EOP)A failure or emergency that threatens people or the loadOnce per scenario, drilled regularlyUtility loss with generator failure; chilled-water leak in a data hall

The difference that matters most is time. A MOP is written for a job whose timing Stonebridge chooses. An EOP is written for an event whose timing nobody chooses, and it must work for whoever is on shift when it happens, including a technician in his second month on nights. So EOPs are written to be followed under stress, by people who may be tired, interrupted and frightened, and they are practised until the first steps are known by heart.

What an alarm response procedure contains

The monitoring system raises hundreds of different alarms, and most of them do not need a full emergency procedure. Each alarm that matters has a short alarm response procedure attached to it in the monitoring system, so that the person who sees the alarm can open the response with one click. A good ARP fits on one screen.

  • What the alarm means, in plain words, and what usually causes it.
  • How to confirm it: which readings or local checks prove the alarm is real and not a sensor fault.
  • What to do first, and what not to do.
  • Who to tell, and how urgently.
  • When it becomes an emergency, and which EOP then applies.

For example, Stonebridge's ARP for a CRAH high return temperature alarm in Hall A tells the technician that the alarm usually means the unit has lost cooling or the aisle has lost containment, asks him to check the unit's chilled-water valve position and supply temperature and to look at the aisle doors and blanking, tells him not to reset or restart the unit until the cause is known, says to tell the shift lead at once, and moves to the EOP for loss of cooling if two or more units alarm together or inlet temperatures in the hall pass a set limit.

What an emergency operating procedure contains

An EOP covers a scenario rather than an alarm: loss of utility power, a UPS failure to bypass, loss of a chiller plant, a chilled-water leak, a fire alarm in a data hall, a generator that fails to start, a release of clean agent, a medical emergency. Stonebridge's EOPs share one format, so that a technician who knows one knows where to look in any of them.

The sections of a Stonebridge emergency operating procedure.
SectionWhat it holds
Title and triggerThe scenario and the alarms or observations that start the EOP
Safety firstHazards to people and what to do about them before anything else
Immediate actionsA short numbered list of first steps, few enough to remember
VerificationHow to confirm what has happened and what is still working
StabilizationSteps that protect the load and prevent the problem spreading
NotificationWho to call, in what order, and what to tell them
RecoveryReturning to normal operation, usually under a separate procedure
ReferencesSingle-line diagrams, valve charts, contacts, related ARPs and EOPs
A flowchart running from top to bottom. An alarm or observation leads to a box labelled confirm it is real. A diamond asks whether people are in danger; the yes branch leads to make people safe and call for help, which rejoins the main flow. The main flow continues through immediate actions, verify what is working, stabilize and protect the load, notify, and finally recover or hand over to incident management. A side note says stop and ask the shift lead if anything does not match the procedure.
The shape of every emergency operating procedure. People come first; then the first actions, verification, stabilization, notification and recovery.

The immediate actions deserve special care. They are the steps that must be taken before there is time to read, so they are kept short, usually three to six steps, and written as plain commands. For the chilled-water leak EOP in Hall A, for example, the immediate actions are: make sure nobody is standing in water near electrical equipment; tell the shift lead and the monitoring desk; find the source if it can be seen safely; and close the isolation valves for that section as shown on the valve chart, but only if the chart shows the other section can carry the load. Everything after that can be read from the page.

Writing procedures people can follow

Stonebridge's EOPs are written by its operations engineers with the shift leads and reviewed with the technicians who will use them. A few rules come from long experience in the industry.

  • One action per step, starting with a verb: close valve CHW-A-14, not the valve should be closed if conditions require.
  • Name equipment exactly as it is labelled in the field, and include the location: switchboard SWBD-A2, electrical room A-E2.
  • Put checks where mistakes are likely: confirm the valve tag before closing it; confirm the partner unit is running before stopping this one.
  • Say what success looks like after each important step, so the user knows whether to go on.
  • Say when to stop and call for help, and make stopping acceptable: an EOP that has stopped matching what you see is no longer the right EOP.
  • Keep it current: an EOP is reviewed when equipment changes, after every use and drill, and at least yearly.

Lesson 1 quoted the industry finding that most human-error outages come from procedures not followed or badly written. EOPs are where that finding bites hardest. A procedure that names a valve that has been replaced, or a phone number that no longer works, or a step that cannot be done in the dark, fails exactly when it is needed. Every review asks the same questions: can this be done as written, by the least experienced qualified person on shift, at night, under pressure?

Where procedures live

The EOPs are kept in three places. The master copies are in the document system, with revision control so that only the current version is in use. Printed copies of the current versions sit in a red binder at the shift lead's desk in the operations centre, because the document system may be on a network that is affected by the emergency. And at key equipment, such as each electrical room, the chilled-water valve stations and the generator yard, laminated placards show the immediate actions and the local valve or breaker chart. When an EOP is revised, the shift lead replaces the binder pages and the placards and signs the change log, and the old versions are removed and destroyed.

Worked problem

The placard that was out of date

During a walk-through drill of the chilled-water leak EOP in Hall A, Jamal reads the laminated valve chart at valve station A-VS2 and goes to close the valves it shows for section 3.

Show solution
  1. Roz stops him at the second valve: its tag reads CHW-A-17, but the placard shows CHW-A-16.
  2. They check the master EOP in the document system: it was revised four months earlier, when a new section valve was added during a pipe modification, and the valve numbers changed.
  3. The binder at the shift desk had been updated, but the placard at the valve station had not.
  4. Dmitri replaces the placard that afternoon, checks every other placard against the current revisions, and adds placards to the EOP revision checklist so that they are always included.

Answer: A drill found the problem when nothing was leaking. In a real leak, closing the wrong valve could have isolated a section that was still needed.

Drills

A procedure that has never been used is a guess. Stonebridge practises its EOPs in three ways. Tabletop exercises gather a shift crew around a table to talk through a scenario step by step, with the shift lead playing the events: the alarm appears, the reading is this, the vendor does not answer. Walk-through drills take the crew to the equipment and have them point to each valve, breaker and reading the EOP names, without operating anything. And for some EOPs, live tests are done under a method of procedure, such as the annual pull-the-plug test of DCT-220, which exercises the utility loss EOP for real. Every crew does at least one drill a month, rotating through the EOPs so that each crew practises each important EOP at least once a year.

Drills are timed and recorded. The point is not to grade the crew but to find out whether the procedure and the people work together. A step that takes much longer than expected, a valve that is hard to reach, a contact who does not answer or a step that two people understand differently are all findings, and each one becomes a change to the procedure, the equipment or the training.

# EOP step tracker: record each step's time and check order and duration against the procedure
eop = [  # step, expected maximum minutes from start
    ("people safe, area clear of water near electrical equipment", 2),
    ("shift lead and monitoring desk told", 3),
    ("source found and confirmed", 8),
    ("section isolation valves closed per valve chart", 12),
    ("other section confirmed carrying the load", 15),
    ("tenants and site manager notified", 20),
]
log = [  # step index, minutes from start (from the drill record)
    (0, 1.5), (1, 2.5), (2, 9.5), (3, 13.0), (4, 14.5), (5, 26.0),
]
last = -1
for idx, t in log:
    step, limit = eop[idx]
    notes = []
    if idx != last + 1:
        notes.append("out of order")
    if t > limit:
        notes.append(f"{t - limit:.1f} min over")
    last = idx
    print(f"{t:5.1f} min  {step:60} {'; '.join(notes) if notes else 'ok'}")
Output
  1.5 min  people safe, area clear of water near electrical equipment   ok
  2.5 min  shift lead and monitoring desk told                          ok
  9.5 min  source found and confirmed                                   1.5 min over
 13.0 min  section isolation valves closed per valve chart              1.0 min over
 14.5 min  other section confirmed carrying the load                    ok
 26.0 min  tenants and site manager notified                            6.0 min over

In this drill, finding the leak took longer than the procedure allowed, because the leak was simulated under the raised floor at the far end of the row and the crew had to lift tiles to find it, which also made the valves close a minute late; and the notification step ran six minutes over because the tenant contact numbers were in a different binder. Both findings went into the drill record. The first led to a request for leak detection cable zoning to be shown on the floor map so the location of an alarm is clearer; the second to the contacts being added to the EOP itself.

Using an EOP for real

When an emergency happens, the shift lead decides which EOP applies, says so aloud, and assigns roles: who reads the procedure, who carries out the steps, who watches the rest of the plant, who handles calls. One person reads each step aloud and the person doing it repeats it back before acting, then reports the result. This read-and-repeat method, borrowed from aviation and power plants, catches mistakes like the wrong valve tag before they become actions. The times of key steps are written down as they happen, on the EOP's own record sheet or in the shift log, because they are needed later for the incident report and the root cause analysis of Lessons 7 and 9.

Two situations need judgement. If the event does not match any EOP exactly, the shift lead chooses the closest one and uses its safety and stabilization steps while calling for help. And if, partway through, what the crew sees stops matching what the procedure expects, they stop and reassess rather than pressing on. Following a procedure is not the same as following it off a cliff. In both cases the incident management of Lesson 7 takes over as soon as there is someone to run it.

Common mistakes

  • MistakeTreating an EOP as reading material to look up during the emergency

    InsteadLearn the immediate actions by heart and practise the rest in drills

  • MistakeWriting steps that only an expert can follow

    InsteadWrite one plain action per step, with exact equipment names, checks and what success looks like

  • MistakeUpdating the master copy but not the placards and binders

    InsteadInclude every printed copy and placard in each revision, and remove old versions

  • MistakeCarrying on when the plant stops matching the procedure

    InsteadStop, tell the shift lead and reassess before taking the next step

  • MistakeRunning drills to grade the crew

    InsteadRun drills to test whether procedure and people work together, and turn findings into changes

Summary and key terms

  • SOPs cover routine work, MOPs planned changes, ARPs the response to particular alarms and EOPs emergencies.
  • An ARP explains an alarm, how to confirm it, what to do first, who to tell and when it becomes an emergency.
  • An EOP has a trigger, safety first, a short list of immediate actions, verification, stabilization, notification and recovery.
  • Procedures are written for the least experienced qualified person, at night, under pressure, and kept current everywhere they are printed.
  • Tabletop, walk-through and live drills test the procedures; every finding becomes a change.
  • In a real event, the shift lead names the EOP, assigns roles, uses read-and-repeat and records the times.
EOP
Emergency operating procedure: a prepared response to a failure or emergency that threatens people or the load.
ARP
Alarm response procedure: the short response attached to a particular alarm.
SOP
Standard operating procedure: instructions for a routine, repeated task.
Immediate actions
The few first steps of an EOP that must be done before there is time to read.
Tabletop exercise
A drill in which a crew talks through a scenario step by step without going to the equipment.
Walk-through drill
A drill at the equipment in which each step is pointed to but not carried out.
Read-and-repeat
A method in which one person reads a step aloud and the other repeats it before acting.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. What is the main difference between a MOP and an EOP?

    Show answer

    A MOP is written for a planned job at a chosen time; an EOP is a prepared response to an event nobody chose.

  2. Name four sections of an EOP.

    Show answer

    Any four of: trigger, safety, immediate actions, verification, stabilization, notification, recovery, references.

  3. A drill finds that a placard shows an old valve number. What should follow?

    Show answer

    Replace the placard, check all other placards and make placards part of every revision.

  4. Why are immediate actions kept to a few steps?

    Show answer

    They must be done from memory before there is time to read.

Lesson quiz · 5 questions

Score 60% or more to complete this lesson.

Take the quiz