CON-375 · Lesson 3 of 12 · 21 min

Correspondence, transmittals and written notice

In month four of the Westgate project, Brightwater's excavation crew hit a buried concrete foundation where the geotechnical report showed only fill. Marcus Bell phoned Robert Kaminski, the owner's project manager, who came to look that afternoon. Everyone agreed it was unexpected. Everyone agreed it would cost money. Nobody wrote anything down for nine days, by which time the old foundation had been broken out and trucked away. When Elena Vasquez later submitted the change request, the first response from the owner's side questioned whether the condition had been as extensive as Brightwater claimed, and whether written notice had been given before the conditions were disturbed. The phone call and the site visit were real, but they were not notice.

Construction contracts run on written communication. Letters, emails, platform messages and transmittals are how instructions are given, information is exchanged and rights are preserved. Some of these communications are ordinary coordination. Others are formal notices that the contract requires, in a set form, to a set person, within a set time, before a party can claim extra time or money. This lesson is about knowing the difference and getting both right.

On Westgate, the CCDC 2 2020 contract uses the defined term Notice in Writing for formal communications, and its articles set out how such notices are delivered and when they are received. The supplementary conditions, written by the Westgate Public Library Board, add specific time periods to several clauses. Brightwater's first job at contract award was to read every clause that required a Notice in Writing and list it, with its trigger, recipient and time limit, in the documentation matrix.

Three kinds of written communication

Three levels of written communication on a construction project.
KindExamplesFormality
Coordination messagesEmails arranging site visits, questions about schedules, informal updatesLow: still recorded, but not relied on for rights
Formal correspondenceLetters on letterhead or numbered platform correspondence, transmittals, requests and responsesMedium: numbered, logged and filed
Contractual noticesNotices of delay, changed conditions, claims, default, termination, objections to determinationsHigh: required form, recipient, method and time limit

The danger lies in letting a contractual notice hide inside a coordination message. An email that says 'FYI, we hit some old concrete today, will keep you posted' may be enough to show the owner knew about the condition, but it may not satisfy a clause that requires notice to a named person, describing the condition and stating an intention to claim. Brightwater's rule is that anything which might lead to a change in time or money gets its own numbered letter, separate from routine traffic, sent by the method the contract requires.

Correspondence that works

Every piece of formal correspondence on Westgate follows the same pattern, whether it is a letter or a numbered message in the project platform.

  • A unique number from the correspondence log, such as BWC-WGT-L-0147, and a clear subject line that names the issue, for example 'Level 2 transfer beam embed plates: RFI-112 response'.
  • The date, the sender and the named recipient, with copies to those who need them. Copies are never a substitute for sending to the person the contract names.
  • References to the documents involved: drawing numbers and revisions, specification sections, RFIs, earlier letters.
  • The facts, in order, without opinion or exaggeration.
  • What the writer wants: a decision, information, a meeting, acknowledgement, by a stated date.
  • Where rights may be affected, a reservation of rights and, if required, an express statement that the letter is notice under a named clause.

Tone matters. Correspondence is often read later by people who were not there. A letter that is calm, factual and specific reads well to an adjudicator; one that is sarcastic or accusatory makes the writer look unreasonable even when the writer is right. Elena's habit is to draft a difficult letter, leave it overnight, and remove every adjective that is not a fact.

Transmittals

A transmittal is a cover record that lists what was sent, to whom, when, why and what action is required. It turns the act of sending documents into a traceable event. On Westgate every drawing issue, submittal, sample delivery and closeout package moves under a transmittal, and the platform generates most of them automatically.

A transmittal record.
Transmittal fieldExample
Number and dateTR-0418, 2026-04-14
From and toArden Moss Architects to Brightwater, attention Jun Park
ItemsSheets A-2101 to A-2108, revision C03, 8 sheets
PurposeIssued for construction
Action requiredDistribute to framing and drywall subcontractors; withdraw C02
Response required byNot required; acknowledge receipt
RemarksRevised to suit RFI-112 response; embed plates relocated

The purpose field is the one most often left vague. 'For your information', 'for review and comment', 'for approval' and 'issued for construction' mean very different things, and a recipient who acts on a document sent only for information may find the sender disowns it later. Transmittals that need a response should state the response date, and the log should show when it came back.

Contractual notice: why the clauses are strict

Notice clauses exist so that the party who will pay for a problem learns about it early enough to do something: to investigate, to change the design, to stop work, to keep records of its own, or to budget. A notice given months later deprives the other party of those choices. Courts and tribunals in both countries have often enforced notice requirements strictly, treating timely notice as a condition that must be met before a claim can succeed, although outcomes depend heavily on the exact wording, on conduct and on the law of the place.

Under CCDC 2 2020, a contractor who intends to claim an increase in the Contract Price must give timely Notice in Writing of its intent to claim, keep records to support the claim, take reasonable steps to limit its losses, and follow up with a detailed account. The contract also contains a waiver clause under which claims not made in the required way may be released when the contract is paid out. Concealed or unknown conditions must be reported promptly, before they are disturbed, and changes in the Work must be agreed in a Change Order or directed in a Change Directive. Supplementary conditions frequently add fixed numbers of days to these clauses, so the specific contract must always be read.

A timeline from the discovery of a condition through the notice deadline, the detailed claim submission and the response, with the contract time limits marked
From event to notice to detailed claim: the clock starts when the condition is discovered or recognized.

The figure shows the sequence Brightwater follows for every potential claim. The clock starts when the event happens or when Brightwater recognizes it, not when it gets round to writing. A short notice goes first, within the contract period, saying what happened and that Brightwater intends to claim. The detailed claim, with quantified time and cost and supporting records, follows later, within whatever period the contract allows. Waiting until the cost is known before giving notice is one of the most common and expensive mistakes in construction.

Writing a notice

A notice does not need to be long. It needs to be complete, clear and on time. Brightwater uses a template with seven parts.

Seven parts of a written notice.
PartPurposeWestgate example
ClauseShow which contract provision the notice is given underGC 6.4 Concealed or Unknown Conditions and GC 6.6 Claims
EventDescribe what happened, where and whenBuried concrete foundation found at grid C-D/4-6 on 2026-02-17
ComparisonExplain how this differs from the contract documentsGeotechnical report borehole BH-4 showed fill to 3.2 m
EffectState the expected effect on cost and time, even if not yet quantifiedAdditional excavation, breaking and disposal; possible delay to footing work
IntentState expressly that a claim will be made or rights are reservedBrightwater intends to claim an adjustment to the price and time
RequestAsk for what is neededInspection before removal; instruction on how to proceed
RecordsSay what is being kept and attachedPhotos, survey, daily reports, separate cost code from today

Had Brightwater sent this notice on the day the foundation was found, Robert Kaminski could have arranged for the geotechnical engineer to inspect it, the extent could have been surveyed jointly, and the argument about how much concrete there had been would never have arisen. Since Westgate, Marcus carries the notice template on his tablet, and the rule on site is that a notice goes the same day as the phone call.

Counting the days

Time limits are expressed in different units: calendar days, working days, business days or periods tied to events such as receipt of an invoice. Each contract defines its terms, and statutes may define them differently. A notice period of five working days that spans a statutory holiday ends later than five calendar days would; a period of 21 calendar days does not stop for weekends.

Worked problem

When is the notice due?

Brightwater discovers a concealed condition on Thursday, 2026-04-02. Its supplementary conditions require notice within 5 working days after first observance, where working days exclude weekends and statutory holidays. Good Friday falls on 2026-04-03. On what date is notice due? If the period were 14 calendar days instead, when would it be due?

Show solution
  1. Count working days after 2026-04-02: Friday 3 April is a holiday and is skipped.
  2. Monday 6 April is day 1, Tuesday 7 day 2, Wednesday 8 day 3, Thursday 9 day 4, Friday 10 day 5.
  3. Working-day deadline: Friday, 2026-04-10.
  4. Calendar-day deadline: 2026-04-02 plus 14 days = Thursday, 2026-04-16.
  5. Brightwater's own practice is to send notice the same day, so either deadline is a backstop, not a target.

Answer: Notice is due by 2026-04-10 under the working-day clause, or 2026-04-16 under a 14-calendar-day clause.

Counting by hand invites mistakes, especially across holidays. Jun keeps a small script that computes deadlines for each notice clause in the documentation matrix whenever a new event is logged.

# Compute notice deadlines in working days and calendar days
from datetime import date, timedelta
holidays = {date(2026, 4, 3), date(2026, 5, 18), date(2026, 7, 1)}

def working_deadline(start, n):
    d, count = start, 0
    while count < n:
        d += timedelta(days=1)
        if d.weekday() < 5 and d not in holidays:
            count += 1
    return d

event = date(2026, 4, 2)
print('Event:', event, event.strftime('%A'))
print('5 working days:', working_deadline(event, 5))
print('14 calendar days:', event + timedelta(days=14))
print('21 calendar days:', event + timedelta(days=21))
Output
Event: 2026-04-02 Thursday
5 working days: 2026-04-10
14 calendar days: 2026-04-16
21 calendar days: 2026-04-23

Email, platforms and proof of delivery

Most correspondence now travels by email or through a project platform. That is efficient, but it raises questions the contract may answer. Does the contract allow notices by email? To which address? When is an email received: when it is sent, when it arrives, or at the start of the next business day? Does a message posted in a platform count as delivery to the named person, or only when that person opens it? Brightwater checks these points at the start of every project and, if the contract is silent or unclear, asks the owner to agree a protocol in writing.

  • Send contractual notices by the method the contract requires, even if everyone usually uses email, and keep the proof: courier receipt, registered mail slip, or a written acknowledgement.
  • When email is allowed, send to the named individual, ask for acknowledgement and file the sent message with its headers.
  • Do not rely on a platform's internal message for notice unless the contract or a signed protocol says platform delivery counts.
  • Keep a notice log separate from the general correspondence log, with the clause, trigger date, deadline, date sent, method and acknowledgement.

Common mistakes

  • MistakeTreating a phone call or site visit as notice.

    InsteadFollow every conversation that might affect time or money with written notice under the named clause, the same day.

  • MistakeWaiting until costs are known before giving notice.

    InsteadGive short notice of intent within the time limit and follow with the detailed claim later.

  • MistakeCopying the owner's representative but not sending to the person the contract names.

    InsteadAddress notices to the designated recipient; copies are extras, not substitutes.

  • MistakeBurying a notice inside a routine email.

    InsteadSend each notice as its own numbered letter that names the clause and states the intent to claim.

  • MistakeCounting calendar days when the contract says working days, or the reverse.

    InsteadRead the contract's definitions and compute deadlines with the holiday calendar.

Summary and key terms

  • Written communication ranges from coordination messages to formal correspondence to contractual notices.
  • Formal correspondence is numbered, dated, addressed to the named recipient, referenced to documents and factual in tone.
  • Transmittals record what was sent, to whom, when, for what purpose and what action is needed.
  • CCDC 2 2020 requires timely Notice in Writing of intent to claim, records, mitigation and a detailed account; supplementary conditions often add fixed periods.
  • A good notice names the clause, describes the event, compares it with the contract, states the effect and the intent to claim, makes a request and lists the records kept.
  • Deadlines must be counted using the contract's definition of days and the holiday calendar.
  • Email and platform delivery count as notice only when the contract or an agreed protocol says so.
Notice in Writing
The CCDC defined term for a formal written communication delivered as the contract requires.
Transmittal
A record listing documents sent, the recipient, the date, the purpose and the action required.
Reservation of rights
A statement that a party is not giving up any entitlement by acting or by not yet claiming.
Condition precedent
A requirement, such as timely notice, that must be met before a right, such as a claim, arises.
Working day
A day defined by the contract, usually excluding weekends and statutory holidays.
Waiver
The giving up of a right, sometimes by failing to make a claim as the contract requires.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. Why do contracts require early notice of claims?

    Show answer

    So the paying party can investigate, change course, keep its own records and budget while it still has choices.

  2. List four parts of a good notice.

    Show answer

    Any four of: the clause, the event, the comparison with the contract, the effect, the intent to claim, the request, the records kept.

  3. An event happens on Monday 2026-06-01; the period is 10 working days and there are no holidays. When is notice due?

    Show answer

    Count 10 weekdays after 1 June: Monday 15 June 2026.

  4. What is wrong with an email to a site engineer saying 'we found some rock, will update you'?

    Show answer

    It may not reach the named recipient, cites no clause, states no intent to claim and gives no details or request.

  5. What should a notice log record?

    Show answer

    The clause, trigger date, deadline, date sent, method of delivery and acknowledgement.

Lesson quiz · 5 questions