Twenty years ago, Keelson coordinated its ductwork by laying printed sheet metal drawings over the sprinkler, plumbing and electrical drawings on a light table and looking for places where lines crossed. Today the same job is done in three dimensions on a screen, with every trade's work combined into one coordination model. The tools have changed the speed and accuracy of coordination, but not its purpose: to prove that everything fits before anyone cuts metal or drills a hole. This lesson explains building information modelling, or BIM, from a sheet metal contractor's point of view, and how Lin Zhao's team uses it on the Eastgate Hospital addition.

What a BIM model is

A building information model is a digital model of a building in which each object is not just a shape but carries information about what it is. A duct in the model is not merely a box; it knows its system, its size, its material and gauge, its insulation, its connector types and its fitting code. A fire damper object knows its rating and its manufacturer. Drawings, schedules and quantities can all be produced from the same model, so a change made once shows up everywhere. That is the main advantage over two-dimensional drafting, where a change to a plan might not be carried into a section or a schedule.

On a project like Eastgate there is not one model but many. The architect and the structural and mechanical engineers each produce design models. Each trade contractor produces its own construction or fabrication model of its work: Keelson for ductwork, Northpoint Mechanical for piping, the sprinkler contractor, the electrical contractor and so on. The general contractor's coordinator combines them in a federated model, in which each trade's model is linked rather than merged, so each trade keeps control of its own work. Common software for this includes design authoring tools used by engineers and detailers, fabrication add-ons that hold real manufacturer and shop content, and model review and clash tools used for coordination.

Models are exchanged in agreed formats. Native files from the authoring software are common within a trade. For exchange between different programs, many projects use IFC, the open Industry Foundation Classes format, which is published as an international standard and can be read by most BIM tools. The BIM execution plan for the project, written early by the general contractor and signed by the trades, sets out which formats, coordinate system, levels of detail, file naming and meeting schedule everyone will use.

Level of development

Not every model is detailed enough to build from. The construction industry uses a scale called level of development, or LOD, to describe how much the information in a model element can be relied on. The scale published by the BIMForum, widely used in North America, runs from LOD 100, a symbol or rough mass, through LOD 200 with approximate size and location, LOD 300 with specific size, shape and location from the design, to LOD 400, where the element is modelled with enough detail and accuracy to be fabricated and installed. A further level is sometimes used for verified as-built conditions.

Level of development for ductwork. The exact definitions are set in the project's BIM execution plan.
LOD (typical meaning)For a ductWho usually models it
100A note or block showing that duct exists in an areaEarly design
200Approximate size and routeSchematic design
300Specific size, route and elevation from the designEngineer's design model
350Plus connections and clearances to other systemsCoordination
400Fabrication detail: joints, gauges, fittings, hangersSheet metal contractor

The engineer's design model for Eastgate is roughly LOD 300: the ducts are sized and routed, but without joints, real fittings or hangers. Keelson's fabrication model has to reach LOD 400. Lin's team rebuilds the ductwork with real connectors, joint lengths, fitting patterns from Keelson's catalogue, insulation thickness, hangers and inserts. That model becomes the source of the shop drawings, the fabrication lists and the CNC data. Kai was surprised how much of the engineer's model had to be redrawn; Lin explained that the design model is right about intent but usually not buildable in detail.

Four views of the same short duct run at increasing level of development: at LOD 200 a simple rectangular box; at LOD 300 a box with a defined elbow and size; at LOD 350 the same with insulation shown and clearances to a beam; at LOD 400 separate joints with flanges, a radius elbow with its tag, hanger rods and a trapeze, and a fire damper.
One duct run at four levels of development. Fabrication needs LOD 400.

Clash detection

Clash detection is the automatic search for places where objects in the federated model occupy the same space. A hard clash is two objects physically overlapping, such as a duct passing through a beam or a sprinkler main running through a duct. A soft clash, or clearance clash, is an object entering a zone that must be kept clear, such as the access space in front of a fire damper's access door, the service clearance below a terminal unit or the insulation thickness around a chilled-water pipe. A workflow clash involves timing, such as a duct that can only be installed if a pipe is hung first.

Clash tools are good at finding problems and bad at judging them. A first clash run on a hospital floor can produce thousands of clashes, many of them trivial or duplicates: a hanger rod touching a conduit, or a duct crossing a pipe that is really above it in a different version. Coordinators filter clashes by system and size, group them by location, and set tolerances so that small overlaps that the field can easily solve do not clutter the list. What matters is that the important clashes are found, assigned to a trade and solved before the drawings are signed off.

# Sorting a clash report by trade and priority
clashes = [("duct", "beam", "hard", 14), ("duct", "sprinkler main", "hard", 37),
           ("duct", "cable tray", "hard", 22), ("hanger rod", "conduit", "hard", 160),
           ("damper access zone", "pipe", "clearance", 9), ("duct", "light fixture", "clearance", 48)]
priority = {"beam": 1, "sprinkler main": 2, "pipe": 2, "cable tray": 3, "light fixture": 3, "conduit": 4}
total = sum(c[3] for c in clashes)
for a, b, kind, n in sorted(clashes, key=lambda c: (priority[c[1]], -c[3])):
    print(f"{a:20s} vs {b:15s} {kind:9s} {n:4d}  priority {priority[b]}")
print(f"total {total}; hanger and conduit touches left for the field: {160}")
Output
duct                 vs beam            hard        14  priority 1
duct                 vs sprinkler main  hard        37  priority 2
damper access zone   vs pipe            clearance    9  priority 2
duct                 vs light fixture   clearance   48  priority 3
duct                 vs cable tray      hard        22  priority 3
hanger rod           vs conduit         hard       160  priority 4
total 290; hanger and conduit touches left for the field: 160

In this example most of the raw clashes are hanger rods touching conduit, which the electricians and Keelson's field crew can solve by shifting a rod or a conduit a few centimetres. The duct-to-beam clashes come first, because only a change in the duct or a structural approval can solve them; then the sprinkler mains and the damper access zones. The coordinator's job is to keep the meeting focused on the clashes that require a decision.

The coordination meeting

At Eastgate, coordination runs floor by floor. Each week the trades upload their latest models, Northpoint's coordinator Arjun Mehta runs the clash tests, and the trades meet with the model on a large screen. They work through the clash groups area by area, agree who moves what, and record each decision with a screenshot and an owner. Lin attends for Keelson, often with Sean Doucette, the field foreman, because some decisions depend on how the duct will actually be hung. When an area is clean, every trade signs it off, and from then on any change in that area requires another round of coordination.

Two habits make the meetings work. The first is to bring solutions, not complaints: Lin arrives with a proposed reroute for each duct clash, already checked against the duct sizes and pressure drop. The second is to respect the order of priority described in Lesson 1, while remembering that the cheapest solution for the project is not always the one that keeps a particular trade's work unchanged. Sometimes it is cheaper for the sprinkler main to drop 150 mm than for a large duct to change shape for 20 m.

Fabrication-ready models

Once an area is coordinated, the LOD 400 model drives fabrication. Each straight joint and fitting in the model carries its fitting code, dimensions, gauge, connector types, sealant class and a unique tag. Keelson's fabrication software exports this information to the shop: cut lists for the coil line, pattern files for the plasma table, labels for each piece and assembly spool sheets. Lessons 8 and 9 follow that data onto the machines. Because the same model also produces the shop drawings, the drawing, the label on the metal and the location in the building all agree, provided nobody edits one without the others.

The model also feeds the field. Hanger and insert locations from the model are exported as points that a layout crew can set out with a robotic total station, or printed as dimensioned layout sheets. Sean's crew on Eastgate set the concrete inserts for levels 2 and 3 from model points before the slabs were poured, so that the duct supports land exactly where the duct is drawn. That only works if the model is right and has been coordinated with the structural engineer's slab openings and embedded items.

A plan and a section of a corridor ceiling from a coordination model. In the plan, a large supply duct crosses a sprinkler main and a cable tray; red circles mark the clashes. In the section, the duct passes below a steel beam with its fireproofing, above a ceiling grid, beside a cable tray, with a dashed zone in front of a fire damper access door marked as a clearance zone.
Clash detection in a coordination model. Hard clashes (red) and a clearance zone (dashed) for damper access.

Limits and good practice

A model is only as good as the information put into it. Structural steel modelled from the design drawings may be off by the amount that the fabricator later adjusts; fireproofing is often not modelled at all; existing buildings are rarely modelled accurately unless they are scanned. On renovations and connections to existing buildings, Keelson uses laser scans of the existing ceiling space, like those described in the geomatics courses, to bring real conditions into the model. On Eastgate, the connection to the existing hospital corridor was scanned before detailing, and the scan showed two existing ducts that the old record drawings had placed 300 mm away from where they really were.

Good modelling practice is mostly discipline: model to the agreed coordinate system and levels; keep each system on its own category or layer; use real fitting content rather than generic boxes; model insulation and hangers; name files and tag objects to the BIM execution plan; and never edit another trade's model. Keelson's checklist also requires that every change after sign-off be logged, with the reason and who approved it, because a late change in one area can reopen clashes that were thought to be solved.

Worked problem

Choosing who moves

On Eastgate level 2, a 1,000 × 450 supply main clashes with a 150 mm sprinkler main for 18 m along a corridor. Moving the duct requires flattening it to 1,400 × 300, adding two transitions and raising the fan's static pressure slightly. Dropping the sprinkler main 200 mm requires two offsets and no other changes, and still clears the ceiling. Which should move?

Show solution
  1. Check fixed items: there is no structural conflict either way.
  2. Compare impacts: the duct change adds fittings and pressure drop over a long run; the sprinkler change adds two offsets.
  3. Check clearances: the lowered sprinkler main still clears the ceiling and lights.
  4. Agree in the meeting and record the decision, with the sprinkler contractor as owner.

Answer: The sprinkler main moves. Coordination looks for the lowest-cost solution for the project, not for any one trade.

Keeping the model honest

A coordination model is only as good as the information in it. Lin checks that each trade's model is current before every clash run, that insulation and access zones are modelled, and that the reference points and levels match the project's survey control. When a field measurement shows the building differs from the model, for example a slab poured a little high or a beam moved during erection, the model is updated before more areas are released, so that the next shop drawings are drawn to the real building.

Common mistakes

  • MistakeTreating the engineer's design model as fabrication-ready.

    InsteadRebuild the work at LOD 400 with real joints, fittings, insulation and hangers.

  • MistakeTrying to resolve every raw clash in the meeting.

    InsteadFilter, group and prioritise clashes so decisions focus on the important ones.

  • MistakeEditing another trade's model to clear a clash.

    InsteadAgree the change in coordination and let each trade change its own model.

  • MistakeForgetting fireproofing and insulation in the model.

    InsteadModel them, or allow for them in clash tolerances.

  • MistakeChanging an area after sign-off without telling anyone.

    InsteadLog every change and re-run coordination in that area.

Summary and key terms

  • A BIM model carries information as well as geometry, so drawings, schedules and quantities stay consistent.
  • Each trade models its own work; a federated model combines them for coordination, often exchanged through IFC.
  • Level of development describes how far a model can be relied on; fabrication needs LOD 400.
  • Clash detection finds hard, clearance and workflow clashes; people decide which matter.
  • Coordinated LOD 400 models drive shop drawings, fabrication data and field layout.
  • Real conditions, especially in existing buildings, should be captured by scanning.
BIM
Building information modelling: digital models whose objects carry data as well as shape.
Federated model
A combined model that links each trade's separate model for coordination.
IFC
Industry Foundation Classes, an open standard format for exchanging BIM data.
LOD
Level of development: how detailed and reliable a model element is.
Hard clash
Two model objects occupying the same space.
BIM execution plan
The project document setting out modelling standards, formats and responsibilities.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. What is the difference between a hard clash and a clearance clash?

    Show answer

    A hard clash is a physical overlap; a clearance clash is an object entering a zone that must be kept clear, such as an access zone.

  2. Why does the sheet metal contractor rebuild ducts from the engineer's model?

    Show answer

    The design model shows intent at about LOD 300; fabrication needs real joints, fittings, gauges, insulation and hangers at LOD 400.

  3. What does a federated model let each trade keep?

    Show answer

    Control of its own model, which is linked rather than merged.

  4. Name one way the model helps the field crew.

    Show answer

    Hanger and insert locations exported as layout points or dimensioned layout sheets.