PMP-131 · Lesson 7 of 12 · 27 min

Procurement planning and make-or-buy

Few projects do everything themselves. Project Compass buys design services, construction, furniture, RFID tags, kiosks and security gates, and possibly app development and tagging labour. Each purchase brings a supplier with its own interests into the project, and each contract shapes who carries which risks. This lesson covers procurement planning: deciding what to buy, writing the procurement management plan and procurement strategy, the make-or-buy analysis, statements of work and solicitation documents, and the legal and ethical context. Lesson 8 compares contract types and lesson 9 covers selecting sellers and managing contracts. CON-330 applies the same ideas to construction buyout and subcontracts in more depth.

Procurement on a project

Procurement management covers the processes needed to purchase or acquire products, services or results from outside the project team. The buyer is the organization acquiring them, here the library; the seller is the supplier, contractor, vendor or service provider. The legal basis is an agreement: a contract, purchase order, memorandum of understanding or, between departments, a service level agreement. A contract is a mutually binding agreement that obliges the seller to provide what is specified and the buyer to pay for it. Because it is legally binding, contract language deserves more care than most project documents, and project managers usually work with procurement specialists and legal advisers rather than alone.

In many organizations the project manager does not have authority to sign contracts. That authority sits with a procurement or contracting officer. The project manager's role is to make sure the project's needs are described correctly, that the timing of procurement fits the schedule, that risks are allocated sensibly and that seller performance is managed once the contract is signed. Exam questions often test this: when a seller asks for a change, the project manager does not simply agree, but follows the contract's change process with the person who has contracting authority.

The procurement management plan and procurement strategy

The procurement management plan describes how the project will acquire goods and services. It is part of the project management plan and typically covers how procurement will be coordinated with scope, schedule and budget, key dates and lead times, who has authority to approve and sign, standard documents to use, legal jurisdiction and currency, independent estimates, risk management issues such as bonds and insurance, how sellers will be prequalified, and how performance will be measured.

The procurement strategy, developed for each significant purchase, decides three things: the delivery method (for example, a professional services agreement for design; for construction, design-bid-build, design-build or construction management, as CON-340 explains), the contract payment type (fixed price, cost-reimbursable or time and materials, lesson 8) and the procurement phases (for example, prequalification, then invitation, then award).

Procurement strategy summary for Project Compass.
PurchaseDelivery method and phasesPayment typeLead time that drives timing
Architect and engineersProfessional services agreement after qualifications-based selectionFixed fee with hourly rates for additional servicesNeeded in month 1
Fit-out constructionDesign-bid-build: drawings complete, then invited tender to five prequalified contractorsStipulated (fixed) price with unit prices for variationsTender after permit drawings; 4 weeks to bid
Furniture and shelvingRequest for quotation from approved vendorsFirm fixed price10 to 12 weeks manufacture
RFID tagsPurchase order under a regional purchasing agreementFirm fixed price per tag (tariff surcharges excluded)6 weeks, doubling before the holidays
Kiosks and security gatesRequest for proposals with weighted evaluationFixed price incentive fee considered; lesson 812 weeks from order
Mobile app developmentRequest for proposals for an agile teamTime and materials with a not-to-exceed ceilingTeam needed in month 3
Collection tagging labourMake or buy decision: in-house temporary staff or vendor serviceWages or unit price per itemBefore the opening collection is moved

Make-or-buy analysis

A make-or-buy analysis decides whether work is done by the project team or bought from outside. Cost is one factor, compared fairly: direct costs of making (staff time, equipment, training) against the price of buying plus the costs of managing the contract. Other factors are often decisive: capacity and skills, schedule, control over quality and intellectual property, confidentiality, the strategic value of building internal capability, and risk. Buying transfers some risks to the seller but creates others, such as dependence on the seller and contract disputes.

Make-or-buy analysis for tagging the opening collection: library staff or a vendor tagging service.
# Make or buy: tag the opening collection in-house or use a vendor tagging service ($, invented)
items = 38_000                     # opening collection (PMP-130, lesson 6)
rate, rework = 110, 0.03           # items per person-hour and second-pass share from the pilot
wage = 42.0                        # library's loaded hourly cost for temporary tagging staff
in_house_fixed = 9_000             # training, supervision and setting up the two stations
in_house_per_item = wage * (1 + rework) / rate
vendor_fixed = 2_500               # vendor mobilization and data mapping
vendor_per_item = 0.72             # vendor quote per item; tags are supplied separately either way
inhouse = in_house_fixed + in_house_per_item * items
vendor = vendor_fixed + vendor_per_item * items
breakeven = (in_house_fixed - vendor_fixed) / (vendor_per_item - in_house_per_item)
print(f"In-house cost per item {in_house_per_item:.3f}")
print(f"In-house total {inhouse:,.0f}   Vendor total {vendor:,.0f}")
print(f"Break-even volume {breakeven:,.0f} items; above it, in-house is cheaper")
effort = items * (1 + rework) / rate
for who, people in (("In-house, 3 staff on 2 stations", 3), ("Vendor, 6 staff on 6 stations", 6)):
    print(f"{who}: about {effort / (people * 6.5):4.1f} working days")
Output
In-house cost per item 0.393
In-house total 23,944   Vendor total 29,860
Break-even volume 19,894 items; above it, in-house is cheaper
In-house, 3 staff on 2 stations: about 18.2 working days
Vendor, 6 staff on 6 stations: about  9.1 working days

In-house tagging is cheaper by about $6,000 for 38,000 items, because the vendor's unit price is higher than the library's labour cost per item; the vendor's lower set-up cost wins only below about 20,000 items. The vendor would finish in about 9 working days instead of 18, because it brings more encoding stations. PMP-130 found that the tagging activity has 35 days of total float, so the extra speed is not needed for the schedule, and in-house tagging builds staff familiarity with the system they will use every day. The team recommends making, with one condition: if float falls below 15 days, for example because of further permit delays, the vendor quote remains available as a contingency response. Make-or-buy decisions are rarely about cost alone, and the analysis should say which other factors tipped the balance.

The app is a different case. The library has no app developers and building that capability would take longer than the project allows, so the team buys development services. The library keeps ownership of the source code and the right to use another supplier later, which the contract must state explicitly.

Statements of work and terms of reference

Each procurement needs a procurement statement of work (SOW) describing the item to be bought in enough detail for prospective sellers to decide whether they can provide it and to price it. It is drawn from the project scope baseline and covers only the part of scope included in the contract. For services, a terms of reference document plays the same role, describing tasks, deliverables, standards, reporting and acceptance.

Types of statement of work.
SOW typeDescribesCompass example
Design (technical)Exactly what to build, with specifications and drawingsFit-out drawings and specifications from the architect
FunctionalThe purpose and required functions, leaving design to the sellerKiosks must check out items, print or email receipts and integrate with the library system
PerformanceMeasurable outputs or results requiredGates must detect 99.5 % of tagged items carried through at walking speed with no more than one false alarm a day

A clear SOW reduces disputes. Vague phrases such as "industry standard" or "fully functional" invite arguments; measurable acceptance criteria, linked to the quality metrics from lesson 1, prevent them. The Eastgate kiosk SOW also includes the lesson from the central library pilot: the firmware version must be stated, updates must be approved by the library before installation, and the seller must test updates against the library's system first.

Solicitation documents and source selection criteria

Bid documents invite sellers to respond. Their names vary by organization and country, but three types appear in exam questions. A request for information (RFI) gathers information about the market and possible solutions before requirements are firm. A request for quotation (RFQ) asks for prices for well-defined goods or services, where the decision is mainly about price. A request for proposal (RFP) asks for proposed solutions and prices when the buyer needs to compare approaches, capability and value, not just price. Public bodies may also use an invitation to tender, invitation for bid or call for tenders for priced bids on fully designed work.

Source selection criteria tell sellers how proposals will be evaluated. They are published in the bid documents so that evaluation is fair and sellers can respond to what matters. Typical criteria include understanding of need, technical approach, management approach and staffing, past performance and references, financial capacity, warranty and support, life-cycle cost and, increasingly, accessibility, security and sustainability. Mandatory requirements screen out non-compliant proposals before scoring. An independent cost estimate, prepared by the buyer or a consultant before bids arrive, provides a benchmark: if bids differ widely from it, the SOW may be unclear or the market misunderstood.

Public bodies in Canada must follow procurement rules set by legislation, trade agreements and their own policies. A municipal library typically follows provincial requirements and the municipality's purchasing bylaw or policy. Above certain dollar thresholds, the Canadian Free Trade Agreement (CFTA) requires open, non-discriminatory competition for the broader public sector, including municipalities, and international agreements such as CETA and the WTO Agreement on Government Procurement may also apply at higher thresholds. Thresholds are adjusted periodically, so procurement staff check current values. At the federal level, the Buy Canadian Policy that took effect on 16 December 2025 favours Canadian suppliers and materials in some large federal procurements; it applies to federal departments rather than to a municipal library, though some provinces have adopted their own buy-local measures. Disputes over federal procurements can go to the Canadian International Trade Tribunal; most municipal procurements are challenged in the courts.

Whatever the jurisdiction, public procurement emphasizes fairness, transparency, value for money and accountability. The practical consequences for a project manager are lead time (formal competitions take weeks or months), limits on talking to bidders outside formal channels, a duty to evaluate strictly against published criteria and a record of decisions that can withstand challenge. Private organizations have more freedom but usually still have purchasing policies and approval limits.

Ethics in procurement

Procurement is where conflicts of interest and unfair preference for particular suppliers most often appear. A project manager should disclose any personal relationship with a bidder, refuse gifts and hospitality beyond what policy allows, treat all bidders equally (sharing the same information at the same time, for example through a bidder conference and written addenda), keep bid information confidential and never steer a contract to a preferred supplier by writing the SOW around one product. PMP-121 covered PMI's Code of Ethics and Professional Conduct; procurement is where its standards of fairness and honesty are tested most directly. On Project Compass, a board member's relative works for one of the kiosk vendors; the board member declared the interest and did not take part in the decision, and the declaration was recorded.

Procurement for adaptive work

Buying adaptive work is harder, because the scope will evolve. Contracts for the app team describe outcomes, team composition, ways of working and the product owner's role, rather than a fixed feature list. Common structures include time and materials with a not-to-exceed ceiling, a fixed price per sprint or release with scope chosen sprint by sprint, and clauses allowing either party to stop after any release with notice, so that the buyer can walk away if value is not being delivered. PMP-140 discusses agile contracting further. Project Compass chose time and materials with a ceiling of $210,000, matching the app's budget, and a right to end the contract after each release.

Worked problem

Make or buy with a capacity constraint

A different project needs 2,000 hours of data migration work. Doing it in-house costs $55 per hour plus $12,000 for training and tools; a vendor offers $68 per hour with no set-up cost. The in-house team can start only in three months, and the vendor can start next week. Which option is cheaper, and what else should be considered?

Show solution
  1. In-house: 12,000 + 55 × 2,000 = $122,000.
  2. Vendor: 68 × 2,000 = $136,000.
  3. In-house is $14,000 cheaper on direct cost; break-even is 12,000 / (68 − 55) ≈ 923 hours.
  4. The three-month delay matters if migration is on or near the critical path; the cost of delay may outweigh the saving. Other factors include data confidentiality, knowledge retention and the risk of each option.

Answer: In-house is cheaper by $14,000, but the schedule impact, confidentiality and capability considerations must be weighed before deciding.

Common mistakes

  • MistakeDeciding make-or-buy on unit price alone.

    InsteadCompare total cost, including set-up and contract management, and weigh schedule, capability, control and risk.

  • MistakeWriting an SOW with vague terms such as "high quality" or "industry standard".

    InsteadUse measurable requirements and acceptance criteria.

  • MistakeUsing an RFQ when the buyer needs to compare different solutions.

    InsteadUse an RFP when approach and capability matter; an RFQ when price is the main differentiator.

  • MistakeGiving one bidder extra information informally.

    InsteadShare information with all bidders equally, through formal channels.

  • MistakeAssuming the project manager can sign or change contracts.

    InsteadWork through the person with contracting authority.

Summary and key terms

  • Procurement acquires products and services from outside the team through legally binding agreements.
  • The procurement management plan sets how procurement is done; the procurement strategy sets delivery method, payment type and phases for each purchase.
  • Make-or-buy compares total costs and weighs schedule, capability, control, confidentiality and risk.
  • SOWs can be design, functional or performance based; terms of reference serve services.
  • RFI gathers information, RFQ seeks prices, RFP seeks solutions and prices.
  • Source selection criteria are published in advance; independent estimates provide a benchmark.
  • Public procurement is shaped by law, trade agreements and funding conditions; ethics requires fairness and disclosure.
Procurement management plan
The component of the project management plan that describes how goods and services will be acquired.
Procurement strategy
The choice of delivery method, contract payment type and procurement phases for a purchase.
Make-or-buy analysis
Evaluation of whether to produce work internally or acquire it externally.
Procurement statement of work
A description of the item to be procured in enough detail for sellers to respond.
Terms of reference
A statement of work for services, describing tasks, deliverables and standards.
Request for proposal
A bid document seeking proposed solutions and prices.
Request for quotation
A bid document seeking prices for well-defined items.
Source selection criteria
The published criteria used to evaluate seller proposals.
Independent cost estimate
A buyer's own estimate of a reasonable price, used to assess bids.

Practice problems

Work each problem on paper first, then reveal the answer to check.

  1. Which bid document is best when the buyer wants sellers to propose different solutions?

    Show answer

    A request for proposal.

  2. What type of SOW describes measurable results rather than design?

    Show answer

    A performance SOW.

  3. Name three factors other than cost in a make-or-buy decision.

    Show answer

    Schedule, capability or capacity, control, confidentiality, strategic value, risk.

  4. Why publish source selection criteria in the bid documents?

    Show answer

    For fairness and so sellers can respond to what matters.

  5. What is an independent cost estimate used for?

    Show answer

    As a benchmark to assess whether bids are reasonable.

  6. Who normally signs contracts?

    Show answer

    A person with contracting authority, often in procurement.

  7. In-house cost is $10,000 + $40 per unit; buying costs $50 per unit. What is the break-even quantity?

    Show answer

    1,000 units.

  8. What does a request for information do?

    Show answer

    Gathers market information before requirements are firm.

  9. What should a project manager do if a relative works for a bidder?

    Show answer

    Disclose the interest and follow policy, usually stepping back from the decision.

  10. Name one contract structure suited to agile work.

    Show answer

    Time and materials with a ceiling, or fixed price per sprint or release.